This document summarizes questions and answers regarding a solicitation for repairing a parking lot. The solicitation seeks a contractor to design and construct a parking lot addition for the Lotts Center building located at the Defense Supply Center Richmond in Virginia. Work includes demolishing an existing berm, installing parking spaces, lighting, landscaping, and a handicap ramp to access the building. The geothermal well field beneath the site must be maintained. Questions addressed include clarifying the contaminated soil removal quantity and type, confirming available electrical power, and providing stormwater permit documents and geothermal system information. Bid submission and question response dates were extended through amendments.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

W91236-20-B-0001 "Lotts Center Parking Lot" is hereby amended as follow s:

1. Reminder the solicitation closing date remains Thursday, 19 December 2019 at 10:00am EST.

2. This amendment is issued to incorporate the Final ProjNet Questions and Answ ers.

3. This amendment w ill include the follow ing attachments: MS101 Geothermal Site Plan dated 03 Nov 2014 1 page, M-609 Geothermal Piping

Diagram dated 03 Nov 2014 1 page, Sealed Lotts Center Parking - VDEQ Submittal Draw ings Final revised 31 July 2019 32 pages, and Lotts

Center Parking Lot_VDEQ Approval Letter dated 16 Aug 2019 2 pages.

4. All other terms and conditions remain unchanged. See Summary of Changes.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 12

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 16-Dec-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9123620B0001

X 9B. DATED (SEE ITEM 11)

13-Nov-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

13-Dec-2019

CODE

USA ENGINEER DISTRICT, NORFOLK

803 FRONT STREET

NORFOLK VA 23510

W91236 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9123620B0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following have been modified:

ATTACHMENTS

ATTACHMENTS

1. Lotts Center parking Lot Specifications dated May 10, 2019 571 pages

2. Lotts Center parking Lot Drawings, dated August 23, 2019 41 pages

3. Lotts Center Parking Lot Site Visit Sign In Sheet, dated 4 December 2019, 1 page

4. MS101 Geothermal Site Plan dated 03 Nov 2014 1 page

5. M-609 Geothermal Piping Diagram dated 03 Nov 2014 1 page

6. Sealed Lotts Center Parking - VDEQ Submittal Drawings Final revised 31 July 2019 32 pages

7. Lotts Center Parking Lot_VDEQ Approval Letter dated 16 Aug 2019 2 pages

252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall--

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

Title File Drawing No.

Lotts Center Parking Lot Specifications dated 10 May 2019 571 pages

Lotts Center Parking Lot Drawings, dated 23 August 2019 41 pages

Lotts Center Parking Lot Site Visit Sign In Sheet, dated 4 December 2019, 1 page

MS101 Geothermal Site Plan dated 03 Nov 2014 1 page

M-609 Geothermal Piping Diagram dated 03 Nov 2014 1 page

Sealed Lotts Center Parking - VDEQ Submittal Drawings Final revised 31 July 2019 32 pages

Lotts Center Parking Lot_VDEQ Approval Letter dated 16 Aug 2019 2 pages

(End of clause)

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following have been modified:

PROJNET QUESTIONS AND ANSWERS

Bid Inquiry Contracting Officers Report

All Inquiries

Project: Repair Parking near Lotts Center at DLA Review: Parking Near Lotts Ctr W91236-20-

B-0001 (00001)

(sorted by CommentID )

Id Discipline Sheet Detail Spec

8288229 General

RFI Deadline Section 11. Offerors Questions and

Comments

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

There is conflicting instructions regarding the RFI deadline for this solicitation. The RFP states that, "All questions and/or comments from the preproposal conference should reach the above referenced Contracting Office no later than 10 calendar days after the pre-proposal conference" and then later says in 1.5.1.2 "The Bidder Inquiry System will be unavailable for new inquires 10 days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary."

Is the deadline 10 days after the site visit? (making the deadline 12/14) or is it 10 days before the proposal submission? (making the deadline 12/2)...

