This solicitation is for renovation work at the Welcome Center building at the Defense Supply Center in Richmond, Virginia. Key details include:
-
Renovating the visitor center area within the building, including replacing casework and workstations. Enlarging the lobby, vestibule, and customer service desk workspaces. Adding a break room, private office, and police office.
-
Updating lighting to LED fixtures with occupancy sensors. Modifying fire protection and alarm systems for the new layout. Repairing and reconfiguring telecommunications and electrical systems to meet standards and the new layout.
-
Updating the current boiler system and HVAC components in the visitor center and mailroom. Restripping the parking lot to maximize capacity.
-
The bid submission due date is not provided. The soliciting agency is the Department of the Army Corps of Engineers Engineering District Norfolk.
-
The work involves architectural, mechanical, electrical, civil, fire protection, and telecommunications disciplines.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| IFB Abstract of Offerors Welcome Center.pdf | ||
| Welcome Center Amend 0005.pdf | ||
| A.01.13 Welcome Center RTA Spec Section 01 45 05.50 Revised.pdf | ||
| W9123622B2009 Amendment 0004.pdf | ||
| 22B2009 Amendment 0003.pdf | ||
| W9123622B2009 Amendment 0002.pdf | ||
| Welcome Center Site Visit SignIn Sheet (2).pdf | ||
| 22B2009 Amend 1.pdf | ||
| A.01.13 Welcome Center RTA Submittal Drawings.pdf | ||
| A.01.13 Welcome Center RTA Spec Section 09 90 00 Revised.pdf | ||
| H.01.04 North Gate RTA Specs VOL 2.pdf | ||
| H.01.01 North Gate RTA Drawings.pdf | ||
| H.01.04 North Gate RTA Specs VOL 1.pdf | ||
| W9123622B2009.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Specifications
Repair Building 210 Welcome Center, DSCR Richmond, VA
Project #:W9123619F0095
22 October 2021
Prepared by Stantec Consulting Services Inc.
Raleigh, North Carolina
With consultants EDI Consultants Raleigh, North Carolina
JMPPE, Fire Protection Engineer Martinez, Georgia
AME Consulting Engineers, PC Charlotte, North Carolina
Prepared for U.S. Army Corps of Engineers Norfolk District
READY TO ADVERTISE
ARCHITECTURAL MECHANICAL CIVIL
FIRE PROTECTION TELECOMMUNICATIONS ELECTRICAL
10/22/2021
Repair Building 210 Welcome Center, DSCR, VA W9123617D0003
PN 2016.01628 W9123619F0095
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00.05 50 12/18 SUMMARY OF WORK FOR NORFOLK DISTRICT
PROJECTS
01 31 19.00 50 12/18 PROJECT MEETINGS
01 32 01.00 10 02/15 PROJECT SCHEDULE
01 33 00 08/18 SUBMITTAL PROCEDURES
01 35 26 11/15 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 11/14 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 11/16 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 45 04.00 50 12/18 CONTRACTOR QUALITY CONTROL
01 50 00 05/18 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 11/15 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 01/07 CONSTRUCTION AND DEMOLITION WASTE
MANAGEMENT
01 78 00 08/11 CLOSEOUT SUBMITTALS
01 78 23 08/15 OPERATION AND MAINTENANCE DATA
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 05/10 DEMOLITION
DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES
06 20 00 08/16 FINISH CARPENTRY
06 41 16.00 10 08/10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
06 61 16 08/10 SOLID SURFACING FABRICATIONS
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 84 00 05/10 FIRESTOPPING
07 92 00 08/16 JOINT SEALANTS
DI VI SI ON 08 - OPENI NGS
08 11 13 02/10 STEEL DOOR FRAMES
08 14 00 08/16 WOOD DOORS
08 31 00 05/17 ACCESS DOORS AND PANELS
08 34 02 08/09 BULLET-RESISTANT COMPONENTS
08 41 13 08/18 ALUMINUM-FRAMED ENTRANCES AND
STOREFRONTS
08 71 00 02/16 DOOR HARDWARE
08 81 00 05/19 GLAZING
DI VI SI ON 09 - FI NI SHES
09 22 00 02/10 SUPPORTS FOR GYPSUM BOARD
09 29 00 08/16 GYPSUM BOARD
09 30 10 08/17 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 08/17 ACOUSTICAL CEILINGS
09 65 00 08/10 RESILIENT FLOORING
09 68 00 11/17 CARPETING
09 72 00 08/17 WALLCOVERINGS
09 90 00 05/11 PAINTS AND COATINGS
PROJECT TABLE OF CONTENTS Page 1
DI VI SI ON 10 - SPECI ALTI ES
10 14 00.20 08/17 INTERIOR SIGNAGE
10 28 13 08/17 TOILET ACCESSORIES
10 44 16 05/15 FIRE EXTINGUISHERS
DI VI SI ON 11 - EQUI PMENT
11 31 13 08/17 ELECTRIC KITCHEN EQUIPMENT
DI VI SI ON 21 - FI RE SUPPRESSI ON
21 13 13.00 10 05/09 WET PIPE SPRINKLER SYSTEM, FIRE
PROTECTION
DI VI SI ON 22 - PLUMBI NG
22 00 00 11/15 PLUMBING, GENERAL PURPOSE
22 07 19.00 40 08/16 PLUMBING PIPING INSULATION
DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)
23 00 00 08/18 AIR SUPPLY, DISTRIBUTION, VENTILATION,
