Issued by
Department of the Army Corps of Engineers Engineering District Huntington

About this file

This document is an abstract of bids for solicitation number W91237-20-B-0002 from the Department of the Army Corps of Engineers Engineering District Huntington. The solicitation is for the construction of the Town of Martin Phase II Redevelopment Site and involves placement of fill from the Mayo Hollow site to raise the area between KY-1428 and the base of the mountain above flood risk, raising existing roads to accommodate the site and maintain traffic, and adjusting or constructing utilities. Four bids were received by the June 11, 2020 deadline ranging from $6.856 million to $8.334 million for the base contract and $19.109 million to $32.764 million for all options. The government estimate was $6.330 million for the base and $25.073 million in total. The apparent low bidder is Aspen Construction.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM NO.

ABSTRACT OF OFFERS

SOLICITATION NO.

ISSUING OFFICE

NO. NAME OF OFFEROR

ACCEP-

TANCE

TIME*

(Days)

BUSI-

NESS

SIZE

L S

SUPPLIES OR SERVICES (General Description)

OPENING DATE PAGE OF PAGES

QUANTITY

UNIT

DELIV-

ERY

TIME**

F.O.B.

POINT REMARKS

* Indicate by an X a 60-day acceptance.

** Indicate by an X if offer conforms to delivery time specified in solicitation.

I CERTIFY THAT I HAVE OPENED, READ

AND RECORDED ON THIS ABSTRACT

(AND CONTINUATION SHEETS, IF ANY)

ALL OFFERS RECEIVED IN RESPONSE TO

THE SOLICITATION.

TYPED NAME AND TITLE

SIGNATURE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is usable

STANDARD FORM 1409 (REV. 9-88)

Prescribed by GSA-FAR (48 CFR) 53.214

W9123720B0002

Base

Contracting Division 502 Eighth Street Huntington WV 25701

Town of Martin Phase II Redevelopment Site, Martin, KY

06/10/2020

06/11/2020

Bush & Burchett, Inc.

Aspen Construction

Semper-Tek Hinkle JV

ARS Aleut Construction

Error in Opt 3, new total bid amount $30,615,520.07

Bethany D. Clinton, Contracting Officer

8,334,252.12

6,856,723.58

6,801,277.17

Options

22,348,416.80

19,109,030.62

25,908,086.81

20,081,677.45

Total

30,264,063.07

27,443,282.74

32,764,810.39

26,882,954.62

7,915,646.27

Government Estimate $6,330,141.12 $25,073,437.46 $31,403,578.58