Please note that the 12/2 due date would make RFIs due before the scehduled site visit. We recommend making the RFI closing date at least 3 days after the site visit.

1-1 Government Response. RFI deadline for ProjNet inquiries is 10 days prior to bid opening (i.e. COB on

12/2). If there are additional questions that come about at the site visit, we will re-open ProNet for those questions to be addressed. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 10 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8291016 Contracting RFI Date

Please extend RFI deadline to at least Friday, December 6th due to the site visit date on Wednesday, Dec 4th. The site visit will generate several RFIs and these RFIs will need these answers to bid the project accordingly.

1-1 Government Response. RFI deadline for ProjNet inquiries is 10 days prior to bid opening (i.e. COB on

12/2). If there are additional questions that come about at the site visit, we will re-open ProNet for those questions to be addressed. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 10 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8291020 Contracting G004

The bid schedule included in the RFP shows 30 cubic yards of contaminated soils for CLIN 0002; however, RFP drawing sheet G-004 states there are 25CY of contaminated soils to be encountered. Which quantity is correct?

1-1 Government Response. Assume 30 cubic yards is correct. By: Synease McArthur; CENAO-CT

Contracting Office; (757-201-7062) On: Dec 10 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8291021 Civil C101

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Sheet C101 shows locations for solar panel area labeled as bid options; however, there are no CLINs on our RFP bid schedule that indicate this is to be provided. Please confirm if the note shown on C-101 SOLAR VEHICLE SERVICES BID OPTION will be performed on a separate contract.

1-1 Government Response. Please submit bids as shown on the bid schedule. Solar Vehicle services will not be exercised on this contract. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On:

Dec 10 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8291022 Civil 02 61 13

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Spec section 02 61 13, paragraph 1.3 states the locations of contaminated materials are to be shown on drawings.

The only information included in the drawings regarding contaminated materials is a sheet note on G-004 stating it's estimated 25 CYD of contaminated soils will be encountered. Are the locations known? If so, please provide this information.

1-1 Government Response. Contaminated soil locations are not known and CLIN 002 was added as a contingency in the event contaminated soil is encountered. General Sheet Notes 4 and 5 on Sheet CG101 Grading Plan also provide guidance if contaminated soil is encountered. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 10 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8291666 Electrical E-001,E-101, E-501, E-502

Drawings State "Progress Print Not For Construction" and "This Drawing is NOT for Pricing or Construction" with the NOT in all capitals and Bold print. Many electrical contractors will not price preliminary drawings. Please provide a statement these are for pricing and construction or provide final drawings.

1-1 Government Response. Unsigned/sealed drawings dated 06/01/19 are complete for pricing. By: Synease

McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 10 2019

Current Request Status: Request Closed

8291680 Electrical EL-101

Drawing EL-101 Calculated lighting levels, was provided but not listed on the Index of Sheets. Please confirm this is the only sheet left off of the Index of Sheets and the information provided is complete and ready for the development of cost estimating.

1-1 Government Response. EL-101 is the only sheet not provided on Sheet G-002. Unsigned/sealed drawings dated 06/01/19 are complete for pricing. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 10 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8292226 Civil BB001 31 00 00

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

In 8-10 locations within the specifications it discusses the re-use of excavated soils. Additionally, Drawing BB001 provides some classification information. However, spec section 1.4.1 states "No consideration will be given to the nature of the materials, and all excavation will be designated as unclassified excavation. This would likely greatly increase cost. Please confirm references to unclassified excavations found in sections 1.4.1, 1.4.1.1 and parts of

3.2.6 applies only to soils above the sub-grade.