AND EXHAUST SYSTEMS
23 05 15 02/14 COMMON PIPING FOR HVAC
23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 02/13 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 09 00 02/19 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.01 02/19 LONWORKS DIRECT DIGITAL CONTROL FOR
HVAC AND OTHER BUILDING CONTROL SYSTEMS
23 11 25 11/08 FACILITY GAS PIPING
23 21 23 08/17 HYDRONIC PUMPS
23 23 00 10/07 REFRIGERANT PIPING
23 25 00 11/08 CHEMICAL TREATMENT OF WATER FOR
MECHANICAL SYSTEMS
23 52 00 04/08 HEATING BOILERS
DI VI SI ON 26 - ELECTRI CAL
26 00 00.00 20 07/06 BASIC ELECTRICAL MATERIALS AND METHODS
26 20 00 02/14 INTERIOR DISTRIBUTION SYSTEM
26 51 00 05/16 INTERIOR LIGHTING
DI VI SI ON 27 - COMMUNI CATI ONS
27 05 14.00 10 04/06 CABLE TELEVISION PREMISES DISTRIBUTION
SYSTEM
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY
28 08 10 05/16 ELECTRONIC SECURITY SYSTEM ACCEPTANCE
TESTING
PROJECT TABLE OF CONTENTS Page 2
28 10 05 05/16 ELECTRONIC SECURITY SYSTEMS (ESS)
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 3
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00.05 50
SUMMARY OF WORK FOR NORFOLK DISTRICT PROJECTS
12/18
PART 1 GENERAL
1.1 DEFINITIONS
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.2 Location
1.3 PERSONNEL RESTRICTIONS
1.3.1 Security Requirements Defense Supply Center Richmond (DSCR)
1.4 TRANSPORTATION FACILITIES
1.4.1 Use of Roads
1.4.2 Road Restrictions
1.4.3 Cleated Vehicles
1.5 SPECIAL CONTRACTOR REQUIREMENTS
1.5.1 Coordination in Work Areas
1.5.1.1 Occupied Work Area
1.5.1.2 Maintenance of Utilities
1.5.1.3 Hours of Work
1.5.1.4 Existing Utility Location
1.5.1.5 Digging Permits
1.5.2 Project Phasing and Performance Period
1.5.3 Structural Drawings Dimensions
1.6 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.6.1 Schedule
1.6.2 Records
1.6.3 Impacted Days
1.7 COOPERATION WITH USING AGENCY AND OTHER CONTRACTORS
1.8 OCCUPANCY OF PREMISES
1.9 EXISTING WORK
1.10 LOCATION OF UNDERGROUND UTILITIES
1.11 INTERRUPTIONS OF UTILITIES AND BUILDING SYSTEMS
1.11.1 Approval
1.11.2 Request
1.11.3 Service Interruption
1.11.4 Timely Disconnections
1.11.5 Utilities Operation
1.11.6 Gas
1.12 SALVAGE MATERIAL AND EQUIPMENT
1.13 PHYSICAL DATA
1.14 HISTORICAL AND ARCHAEOLOGICAL FINDS
1.15 SITE CONTAMINATION
1.15.1 Contamination Removal
1.15.1.1 Compliance Requirements
1.15.1.1.1 Requirements
1.16 WORK IN QUARANTINED AREA
1.17 EQUIPMENT-IN-PLACE LIST
1.18 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
1.18.1 Allowable Costs
1.18.2 Rental Costs
SECTION 01 11 00.05 50 Page 1
1.18.3 Equipment Costs
1.19 SUBCONTRACTS AND WORK COORDINATION
1.20 CONSTRUCTION MANPOWER AND EQUIPMENT REPORT
1.21 PURCHASE ORDERS
1.22 PROFIT
1.22.1 Weighted Guidelines
1.22.2 Value
1.22.2.1 Degree of Risk
1.22.2.2 Relative Difficulty of Work
1.22.2.3 Size of Job
1.22.2.4 Periods of Performance
1.22.2.5 Contractor's Investment
1.22.2.6 Assistance by Government
1.22.2.7 Subcontracting
1.23 BLASTING
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00.05 50 Page 2
SECTION 01 11 00.05 50
SUMMARY OF WORK FOR NORFOLK DISTRICT PROJECTS
12/18
PART 1 GENERAL
1.1 DEFINITIONS
a. Facility: The Facility is:
Building 210
D.S.C.R., Richmond, VA
CO: Contracting Officer or his authorized representative.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
This project includes the repair and renovation of the Visitor Center within Building 210 at the North Entrance to the Defense Supply Center in Richmond Virginia. The work includes kiosk services, a multipurpose group check-in, enlarged lobby, repaired vestibule, four enlarged workspaces at the customer service desk, an enlarged private workstation area, break room, latrines, a private office and a police office. This will be accomplished by converting a portion of the mailroom into additional Visitor Center area. Existing casework and workstations in the Visitor Center will be replaced and the existing workstations in the Mail Room will be relocated or removed based on current user needs.
The existing building lighting will be updated to LED fixtures, and will include occupancy/vacancy sensors for sustainable control. The fire protection and alarm systems shall be modified and reconfigured to accommodate the new layout. Telecommunications and electrical systems will be repaired and reconfigured to meet the new layout and meet base standards. The current boiler system and the HVAC components within the visitor center and mailroom will be updated. Finally, the existing parking lot will be restriped to maximize the space for capacity.
