UNCLASSIFIED\\FOR OFFICIAL USE ONLY
Bid Inquiry Technical Evaluators Report Closed Inquiries
Project: Joint Base Langley Eustis DLA Fuel Pier Review: W91236-16-R-0008 (00001) (sorted by CommentID ) Displaying 22 inquiries.
Id Discipline Sheet Detail Spec 6583915 Contracting Evaluation Criteria Section 6.2.2.3a Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The referenced section states that the requirement is for Construction of a new concrete pier, equal to or greater than 500 feet long with concrete piles.
We request that the requirement be changed to read construction of a new concrete pier equal to or greater than 500 feet long?
On: Jul 01 2016. Forward request by email.
1-0 Evaluation For Information Only. Meet the requirements as stated in the RFP By: Drew
Johnson; CENAO-EC-CQ Quality Assurance Section; (757-201-7850) On: Jul 27 2016 1-1 Government Response. Meet the requirements as stated in the RFP On: Aug 01 2016
Current Request Status: Request Closed Information for this report is procurement sensitive.
6583928 Contracting Submission Requirements Section 6.2.1.6
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The referenced section calls out that only projects completed or in process within the last 10 years will be considered.
We request that the time frame be extended to from 10 years to 20 years.
On: Jul 01 2016. Forward request by email.
1-0 Evaluation For Information Only. The requirement will be 10 years. By: Drew Johnson; CENAO-EC-
CQ Quality Assurance Section; (757-201-7850) On: Jul 27 2016 1-1 Government Response. The requirement will be 10 years. On: Aug 01 2016
Current Request Status: Request Closed Information for this report is procurement sensitive.
6583932 Civil Solicitation (Page 6 of 108) Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
There are 2 bid items (0007 and 0008) that refer to the dredging portion of the project.
Can you please provide plans, specifications, and any environmental permits in relation to this scope of work.
On: Jul 01 2016. Forward request by email.
1-0 Evaluation For Information Only. Drawings and specs are available on FOB as an attachment to the posting. The file is entitled "H.01.04_DLA Fuel Pier Final Specifications" By: Drew Johnson; CENAO-EC- CQ Quality Assurance Section; (757-201-7850) On: Jul 22 2016
1-1 Government Response. Drawings and specs are available on FBO as an attachment to the posting. The file is entitled "H.01.04_DLA Fuel Pier Final Specifications" On: Aug 01 2016 Current Request Status: Request Closed
Information for this report is procurement sensitive.
6590251 Contracting Section 00 22 11 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Par. 6.2.2.1 Recent. For a submitted project to be considered "Recent," the project shall demonstrate that it is well underway; i.e., at least 50% construction progress complete, or has been completed within the ten (10) years
Page 1 of 7ProjNet: Logged In User
8/1/2016https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminClosedRe...
preceding the date of this Solicitation.
We request expanding the 10 year completion window to 15 years preceding the date of this soliciation.
On: Jul 07 2016. Forward request by email.
1-0 Evaluation For Information Only. The requirement will be 10 years. By: Drew Johnson; CENAO-EC-
CQ Quality Assurance Section; (757-201-7850) On: Jul 27 2016 1-1 Government Response. The requirement will be 10 years. On: Aug 01 2016
Current Request Status: Request Closed Information for this report is procurement sensitive.
6590255 Contracting Section 00 22 11 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
6.2.2.3 Type/Scope. a. Construction of a new concrete pier, equal to or greater than 500 feet long with concrete piles.
With the Navy's extensive use of both steel pipe piles and concrete piles in new pier construction, we request adjusting this requirement to:
Construction of a new concrete pier, equal to or greater than 500 feet long with concrete piles or steel pipe piles.
On: Jul 07 2016. Forward request by email.