1-1 Government Response. In Section 1.4.1, "No consideration will be given to the nature of the materials, and all excavation will be designated as unclassified excavation" will be removed and replaced with "Finish the specified excavation on a classified basis, in accordance with the designations and classifications contained in this specification." Section 1.4.1 (as revised above) refers to all excavation. The discussion of unclassified soils in Section 3.2.6 refers to soils above the subgrade. Section 1.4.1.1 will be removed from this Specification. By:

Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 10 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8292248 Civil CG101 1.3.2 31 00 00

Does any of the berm shown to be removed contain unsatisfactory materials such as "backfills from previous construction" (1.3.2) which would prevent it from being re-used or increase the cost of disposal over 100% soil.

1-1 Government Response. According to USACE (from Section 1.4 Project Narrative of the AESOW), "the berm is comprised of concrete and brick rubble (estimated at 50% by volume), with fill and topsoil. The berm does not contain hazardous material". By: Synease McArthur; CENAO-CT Contracting Office; (757- 201-7062) On:

Dec 10 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8292250 Civil 31 00 00

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Specification 3.2.6 states "undercutting to remove very soft/loose soils should be anticipated and The project's budget should include an allowance for sub-grade improvements as described above." Section 3.3.1 states "Remove and replace unsatisfactory material with satisfactory materials as directed by the contracting officer, in surfaces to receive fill or in excavated areas. The specifications/Contracting officer does not quantify the amount of soil to be removed.

This information can not be gained from the contract documents nor during the site visit. Please specify an amount of soil to be removed and replaced for bid purposes.

1-1 Government Response. For bid purposes, assume 925 cubic yards of unsatisfactory material to be removed and disposed of as undercut and replaced with satisfactory material. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 10 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8296623 General 26 31 00 Photovoltaic

The solar photovoltaic specification section 26 31 00 references testing to be first tier contractor. The testing it typically performed by the installer or a certified manufacturer representative. Will it be allowed to have the installer or manufacturer representative complete the required testing of the solar panel system?

1-1 Government Response. Testing of PV solar array by a certified manufacturer representative is acceptable. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 10 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8296634 General Soil Removal

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

When pricing the 25cyd of contaminated soil removal in Option 1, what type / classification of contaminated soil are we to price? Where is this contaminated soil located on the site? Is this an in-house estimate option only to cover future MODs to the contract?

1-1 Government Response. Per Specification 01 11 00, the site is defined as "a current or former industrial site or other hazard producing activity site which is perceived to be a clean location; however, due to former industrial or other activities within or near the site, it has the potential for contamination". There are no known locations of contaminated soil on the site. Option 1 was added as contingency based on historical use of the property. According to USACE (from Section 1.4 Project Narrative of the AESOW), " The berm does not contain hazardous material". Excavations for drainage, stormwater management structures, and other utilities could encounter contaminated soil. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 10 2019

Current Request Status: Request Closed

8296641 General Asphalt

The civil drawings indicate there is no fabric liner under asphalt in areas identified for demolition. Please confirm there is no fabric liner present in the existing asphalt profile. Recycling centers will not take asphalt with fabric liners, which can affect our pricing.

1-1 Government Response. Design drawings of the adjacent Operations Center do not show fabric liner on pavement section details. Presence of a liner was not noted in test holes or borings performed in the Lotts Center Parking Lot project area. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 10 2019

Current Request Status: Request Closed

8300255 Civil CD101, C201

CD101 appears to require only the lateral storm pipes running perpendicular to the main storm line and building itself to be removed. C201 requires the storm pipe to be of specific size and grades. Please confirm the intent of the drawings is to remove and replace all storm pipe including the main line running parallel with the building and connecting to the new MTD as part of this work while the area is under construction and equipment is onsite.

1-1 Government Response. Sheet CD-101 identifies the pipes that are to be removed. The "main line running parallel with the building" is to remain, with existing structures removed and replaced as shown on C-

101. The intent is to maintain the existing "main line" and tie it into new junction box (101-5) as shown on Sheet C-101. C-201 shows the new storm line to be constructed parallel to the existing "main line", shown on C- 101 (from structure 101-8 to the MTD, then to 101-5). The overall intent is to convey stormwater runoff from the new pavement through the MTD, while maintaining the existing "main line" and its roof drain connections. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 13 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8300256 Utilities Engineering CD101

CD101 states to raise hatch to match new grade. The hatch manufacturer has stated they do not manufacture a riser or attachment to achieve this function. It appears the vault top, frame, and hatch assemble must be cut off and replaced with cast in place concrete. Vehicular hatch ratings are dependent on the structural steel embedded in the concrete. Please specify the vault depth (locked during the site visit) and vehicular rating required for the new hatch.