1.2.2 Location
The work shall be located at the Building 210 at the Defense Supply Center Richmond, Virginia, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.3 PERSONNEL RESTRICTIONS
Personnel are limited to the immediate site areas and shall not enter buildings or facilities not involved in the work. All employees of the Contractor will be subject to all rules and regulations of the Facility which pertain to personnel. The Contractor shall erect fences and signs as specified and be responsible for the restrictions of all personnel. The Contractor's plans for restricting personnel access to the project site shall be submitted for approval as a part of the Safety Plan (Accident Prevention Plan). Facility access shall be restricted. Contractor shall
SECTION 01 11 00.05 50 Page 3 comply with current security requirements. All vehicles shall be registered with the military police.
1.3.1 Security Requirements Defense Supply Center Richmond (DSCR)
No employee or representative of the Contractor will be admitted to the work site unless he furnishes satisfactory proof that he is a citizen of the United States or has proper identification to work in the United States.
a. Personnel Information - All authorized non-military personnel utilizing the base are required to have in their possession at all times a Base Visitor Pass or Base Identification. This pass is issued by the DSCR Visitors Center located at the North Gate. Proof of identity is required to obtain a visitor pass or Base Identification.
The Visitors Center is open Monday through Friday except Federal holidays from 7:00 a.m. to 3:00 p.m. A minimum of 14 working days prior to start of work, the Contractor shall furnish to the Defense Supply Center Richmond (DSCR), Richmond, VA, Security Department, via the Contracting Officer, the following information for Contractor and subcontractor personnel required to enter the Station:
(1) Contract Number
(2) Beginning Date (Month, Day, Year)
(3) Ending Date (Month, Day, Year)
(4) Name of the company (The Prime Contractor and Sub Contractor)
(5) Full Name of the employee (First, Middle and Last)
(6) Address of Current (Employee 1 s) Residence (Bldg#, Street, City, State, Zip or City and Country)
(7) Social Security Number (SS#)
(8) US Citizen (Yes / No)
(9) Gender (Male/Female)
(10) Race (American Indian or Alaska Native, Asian, Black or African American, Native Hawaiian or Other Pacific Islander, and White)
(11) Date of Birth (Month, Day, Year)
(12) Place of Birth (City, State, Country)
b. The DSCR Security Department will run a criminal history check on Contractor employees as a condition of employment. Official proof of identity or naturalization papers may be required, which will be returned once entered into the security computer system. Based on the results of the criminal history check, the Security Officer will or will not grant entry to the Station. If entry is denied, the Contractor will be immediately notified. DSCR Security may require updating or rechecking criminal history based on the duration of the contract. NOTE: DSCR Security has been denying entry to persons whose police record checks are positive. Failure to obtain entry approval shall not affect the contract price or time of completion.
SECTION 01 11 00.05 50 Page 4
c. Proof of Identity -Official identification can consist of copies of birth certificates, valid federal identification, valid state identification, or valid naturalization papers. Examples of official identification are valid state issued driver's license, military ID card, military dependent ID card, green card, etc. Expired identification is not valid.
d. Base Entry Passes - Contractor base entry passes will be valid for each entry aboard DSCR from 6:00 a.m. to 6:00 p.m., Monday through Friday except for Federal holidays, unless prior arrangements have been made with the Contracting Officer, and DSCR Security has been notified. The passes are the property of the base and are to be returned to Visitors Control at the North Gate upon completion of the contract or termination of employment. Replacement passes must be requested in writing and be accomplished by written authorization from the Contracting Officer. Compliance with this requirement is mandatory and certification thereof to the Contracting Officer is required prior to submitting final invoices. Failure to return badges will hold up Contractor's final payment.
e. Contractor Responsibility for Employees - The Contractor is responsible for employees under his employment. Ensure that employees are familiar with and obey station traffic, safety, and security regulations.
f. Unofficial photography, cameras, or photographs are prohibited ort DSCR property. When official photographs are required, submit a written approval request containing specific justification and details to the Contracting Officer 5 days prior.
g. Firearms, Weapons, Alcoholic Beverages, Illegal Drugs, and Contraband are prohibited on DSCR property. Violators may be prosecuted. State issued/authorized concealed weapons permits are not valid on Federal (DSCR) property.
h. Motor Vehicle Operation - Ingress and egress of personnel will be subject to the DSCR security regulations.
(1) All personnel must be made aware of the base speed limits:
25 mph (unless otherwise ·posted)
Speed limits are enforced and violators will be ticketed. DSCR traffic violations are processed through the federal court system.
(2) Seat belts are MANDATORY.
(3) Parking is in designated areas only, between two white lines.
No parking is permitted in fire lanes, on seeded areas, in reserved parking slots, or assigned handicapped parking. Any equipment or vehicle that does not fit within a standard parking space must contact the Contracting Officer to determine a designated area for parking such equipment or vehicle.
Contractor employees shall park vehicles (Commercial or Private) in areas designated by the Contracting Officer. This area may or may not necessarily be within reasonable walking distance of the construction site. The contractor shall provide transportation
SECTION 01 11 00.05 50 Page 5 between the parking area and the construction site. Contractor employee parking shall not interfere with existing and established parking requirements of the Base.
(4) Traffic accidents should be reported immediately to the DSCR Emergency Dispatch by calling 9ll or (804) 279-4888.