1-0 Evaluation For Information Only. Meet the requirements as stated in the RFP. By: Drew
Johnson; CENAO-EC-CQ Quality Assurance Section; (757-201-7850) On: Jul 27 2016 1-1 Government Response. Meet the requirements as stated in the RFP. On: Aug 01 2016
Current Request Status: Request Closed Information for this report is procurement sensitive.
6590258 Contracting Section 00 22 11 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
FACTOR 2 – PAST PERFORMANCE, 6.3.1 SUBMISSION REQUIREMENTS
Par 6.3.1.2 requires a Past Performance Questionnaire for each project submitted under Factor 1 - Specialized Experience. Please confirm that a completed CPARS or CCASS is acceptable in lieu of a PPQ.
On: Jul 07 2016. Forward request by email.
1-0 Evaluation For Information Only. The Past Performance Questionnaire is provided to all offerors in the solicitation. Failure to submit the questionnaire may result in an offeror's proposal being rated as "Unacceptable" by members of the evaluation board. By: Drew Johnson; CENAO-EC-CQ Quality Assurance Section; (757-201-7850) On: Jul 22 2016
1-1 Government Response. The Past Performance Questionnaire is provided to all Offerors in the solicitation. Failure to submit the questionnaire may result in an Offeror's proposal being rated as "Unacceptable" by members of the evaluation board. On: Aug 01 2016 Current Request Status: Request Closed
Information for this report is procurement sensitive.
6593361 Contracting 52.211-10 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
With regards to developing a project schedule, will there be any work day restrictions such as:
(1) time of day
(2) day of week
(3) special event
(4) holiday
(5) work restrictions otherwise
On: Jul 11 2016. Forward request by email.
1-0 Evaluation For Information Only. 1.3.1 Work Hours
Normal duty hours for Langley AFB, JBLE are 0730 through 1630, Monday through Friday. Work on weekends, recognized Federal holidays, or other than normal duty hours must be coordinated with the Contracting Officer
Page 2 of 7ProjNet: Logged In User
(CO) or his/her designated representative.
1.3.2 General Working Conditions
a. Work shall be performed in such a manner as to cause minimum disruption to the users in the area.
b. The Contractor shall notify the Contracting Officer or his/her designated representative when he intends to work so Government inspection can be provided while work is in progress.
1.13.4.6 Security Manager
The Contractor shall designate a representative as Security Manager to coordinate security matters. At least 48 hours in advance of a change in work hours, the Security Manager shall notify the Contracting Officer or his/her designated representative, who will notify the Security Forces. By: Drew Johnson; CENAO-EC-CQ Quality Assurance Section; (757-201-7850) On: Jul 26 2016
1-1 Government Response. 1.3.1 Work Hours Normal duty hours for Langley AFB, JBLE are 0730 through 1630, Monday through Friday. Work on weekends, recognized Federal holidays, or other than normal duty hours must be coordinated with the Contracting Officer (CO) or his/her designated representative.
1.3.2 General Working Conditions
a. Work shall be performed in such a manner as to cause minimum disruption to the users in the area.
b. The Contractor shall notify the Contracting Officer or his/her designated representative when he intends to work so Government inspection can be provided while work is in progress.
1.13.4.6 Security Manager
The Contractor shall designate a representative as Security Manager to coordinate security matters. At least 48 hours in advance of a change in work hours, the Security Manager shall notify the Contracting Officer or his/her designated representative, who will notify the Security Forces. On: Aug 01 2016 Current Request Status: Request Closed
Information for this report is procurement sensitive.
6593392 Structural 31 62 13.20 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Considering the crane height restrictions, would splicing of concrete piles be considered?
On: Jul 11 2016. Forward request by email.
1-0 Evaluation For Information Only. Splicing piles will not be considered. By: Drew Johnson; CENAO-
EC-CQ Quality Assurance Section; (757-201-7850) On: Jul 27 2016 1-1 Government Response. Splicing piles will not be considered. On: Aug 01 2016
Current Request Status: Request Closed Information for this report is procurement sensitive.