1-1 Government Response. The vehicle load rating is AASHTO H-20. Vault depth is approximately 8 feet deep. Contractor to field verify. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On:

Dec 13 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8300258 Utilities Engineering C202

Sheet C-202 requires the existing 4" gas line to be removed and replaced. Please identify what this gas line supplies or is used for and confirm that the gas utility can be shut off (complete outage) for a period of 5-6 days to perform the work required prior to it being re-connected.

1-1 Government Response. This gas line is owned by and used by DSCR. Per General Sheet Note 2 on

Sheet C-202, the contractor must coordinate gas installation and shutdown with the COR and DSCR Chief of Utility. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 13 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8300264 Construction Management G004

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Sheet G004 general notes 12 and 20 appear to indicate the contractor must allow access to the building thru the job site to include emergency vehicles and tractor trailers. A majority of the work to include extremely deep trenching, occurs within 60 feet of the loading dock along the entire length of the building. Contractor has the liability for both safety and schedule and must restrict access to accomplish these task. Please confirm, that the contractor must keep roads open but can completely restrict access within the limits of construction.

1-1 Government Response. General Note 21 on Sheet G-004 provides a procedure for coordinating a complete road closure with DSCR. The intent is to keep roads open and restrict general access within the limits of construction. Fire Department access to fire hydrants must be provided. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 13 2019

Current Request Status: Request Closed

8300266 Construction Management G004 02 61 13

Contaminated soil is a general term which can be interpreted in various ways. It could be contaminated with construction debris, special waste such as petroleum, or hazardous waste (not likely since the general public could currently come in contact with it). Pricing for the handling, special equipment and disposal of contaminated soil could vary from $50.00/yd to over $3000.00/yd. Please identify the type of contamination in the soil so bidders can price the contract line item.

1-1 Government Response. Per Specification 01 11 00, the site is defined as "a current or former industrial site or other hazard producing activity site which is perceived to be a clean location; however, due to former industrial or other activities within or near the site, it has the potential for contamination". There are no known locations of contaminated soil on the site. Option 1 was added as contingency based on historical use of the property. According to USACE (from Section 1.4 Project Narrative of the AESOW), " The berm does not contain hazardous material". Excavations for drainage, stormwater management structures, and other utilities could encounter contaminated soil. Section 3.4 of Specification 02 61 13 refers to Commonwealth of Virginia Voluntary Remediation Program (VRP) Tier III Screening Table for Soil as a standard for removal confirmation sampling. By: Synease McArthur; CENAO-CT Contracting Office; (757- 201- 7062) On: Dec 13 2019

Current Request Status: Request Closed

8300269 Electrical E101

Source location to obtain electrical power in F Bay could not be verified during the site walk. Please confirm sufficient and properly sized electrical power is readily available from an existing electrical panel.

1-1 Government Response. At the start of the design of this project (October 2018) there was an existing spare 200A-3P circuit breaker in MDP at 120/208V for use for this project. By: Synease McArthur; CENAO- CT Contracting Office; (757-201-7062) On: Dec 13 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8300331 Utilities Engineering V102

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

A prerequisite to developing an accurate cost estimate at time of bid requires additional information on the existing Geo- Thermal system. Contract documents nor the site visit provides the necessary information. Please provide as- built drawings for the Geo-thermal system installation. If for some reason as-built documents are not available, please provide the solicitation documents governing installation for that work.

2-1 Government Response. The text below appends or clarifies ALL previous replies.