(5) All personnel entering the installation are subject to random vehicle inspections/searches at any time while on the base. The purpose of these inspections is to detect the theft of Government and private property, firearms, weapons, alcoholic beverages, illegal drugs, or contraband.
(6) Information required for Vehicle Passes- Driver 1 s are required to bring the vehicle, contract number, vehicle registration, copy of vehicle insurance policy, valid state inspection documentation, and valid driver's license to the Visitor Control Center at the North Gate. Vehicles without passes will not be allowed entry to base.
1. Commercially Owned Vehicles - All commercial Vehicles are to clearly display the authorized company name or logo on both sides of the vehicle.
2. Privately Owned Vehicles - No Privately Owned Vehicles will be allowed within the Defense Distribution Depot, Richmond, VA (DDRV) area or any other secure/controlled industrial area located on
DSCR.
3. Rental Vehicles - The driver is to show all paper work from the rental company showing that the driver is authorized to operate the subject vehicle. Rental vehicles will not be allowed in secure/controlled industrial areas located on DSCR unless the rental vehicle clearly displays the authorized operating company name or logo on both sides of the vehicle.
i. Access to Restricted Areas - Base entry passes allow access to designated areas on the installation only. Entries into secure/controlled industrial areas are prohibited unless the contract requires it.
j. Current Information - Contractors will be responsible for keeping the vehicle and employee lists current, and for securing and returning identification cards belonging to terminated employees to the DSCR Security Department.
k. Providing Information to Subcontractors - Prime Contractors shall be responsible for ensuring that subcontractors receive security information. Failure to comply with the specified requirements will result in prime contractors and subcontractors being denied access to the construction site.
1. DSCR is not responsible for job site security. Removal of material from job-site and base are subject to security checks. Contractor is to notify DSCR security of any special measures (watchmen, alarm, etc), security concerns, security problems, or unusual activities within the job site.
m. Failure to attain entry approval will not affect the contract price
SECTION 01 11 00.05 50 Page 6 or time of completion.
1.4 TRANSPORTATION FACILITIES
The Facility is served by an all weather surfaced road network. Road(s) within the Facility proposed to be used by the Contractor shall be subject to prior approval of the Facility authorities and such roads, if used, shall be maintained throughout construction and shall be restored to as good condition as existed prior to their use. The Contractor shall also construct, subject to approval, such temporary haul roads and bridges as may be necessary for conducting his work. Any such temporary construction shall be removed and the affected area restored to its original condition.
All costs for the use of existing transportation facilities, for the construction of temporary facilities, and for maintenance, repair, removal and restoration shall be borne by the Contractor.
1.4.1 Use of Roads
Hard-surfaced roads from major and primary municipal roads serve the Facility. The movement of all vehicles within the Facility shall be confined to the roads designated and shall comply with traffic regulations within the Facility. The Contractor shall keep all roads clear of all obstructions and free of mud and other foreign materials resulting from operations. The Contractor's vehicles shall at no time follow a vehicle closer than 50 feet, and all vehicles shall pull off the road and come to a complete stop when meeting emergency vehicles, or vehicles with flashing lights. Facility speed limits and traffic controls shall be observed.
1.4.2 Road Restrictions
The movement of all vehicles within the Facility shall be confined to the roads designated and shall comply with traffic regulations within the Facility. Other roads may be used only with the approval Of the CO.
1.4.3 Cleated Vehicles
Cleated vehicles shall not be moved over surfaced roads except at the immediate site of the area where they are to be used.
1.5 SPECIAL CONTRACTOR REQUIREMENTS
1.5.1 Coordination in Work Areas
1.5.1.1 Occupied Work Area
The area where work is to be accomplished will be occupied during the work. Activities of the occupants of the scheduled work area shall not be interrupted or hampered in any way without prior written approval of the Contracting Officer. However, it is understood that it will be necessary for temporary relocations at times to accommodate the work.
1.5.1.2 Maintenance of Utilities
Any active utilities, including but not limited to electricity, gas, water, sewer, heating, air conditioning, or any like service, that will require interruption or replacement in any occupied area affected as a result of the Contractors scheduled work activities, shall be temporarily provided by the Contractor at his own expense until the affected service is fully and permanently restored. All temporary method(s) of service replacement the
SECTION 01 11 00.05 50 Page 7
Contractor proposes for use on this contract shall be approved by the CO prior to commencing the work.
1.5.1.3 Hours of Work
The normal work hours for construction shall be from 8:00 a.m. to 4:30 p.m.
Monday through Friday of each week. Any request to change these hours shall be made in writing to the Contracting Officer at least two calendar days prior to the desired day on which the change is to go into effect.
The changed hours shall not go into effect until written permission has been received from the Contracting Officer.
1.5.1.4 Existing Utility Location
Existing utilities must be located before doing any digging work on Facility. The Contractor shall be responsible to contact USACE and DSCR through DSCR Chief of Utilities, obtain all necessary existing utility locations, which may be necessary to accomplish his work, and mark any utility lines in the immediate vicinity of his work. It shall be the responsibility of the Contractor to contact USACE and DSCR through DSCR Chief of Utilities for locating commercial utilities 48 hours prior to digging operations. The Contractor is responsible for maintaining marked utilities. The Contractor shall be responsible for maintaining utility markings.
1.5.1.5 Digging Permits
Contractor is responsible for obtaining all digging permits, including associated locating and marking services, in accordance with installation and local requirements, at no additional cost to the Government.