6593419 Contracting 00 22 11 - 6.2.2 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Section 00 22 11 Para 6.2.2 a, requires prior "construction of a new concrete pier, equal to or greater than 500 ft.
long with concrete piles." Would the government consider flexibility in this requirement as long as the prior projects were of similar size and magnitude($10,000,000 - $25,000,000), recently completed, relevant, of similar type/scope, but were not specifically a 500 ft long or greater concrete pier?
On: Jul 11 2016. Forward request by email.
1-0 Evaluation For Information Only. Since this project is specifically a concrete pier, we will leave the requirement as is. By: Drew Johnson; CENAO-EC-CQ Quality Assurance Section; (757-201-7850) On:
Jul 22 2016
1-1 Government Response. Since this project is specifically a concrete pier, we will leave the requirement as is. On: Aug 01 2016 Current Request Status: Request Closed
Information for this report is procurement sensitive.
Page 3 of 7ProjNet: Logged In User
6596796 General 1 Solicitation Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will the owner please extend the bid due date by two weeks?
On: Jul 13 2016. Forward request by email.
1-0 Evaluation For Information Only. The Government intends to make award on this action on or before
30 September 2016. In order to meet acquisition milestones and administrative deadlines, extension of the proposal due date is not possible at this time. By: Drew Johnson; CENAO-EC-CQ Quality Assurance Section; (757-201-7850) On: Jul 22 2016
1-1 Government Response. The Government intends to make award on this action on or before 30 September 2016. In order to meet acquisition milestones and administrative deadlines, extension of the proposal due date is not possible at this time. On: Aug 01 2016 Current Request Status: Request Closed
Information for this report is procurement sensitive.
6596802 General G-007 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
For the piles to be driven in full length sections there will need to be a height restriction waiver issued to the contractor. Will the Owner be providing this waiver?
On: Jul 13 2016. Forward request by email.
1-0 Evaluation For Information Only. It will be the responsibility of the Contractor to obtain the waiver. By:
Drew Johnson; CENAO-EC-CQ Quality Assurance Section; (757-201-7850) On: Jul 22 2016 1-1 Government Response. It will be the responsibility of the Contractor to obtain the waiver. On: Aug 01
Current Request Status: Request Closed
Information for this report is procurement sensitive.
6599416 Mechanical M-702 33 52 43.23 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Drawing M-702, the pump schedule shows pumps SWP-1 thru 7 as Sliding Vane Positive displacement pumps.
Specification section 33 52 43.23, paragraph 2.5 describes "Stripper Pumps (STP-1 and STP-2)" and paragraph 2.6 describes "Containment Sump Pumps (STP-1 and STP-2)". Where are the SWP pumps specified?
On: Jul 14 2016. Forward request by email.
1-0 Evaluation For Information Only. Part 2.6 of specification section 33 52 43.23 is the correct paragraph for the Storm Water Pumps. It should read "2.6 Containment Stormwater Pumps (SWP-1 thru SWP-7)" rather than Containment Sump Pump (STP-1 and STP-2). By: Drew Johnson; CENAO-EC-CQ Quality Assurance Section; (757-201-7850) On: Jul 27 2016
1-1 Government Response. Part 2.6 of specification section 33 52 43.23 is the correct paragraph for the Storm Water Pumps. It should read "2.6 Containment Stormwater Pumps (SWP-1 thru SWP-7)" rather than Containment Sump Pump (STP-1 and STP-2). On: Aug 01 2016 Current Request Status: Request Closed
Information for this report is procurement sensitive.
6603086 Contracting 00 11 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Item 0005 on the bid form calls for Prestressed precast concrete piles - 14" square. I have found 20" and 18" square precast piles, HP 12x84 steel piles, and 14" diameter timber piles associated with the new pier, but no 14" square precast piles. Please advise where these are located in the drawings.
On: Jul 18 2016. Forward request by email.