Asbuilt drawings were not provided to the AE. AE excavated several utiilty test holes to 7' below grade, but could not locate geothermal piping to confirm depth or pipe material. Sheet MS-101 and M-609 of DLA Operations Center drawings is being provided, which shows pipe depths of 5-6" to 7-9" below finished grade. Sheet M-609 Geothermal Piping Diagram of DLA Operations Center drawings , which shows a schemtic of the geothermal system and a detail of the vault.

Sheet MS-101 and M-609 will be uploaded to beta.sam.gov.By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 13 2019

Current Request Status: Request Closed

8300332 Electrical E101

Drawing E101 states "Contractor to install concrete pole bases and underground conduits in such a manner not to damage existing geothermal well field components." Industry standard margin of error on underground utilities is 3' either side of the marking and 15% on estimated depth. The state of Virginia is only rated as moderately successful for use of Ground Penetrating Radar for non-metallic piping. Please provide the type of pipe used, size of pipe used, depth of buried pipe for the geothermal system.

1-1 Government Response. Asbuilt drawings were not provided to the AE. AE excavated several utiilty test holes, but could not locate geothermal piping to confirm depth or pipe material. Sheet M-609 Geothermal Piping Diagram of DLA Operations Center drawings is being provided, which shows geothermal "send" and "return" pipe depths from 5-6" to 7-9" below finished grade. Pipe material is not labeled on Sheet M-609, but pipe diameters are labeled ranging from 1.25" to 10". Sheet M-609 Geothermal Piping Diagram of DLA Operations Center drawings , which shows a schemtic of the geothermal system and a detail of the vault.

By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 13 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8300336 Civil CD101

CD101 requires storm pipe to be removed but does not indicate if it is above or below the existing Geothermal system.

Is this pipe located above or below the geo-Thermal System?

1-1 Government Response. Based on the information available, the pipes are located above the geothermal system. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 13 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8300343 Civil CD101

Is the existing underground electric providing power to the geothermal system vaults located above the Geo-Thermal piping system? Grade cuts to achieve proper finish grades may conflict with existing underground. There was no way of gathering information on the Geo-Thermal system from the contract documents or site visit.

1-1 Government Response. Based on the information available, the existing electric serving the geothermal vaults is not expected to be in conflict with excavation of the pavement section. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 13 2019

8300344 Construction Management A101

General note one says to see sheet CD101 for guardrail demolition. Is this note referring to "Remove existing loading dock railing 5' horizontally from top of existing stairs"?

1-1 Government Response. Correct. The guardrail reference on A101 refers to the loading dock railing. By:

Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 13 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8301285 Construction Management G-004 thru G-007

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

VA DEQ usually will not accept storm water and erosion and sediment drawings that are not stamped. Engineering firms will not stamp or sign off on other companies drawings or storm water calculations. Without these documents start of construction will be delayed 4-6 months. Please provide stamped drawings, VA DEQ approval letter (if available) and storm water calculations (bidders have no way of getting engineers onsite at DSCR or work stations for extended periods of time to review calculations).

2-1

Government Response. Final VDEQ Submittal (dated 31 July 2019) and the VDEQ Approval Letter (dated

16 August 2019) are attached. By: Synease McArthur; CENAO-CT Contracting Office; (757-201- 7062) On:

Dec 13 2019

8302076 Construction Management General

As there are currently 25 outstanding questions and ProjNet will not close until 12/10/19 with bids currently due on 12/12/19, we request that the government issue an extension of the proposal due date. Please advise as to when an amendment will be forthcoming to answer questions and address the proposal due date.

1-1 Government Response. Please refer to Beta.Sam for any amendments issued. By: Synease McArthur;

CENAO-CT Contracting Office; (757-201-7062) On: Dec 10 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8302317 Electrical E501

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Bolt down Pole foundation shows the top of the concrete foundation pole to be 4" above grade on one side of the detail and 12" on the other side of the detail. On the same page the Concrete Base detail requires the top of the pole base to be 18" above finished grade. Please confirm the top of pole base should be 18" above finished grade.