"Clearance Permits for Digging', must be obtained before doing any work on Facility. The Contractor shall be responsible to obtain all necessary digging permits and pay costs associated with the permit,which may be necessary to accomplish his work.
1.5.2 Project Phasing and Performance Period
The Contractor shall complete the work within the duration specified in Section 00800 11 "Contract Requirements 11".
1.5.3 Structural Drawings Dimensions
The building layout, including both horizontal and vertical dimensions, is shown on the Architectural sheets contained in the contract drawings.
The Contractor shall use the dimensions from the Architectural sheets to obtain dimensions for foundation layout and structural members as necessary to prepare all shop drawings and fabricate structural members. There may be some instances where the Contractor shall have to adjust actual dimensions to the submitted items that he will use, to finalize the location of a structural member. Any such adjustments shall be clearly identified on the submitted shop drawings for Government review.
1.6 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
SECTION 01 11 00.05 50 Page 8
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
1.6.1 Schedule
The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS
BASED ON (5) DAY WORK WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
DSCR 10 9 9 6 8 7 8 7 6 5 7 9
1.6.2 Records
Upon acknowledgement of the Notice to Proceed and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.
1.6.3 Impacted Days
The number of actual adverse weather days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically for the first to the last day in each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in the schedule of monthly anticipated adverse weather delays, above, the contracting officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Contract Clauses entitled "Default (Fixed Price Construction)".
1.7 COOPERATION WITH USING AGENCY AND OTHER CONTRACTORS
During the period of this contract, other contracts may be in force for the construction of other features of work on or adjacent to the site of work being accomplished under this contract. It shall be the responsibility of the Contractor on this contract to be fully informed of the extent of the limits of work to be performed by other Contractors. Should there be any conflict between these limits, it shall be brought to the attention of the Contracting Officer(CO)and the CO's decision shall be final. Also, prior to completion of work under this contract, members of the Using Agency may be performing work or occupying facilities on or adjacent to the area. The Contractor shall arrange his plant and shall schedule and perform this work
SECTION 01 11 00.05 50 Page 9 so as to effectively cooperate with all other Contractors and Government agencies.
1.8 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.
Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.9 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.10 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation. Notify the Contracting Officer at least 48 hours prior to starting excavation work.
1.11 INTERRUPTIONS OF UTILITIES AND BUILDING SYSTEMS
1.11.1 Approval
Utilities and Building systems shall not be interrupted by the Contractor without written approval of the CO.
1.11.2 Request
Request for permission to shut down services shall be submitted in writing to the CO not less than 15 calendar days prior to date of proposed interruption. The request shall give the following information:
a. Nature of Utility or service (Gas, L.P. or H.P., Water, Elec. or HVAC, Communications, Fire Alarm Systems, Security Systems).
b. Nature and extent of impact of service interruption.
c. Hours and date of shutoff.
d. Estimated length of time service will be interrupted.
1.11.3 Service Interruption
Services shall not be shut off until receipt of approval of the proposed hours and date from the Contracting Officer.
SECTION 01 11 00.05 50 Page 10
1.11.4 Timely Disconnections
Shutoffs which will cause interruption of Government work operations as determined by the Contracting Officer shall be accomplished during regular non-work hours or non-work days of the Using Agency without any additional cost to the Government.
1.11.5 Utilities Operation
Operation of valves on water mains will be by Government personnel. Where shutoff of water lines interrupts service to the fire hydrants or fire sprinkler systems, the Facility Fire Department shall be notified by the Contractor in writing 72 hours prior to the proposed interruption. The Contractor shall arrange his operations and have sufficient material and personnel available to complete the work without undue delay and shall restore service without delay in event of emergency.
1.11.6 Gas
Flow in gas mains which have been shut off shall not be restored until the Government inspector has determined that all items serviced by the gas lines have been shut off.
1.12 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged shall remain the property of the Government.
The salvaged property shall be segregated, itemized, delivered, and off-loaded at the Government designated storage area located within 2 miles of the construction site.
Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.
1.13 PHYSICAL DATA
The physical conditions indicated on the drawings and in the specifications are the result of site visits.
1.14 HISTORICAL AND ARCHAEOLOGICAL FINDS
Federal legislation provides for the protection, preservation, and collection of scientific, prehistoric, historical, and archaeological data, including relics and specimens which might otherwise be lost due to alteration of the terrain or building features as a result of any Federal construction project. Should the Contractor, or any of the Contractor 1 s employees, or parties operating or associated with the Contractor, in the performance of this contract discover evidence of possible scientific, prehistoric, historical, or archaeological data, the Contractor shall immediately cease work at that location, avoid further disturbance, and notify the Contracting Officer, giving the location and nature of the findings. The Contractor shall forward written confirmation to the Contracting Officer as directed. The Contractor shall exercise care so as not to disturb or damage artifacts or fossils uncovered during excavation operations, and shall provide such cooperation and assistance as may be
SECTION 01 11 00.05 50 Page 11 necessary to preserve the findings for removal or other disposition. Any person who, without permission, injures, destroys, excavates, appropriates, or removes any historical or prehistoric artifact, object of antiquity, or archaeological resource on the public lands of the United States is subject to arrest and penalty of law. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance or changes in the work, or both. If such delays or changes are ordered, an equitable adjustment will be made in the contract in accordance with the applicable clauses of the contract.