1-0 Evaluation For Information Only. The bid schedule will be amended to correct this mistake. By: Drew
Johnson; CENAO-EC-CQ Quality Assurance Section; (757-201-7850) On: Jul 22 2016 1-1 Government Response. The bid schedule will be amended to correct this mistake. On: Aug 01 2016
Current Request Status: Request Closed Information for this report is procurement sensitive.
Page 4 of 7ProjNet: Logged In User
6605735 Contracting Section 00 22 11 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Considering that new construction of concrete piers that are 500+ LF does not occur along the Eastern seaboard frequently please reconsider altering the specs so that projects can be considered "Recent" if they were well underway or completed within the twelve (12) years preceding the date of this Soliciation.
On: Jul 20 2016. Forward request by email.
1-0 Evaluation For Information Only. The requirement will be 10 years. By: Drew Johnson; CENAO-EC-
CQ Quality Assurance Section; (757-201-7850) On: Jul 27 2016 1-1 Government Response. The requirement will be 10 years. On: Aug 01 2016
Current Request Status: Request Closed Information for this report is procurement sensitive.
6607361 Specifications Division 01 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please provide any permits acquired for this project.
On: Jul 21 2016. Forward request by email.
1-0 Evaluation For Information Only. Permits will be submitted in an amendment By: Drew
Johnson; CENAO-EC-CQ Quality Assurance Section; (757-201-7850) On: Jul 22 2016 1-1 Government Response. Permits will be submitted in an amendment On: Aug 01 2016
Current Request Status: Request Closed Information for this report is procurement sensitive.
6607362 Specifications Division 01 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please provide the dredging permit acquired for this project.
On: Jul 21 2016. Forward request by email.
1-0 Evaluation For Information Only. Permits will be submitted in an amendment By: Drew
Johnson; CENAO-EC-CQ Quality Assurance Section; (757-201-7850) On: Jul 22 2016 1-1 Government Response. Permits will be submitted in an amendment On: Aug 01 2016
Current Request Status: Request Closed Information for this report is procurement sensitive.
6607659 Specifications 00 11 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
2.Bid item 0006 Includes All work for removal and disposal of fuel contaminated soil exceeding 100ppm within the Revetment Area. How much contaminated soil is anticipated? We recommend a Unit Price bid item per Ton as soil disposal is paid per ton and measured by weight tickets and would therefore be easily tracked and invoiced and should a variation in quantity occur additional or reduced tonnage would be easily addressed rather than a single lump sum for variable assumed quantities by bidders. We recommend 1000 tons as the intial bid quantity. The specifications call for screening, stockpiling and sampling (per 250 cy) and 1000 tons would provide a reasonable average unit price and allow for a substantial removal of impacted soil without delaying field work.
On: Jul 21 2016. Forward request by email.
1-0 Evaluation For Information Only. We will use 100 CY as the initial bid quantity. By: Drew
Johnson; CENAO-EC-CQ Quality Assurance Section; (757-201-7850) On: Jul 26 2016 1-1 Government Response. We will use 100 CY as the initial bid quantity. On: Aug 01 2016
Current Request Status: Request Closed Information for this report is procurement sensitive.
6607664 Specifications 00 21 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
1.Please incorporate FAR Clause 52.219-4 Notice of price evaluation preference for HUBZone small business concerns.
Page 5 of 7ProjNet: Logged In User
On: Jul 21 2016. Forward request by email.
1-0 Evaluation For Information Only. The referenced provision will be incorporated. By: Drew
Johnson; CENAO-EC-CQ Quality Assurance Section; (757-201-7850) On: Jul 27 2016 1-1 Government Response. The referenced provision will be incorporated. On: Aug 01 2016
Current Request Status: Request Closed Information for this report is procurement sensitive.
6607955 General Demolition Drawings Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please provide the as-built drawings for the existing structures to be demolished.
On: Jul 21 2016. Forward request by email.