1-1

Government Response. Concrete base top of foundation shall be 18" AFG. By: Synease McArthur; CENAO-

CT Contracting Office; (757-201-7062) On: Dec 13 2019 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8302360 General General

There are two different beta.SAM.gov links for this opportunity. The original link from 10/4/19 that the pre-solicitation was released and when the actual solicitation was released on 11/13/19 a new link was created and used for the solicitation and Amendment 01. Amendment 02 was then released on the previously used original pre-sol link that most of the bidders were "watching". Given the confusion with the new system We would like to respectfully request an extension of the due date as well as a second site visit for those bidders who were not aware of the solicitation release in time.

1-1 Government Response. Please refer to Amendments 1-3 posted on Beta.Sam. By: Synease

McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 13 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8302413 Construction Management 01 30 00.20 50

Contractors need 5 days after ALL questions have been answered to modify/develop approaches and ensure coverage, obtain subcontractor quotes, negotiate responsibilities and price, modify cost estimate and obtain bonding.

Please extend bid due date accordingly.

1-1 Government Response. Please refer to Amendment 3 posted on Beta.Sam on 11 Dec. By: Synease

McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 13 2019

Current Request Status: Request Closed

8302897 Civil 31 00 00

Paragraph 3.4 states "Dispose unsatisfactory materials removed from excavations into designated waste disposal OFFSITE." However it goes on to state "Dispose of Satisfactory material, authorized to be wasted, in designated areas approved for surplus material storage or designated waste areas as directed. Federal and State requirements would require this area to meet the same SWPPP requirements as the job site. Unless DSCR already has an area designated in their current SWPPP this would include silt fence, seeding, storm water calculations, DEQ approvals etc. Does DSCR already have a state approved designated area or should bidders plan to dispose of all excess material offsite.

1-1 Government Response. The contractor must assume all unsatisfactory material and satisfactory material not used on the site is to be disposed of offsite and that SWPPP coverage for this action is the contractor's responsibility. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 13 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8302914 Civil 31 00 00

A Geotechnical Engineer is required in several places throughout the specification but a definition was not found.

Does this individual have to possess a four year degree in engineering or can a soil scientist who perform soils classification as part of their daily duties and who possess a Soil evaluator license be utilized.

1-1 Government Response. Assume qualified Geotechnical Engineer in Specification 31 00 00 is a licensed

Professional Engineer. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 13 2019

8303223 Environmental 01 57 19

Please confirm that the contractor can connect and maintain a connection to the fire hydrant. Dust Control/ Seeding Etc.

1-1 Government Response. DSCR must authorize any connection to its utilities. Assume connection to existing fire hydrants is not allowed. By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 13 2019

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8303492 Construction Management 01 35 26 00 50

Since 1.5.1.1 states that "The contractor quality control (QC) person cannot be the SSHO on this project" please confirm the COE is requiring at least two management personnel (superintendent/SSHO and QC) onsite at all times and one person can not wear all three hats.

1-1 Government Response. The contractor QC person cannot have another role on this project. The SSHO can serve as superintendant By: Synease McArthur; CENAO-CT Contracting Office; (757-201-7062) On:

Dec 13 2019

Current Request Status: Request Closed

8304912 Civil X-001

Thermoplastic striping is approximately three times as expensive as paint and usually not used in this geographic area with the exception of roads where the specific properties are required. Removal by snow plow is not an adhesion issue and outside of warranty. Adjacent parking areas at DSCR have painted striping. Can Type A, Class 1 (paint) be used.

1-1 Government Response. DSCR directed WSP to use thermoplastic on recent road and parking lot projects adjacent to Lotts Center. Assume thermoplastic striping is required. By: Synease

McArthur; CENAO-CT Contracting Office; (757-201-7062) On: Dec 13 2019

Current Request Status: Request Closed

Report Complete

(End of Summary of Changes)