1.15 SITE CONTAMINATION
This site is designated a Category II site and is defined as a current or former industrial site or other hazard producing activity site which is perceived to be a clean location; however, due to former industrial or other activities within or near the site, it has the potential for contamination.
1.15.1 Contamination Removal
In the event that contamination beyond that shown or specified is encountered, the Contracting Officer shall be advised immediately. The contamination shall be removed as directed and replaced with satisfactory material. Payment therefore will be made in conformance with the CHANGES clause of the CONTRACT CLAUSES.
1.15.1.1 Compliance Requirements
The Contractor shall comply with applicable Federal, state and local laws, codes, ordinances and regulations (including the obtaining of licenses and permits) in connection with any hazardous material, substance or waste.
1.15.1.1.1 Requirements
The requirements of this clause and any act or failure to act by the Government shall not relieve the Contractor of any responsibility or liability for the safety of Government, Contractor or subcontractor personnel or property.
1.16 WORK IN QUARANTINED AREA
The work called for by this contract involves activities in counties quarantined by the Department of Agriculture to prevent the spread of certain plant pests which may be present in the soil. The Contractor agrees that all construction equipment and tools to be moved from such counties shall be thoroughly cleaned of all soil residues at the construction site with water under pressure and that hand tools shall be thoroughly cleaned by brushing or other means to remove all soil. In addition, if this contract involves the identification, shipping, storage, testing, or disposal of soils from such a quarantined area, the Contractor agrees to comply with the provisions of ER 1110-1-5 and attachments, a copy of which will be made available by the Contracting Officer upon request. The Contractor agrees to assure compliance with this obligation by all subcontractors.
1.17 EQUIPMENT-IN-PLACE LIST
The Contractor shall maintain a list of equipment installed under the terms of the contract. Forms to be used for this purpose shall be obtained
SECTION 01 11 00.05 50 Page 12 from the Area Engineer's Office. The list shall include the following:
a. Contract number
b. Description of item
c. Model number
d. Serial number
e. Capacity
f. Name of manufacturer
g. Address of manufacturer
h. Condition of item
i. Replacement cost
j. Name of person who checked item
1.18 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
1.18.1 Allowable Costs
Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a Contractor or subcontractor at any tier shall be based on actual cost data when the Government can determine both ownership and operating costs for each piece of equipment or equipment groups of similar serial and series from the Contractor's accounting records. When both ownership and operating costs cannot be determined from the Contractor's accounting records, equipment costs shall be based upon the applicable provisions of EP 1110-1-8, 11 Construction Equipment Ownership and Operating Expense Schedule, 11 Region II. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the Contracting Officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retrospective pricing, the schedule in effect at the time the work was performed shall apply.
1.18.2 Rental Costs
Equipment rental costs are allowable, subject to the applicable provisions of the Federal Acquisition Regulations, and shall be substantiated by certified copies of paid invoices. Rates for equipment rented from an organization under common control, lease-purchase or sale-leaseback arrangements will be determined using the schedule except that rental costs leased form an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees are allowable. Costs for major repairs and overhaul are unallowable.
1.18.3 Equipment Costs
When actual equipment costs are proposed and the total amount of the pricing action is over $25,000, cost or pricing data shall be submitted on the Standard Form 1411, "Contract Pricing Proposal Cover Sheet", by submitting cost or pricing data, the Contractor grants to the Contracting Officer or an authorizing representative the right to examine those books, records, documents and other supporting data that will permit evaluation of the proposed equipment costs. After price agreement the Contractor shall certify that the equipment costs or pricing data submitted are accurate, complete and current.
SECTION 01 11 00.05 50 Page 13
1.19 SUBCONTRACTS AND WORK COORDINATION
Contract Clauses "SUBCONTRACTS", "PERMITS AND RESPONSIBILITIES", and "MATERIAL AND WORKMANSHIP" are supplemented as follows:
a. Divisions or sections of specifications are not intended to control the Contractor in dividing the work among subcontractor, or to limit work performed by any trade.
b. Contractor shall be responsible for coordination of the work of the trades, subcontractors, and materials.
c. The Government or its representative will not undertake to settle any difference between the Contractor and Contractor 's subcontractors, or between subcontractors.
d. The Government reserves the right to refuse to permit employment on the work or require dismissal from the work of any subcontractor who, by reason of previous unsatisfactory work on Corps of Engineers projects, or for any other reason is considered by the Contracting Officer to be incompetent or otherwise objectionable.
1.20 CONSTRUCTION MANPOWER AND EQUIPMENT REPORT
The Contractor shall submit executed CENAO Form 987, Construction Manpower and Equipment Report daily. The report shall include manpower and equipment for the general and subcontractors. Forms are available from the Contracting Officer.
1.21 PURCHASE ORDERS
To ensure proper expediting of orders the Contractor and his subcontractors shall furnish to the Contracting Officer, one copy of each purchase order covering supplies or services required for performance of the work. Each purchase order shall clearly indicate the date of placement, the date delivery is required in order to avoid delay in the scheduled progress of the work, and the date delivery is promised by the supplier or producer.
Copies of purchase orders shall be forwarded on the date issued.