1-0 Evaluation For Information Only. As-builts will be provided By: Drew Johnson; CENAO-EC-CQ Quality
Assurance Section; (757-201-7850) On: Jul 27 2016 1-1 Government Response. As-builts will be provided On: Aug 01 2016
Current Request Status: Request Closed Information for this report is procurement sensitive.
6608216 Contracting 35 20 23 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Given the shallow water leading into the facility and the small quantity of material to be dredged, dumping at an off shore site is extremely cost prohibitive. The cost of pre and post project dry-dock surveys of the barges used, and the cost of ocean-going tugs for towing are high, and the relatively small barges that must be used for this project because of the shallow water will make the cost per cubic yard excessive. The owner could realize a substantially lower price if the contractor were able to dispose of the dredged material in the Craney Island Rehandling Basin.
Please advise if this is a possibility.
On: Jul 21 2016. Forward request by email.
1-0 Evaluation For Information Only. The DLA Fuel Pier Project is outside the Geographic Service location of the Craney Island Rehandling Basin as outlined in the original authorizing language for the Craney Island Federal Civil Works Project. By: Drew Johnson; CENAO-EC-CQ Quality Assurance Section; (757- 201-7850) On: Jul 22 2016
1-1 Government Response. The DLA Fuel Pier Project is outside the Geographic Service location of the Craney Island Rehandling Basin as outlined in the original authorizing language for the Craney Island Federal Civil Works Project. On: Aug 01 2016 Current Request Status: Request Closed
Information for this report is procurement sensitive.
6611234 General S101 Section 31 62 16.16 Steel H Piles Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
What is the bid length of the production/test steel H-Piles?
On: Jul 25 2016. Forward request by email.
1-0 Evaluation For Information Only. Cutoff Elevation and Minimum Tip elevation for production and test
HP sections is called out on sheet S-601. HP bid length = (cutoff elevation - min tip elevation) + 4 ft. See also Section 31 62 16.16 Subpart 3.2.1 as the production pile length may increase based on results of the test pile program. By: Drew Johnson; CENAO-EC-CQ Quality Assurance Section; (757-201-7850) On:
Jul 27 2016
1-1 Government Response. Cutoff Elevation and Minimum Tip elevation for production and test HP sections is called out on sheet S-601. HP bid length = (cutoff elevation - min tip elevation) + 4 ft. See also Section 31 62 16.16 Subpart 3.2.1 as the production pile length may increase based on results of the test pile program. On: Aug 01 2016 Current Request Status: Request Closed
Information for this report is procurement sensitive.
6614557 Construction Phasing Solicitation Page 1 Box 13 Due Date Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Page 6 of 7ProjNet: Logged In User
On page one of the solicitation documents, the time and date of when the bids are due is left blank. Please clarify the due date and time by which bids must be submitted.
Question Submitted: July 27, 2016
(Attachment: Langley_Pier_Solicitation_Page_1.pdf) On: Jul 27 2016. Forward request by email.
1-0 Evaluation For Information Only. The time and date for receipt of proposals will be amended. Sealed offers are due at USACE Norfolk District (Contracting), 803 Front Street, Norfolk, VA 23510-1096, on 12 August 2016, 1200 EST. The solicitation and FBO posting will be amended to reflect the new date and time. By: Drew Johnson; CENAO-EC-CQ Quality Assurance Section; (757-201-7850) On: Jul 28 2016
1-1 Government Response. The time and date for receipt of proposals will be amended. Sealed offers are due at USACE Norfolk District (Contracting), 803 Front Street, Norfolk, VA 23510-1096, on 12 August 2016, 1200 EST. The solicitation and FBO posting will be amended to reflect the new date and time. On:
Aug 01 2016 Current Request Status: Request Closed
Information for this report is procurement sensitive.
Report Complete
UNCLASSIFIED\\FOR OFFICIAL USE ONLY