1.22 PROFIT
1.22.1 Weighted Guidelines
Weighted guidelines method of determining profit shall be used on any equitable adjustment change order or modification issued under this contract. The profit factors shall be ·as follows:
Factor Rate Weight Value
Degree of Risk 20 ___ ___ Relative difficulty of work 15 ___ ___ Size of Job 15 ___ ___ Period of performance 15 ___ ___ Contractor's investment 05 ___ ___ Assistance by Government 05 ___ ___ Subcontracting 25 ___ ___ 100 ___
SECTION 01 11 00.05 50 Page 14
1.22.2 Value
Based on the circumstances of each procurement action, each of the above factors shall be weighted from .03 to .12 as indicated below. The value shall be obtained by multiplying the rate by the weight. The value column when totaled indicates the fair and reasonable profit percentage under the circumstances of the particular procurement.
1.22.2.1 Degree of Risk
Where the work involves no risk or the degree of risk is very small, the weighting should be .03; as the degree of risk increases, the weighting should be increased up to a maximum of .12. Lump sum items will have, generally, a higher weighted value than the unit price items for which quantities are provided. Other things to consider: the portion of the work to be done by subcontractors, nature of work, where work is to be performed, reasonableness of negotiated costs, amount of labor included in costs, and whether the negotiation is before or after performance of work.
1.22.2.2 Relative Difficulty of Work
If the work is most difficult and complex, the weighting should be .12 and should be proportionately reduced to .03 on the simplest of jobs. This factor is tied in to some extent with the degree of risk. Some things to consider: the nature of the work, by whom it is to be done, where, and what is the time schedule.
1.22.2.3 Size of Job
All work not in excess of $100,000 shall be weighted at .12. Work estimated between $100,000 and $5,000,000 shall be proportionately weighted from .12 to .05.
1.22.2.4 Periods of Performance
Jobs in excess of 24 months are to be weighted at .12. Jobs of lesser duration are to be proportionately weighted to a minimum of .03 for jobs not to exceed 30 days. No weight where additional time not required.
1.22.2.5 Contractor's Investment
To be weighted from .03 to .12 on the basis of below average, average, and above average. Things to consider: amount of subcontracting, mobilization payment item, Government furnished property, equipment and facilities, and expediting assistance.
1.22.2.6 Assistance by Government
To be weighted from .12 to .03 on the basis of average to above average.
Things to consider: use of Government owned property, equipment and facilities, and expediting assistance.
1.22.2.7 Subcontracting
To be weighted inversely proportional to the amount of subcontracting.
Where 80 percent or more of the work is to be subcontracted, the weighting is to be .03 and such weighting proportionately increased to .12 where all
SECTION 01 11 00.05 50 Page 15 the work is performed by the Contractor's own forces.
1.23 BLASTING
Blasting will not be permitted.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00.05 50 Page 16
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 31 19.00 50
PROJECT MEETINGS
12/18
PART 1 GENERAL
1.1 SUBMITTALS
1.2 PRECONSTRUCTION CONFERENCE
1.2.1 Scheduling
1.2.2 Purpose
1.2.3 Discussion Items
1.3 PROJECT MEETINGS
1.4 OTHER MEETINGS
1.5 FACILITY MEETINGS
1.6 MINUTES OF MEETINGS
1.7 WARRANTY MANAGEMENT PLAN
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 31 19.00 50 Page 1
SECTION 01 31 19.00 50
PROJECT MEETINGS
12/18
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Transmit submittal items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
Bring following administrative submittal items to Preconstruction Conference:
SD-01 Preconstruction Submittals
A Project Submittal Schedule shall be submitted in accordance with paragraph entitled, "Project Meetings", of this section
The Contractor shall submit a Weekly Progress Report at the first meeting of each month.
1.2 PRECONSTRUCTION CONFERENCE
1.2.1 Scheduling
After award of the construction contract and prior to the start of any construction work, the Contracting Officer (CO) will schedule and conduct a preconstruction conference. The Contractor's Project Manager, Superintendent and Quality Control System Manager shall attend this meeting. The Contractor is encouraged to have an officer of his company (Project Manager could be this person) and representation from each of his sub-contractors at the conference. This conference will be held at a location and time as specified by the CO.
1.2.2 Purpose
The purpose of this preconstruction conference is to enable the CO to outline the procedures that will be followed by the Government in its administration of this construction contract and to the discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government's supervision and inspection of contract work, about security requirements, regulations, etc. The CO may invite Using Service personnel and any other Government personnel to attend this conference.
1.2.3 Discussion Items
The following is a list of items for discussion during the preconstruction conference. However, the Contracting Officer may include additional items for discussion as conditions and the work require.
a. Authority of the Area/Resident Engineer and organization of the Area/Resident office.
SECTION 01 31 19.00 50 Page 2
b. Contractor's Progress Schedule.
c. Correspondence Procedures.
d. Contractor Labor Standards Provisions.
e. Contract Modifications and Administrative Procedures.
f. Contractor's Administrative, Laydown and Storage Areas.
g. Procedures for Processing Submittals.
h. Payment Estimate Data and Procedures.
i. Contractor Utilities.
j. Security Requirements and Other Regulations, if applicable.
k. Government Furnished Equipment, if applicable.
l. Disposition of Salvage Property.
m. Contractor Insurance Requirements.
n. Value Engineering Program.
o. Contractor Performance Evaluation.
p. As-Built Drawings.
q. Single Point of Contact for Warranty for Construction.
r. Turnover of Completed Facilities.
1.3 PROJECT MEETINGS
The Contractor shall attend weekly project meetings scheduled by the Government. The Contractor's Project Manager, Superintendent, and Contractor Quality Control System Manager (CQC System Manager) shall attend scheduled project meetings.
A Weekly Project Report shall be submitted with the progress schedule, and shall address potential factors of delay, deficiencies, material delivery schedules, submittals and safety issues.
A Project Submittal Schedule shall be submitted showing full coordination with the project schedule. All products and tests under each submittal number shall be prioritized and linked to the progress schedule.
1.4 OTHER MEETINGS
Other meetings are or may be scheduled to be held after the Preconstruction Conference, and such meetings may include the following:
a. Accident Prevention Safety Plan
b. Quality Control Plan
SECTION 01 31 19.00 50 Page 3
c. Environmental Protection Plan
d. Warranty Management Plan (Post Construction Warranty Conference)
1.5 FACILITY MEETINGS
The Facility may also schedule meetings with the Contractor through the CO during the progress of construction work.
1.6 MINUTES OF MEETINGS
The Contractor shall prepare minutes of the meeting and shall provide the Government with a signed original for review and concurrence. The minutes shall include all items discussed at the meeting and the Contractor shall make all corrections provided by the Government and resubmit the corrected minutes to the Government within seven days.
1.7 WARRANTY MANAGEMENT PLAN
The Contractor shall provide a Warranty Management Plan, not less than 30 days prior to the Post-Construction Warranty Conference. As a minimum, include a table, showing the requirements, and attach certificcates:
a. List of warranties provided.
b. List of equipment, names of manufacturers an suppliers and phone numbers.
c. Period warranties and Start Date.
d. List of Extended Warranties.
e. Warranty Certificates.
f. Single Point of Contact for Warranty of Construction.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
SECTION 01 31 19.00 50 Page 4
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01.00 10
PROJECT SCHEDULE
02/15
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 PROJECT SCHEDULER QUALIFICATIONS
PART 2 PRODUCTS
2.1 SOFTWARE
2.1.1 Government Default Software
2.1.2 Contractor Software
2.1.2.1 Primavera
2.1.2.2 Other Than Primavera
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 BASIS FOR PAYMENT AND COST LOADING
3.2.1 Activity Cost Loading
3.2.2 Withholdings / Payment Rejection
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
3.3.2 Activity Durations
3.3.3 Procurement Activities
3.3.4 Mandatory Tasks
3.3.5 Government Activities
3.3.6 Standard Activity Coding Dictionary
3.3.6.1 Workers Per Day (WRKP)
3.3.6.2 Responsible Party Coding (RESP)
3.3.6.3 Area of Work Coding (AREA)
3.3.6.4 Modification Number (MODF)
3.3.6.5 Bid Item Coding (BIDI)
3.3.6.6 Phase of Work Coding (PHAS)
3.3.6.7 Category of Work Coding (CATW)
3.3.6.8 Feature of Work Coding (FOW)
3.3.7 Contract Milestones and Constraints
3.3.7.1 Project Start Date Milestone and Constraint
3.3.7.2 End Project Finish Milestone and Constraint
3.3.7.3 Interim Completion Dates and Constraints
3.3.7.3.1 Start Phase
3.3.7.3.2 End Phase
3.3.8 Calendars
3.3.9 Open Ended Logic
3.3.10 Default Progress Data Disallowed
3.3.11 Out-of-Sequence Progress
3.3.12 Added and Deleted Activities
SECTION 01 32 01.00 10 Page 1
3.3.13 Original Durations
3.3.14 Leads, Lags, and Start to Finish Relationships
3.3.15 Retained Logic
3.3.16 Percent Complete
3.3.17 Remaining Duration
3.3.18 Cost Loading of Closeout Activities
3.3.18.1 As-Built Drawings
3.3.18.2 O & M Manuals
3.3.19 Early Completion Schedule and the Right to Finish Early
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Preliminary Project Schedule Submission
3.4.2 Initial Project Schedule Submission
3.4.3 Periodic Schedule Updates
3.5 SUBMISSION REQUIREMENTS
3.5.1 Data CD/DVDs
3.5.2 Narrative Report
3.5.3 Schedule Reports
3.5.3.1 Activity Report
3.5.3.2 Logic Report
3.5.3.3 Total Float Report
3.5.3.4 Earnings Report by CLIN
3.5.3.5 Schedule Log
3.5.4 Network Diagram
3.5.4.1 Continuous Flow
3.5.4.2 Project Milestone Dates
3.5.4.3 Critical Path
3.5.4.4 Banding
3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram
3.6 PERIODIC SCHEDULE UPDATE
3.6.1 Periodic Schedule Update Meetings
3.6.2 Update Submission Following Progress Meeting
3.7 WEEKLY PROGRESS MEETINGS
3.8 REQUESTS FOR TIME EXTENSIONS
3.8.1 Justification of Delay
3.8.2 Time Impact Analysis (Prospective Analysis)
3.8.3 Forensic Schedule Analysis (Retrospective Analysis)
3.8.4 Fragmentary Network (Fragnet)
3.8.5 Time Extension
3.8.6 Impact to Early Completion Schedule
3.9 FAILURE TO ACHIEVE PROGRESS
3.9.1 Artificially Improving Progress
3.9.2 Failure to Perform
3.9.3 Recovery Schedule
3.10 OWNERSHIP OF FLOAT
3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS
3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS
SECTION 01 32 01.00 10 Page 2
SECTION 01 32 01.00 10
PROJECT SCHEDULE
02/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications ; G
Preliminary Project Schedule ; G
Initial Project Schedule ; G
Periodic Schedule Update ; G
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification.