United States Army Corps of Engineers Norfolk District
Millennium Project Arlington National Cemetery Arlington, VA 22211 Contract No: W912DS-10-D-0002
Specifications (65%) Interim Design Submission
22 January 2013 in association with
Beyer Blinder Belle Architects & Planners LLP Sasaki Associates, Inc.
Rice Associates Wetlands Studies and Solutions, Inc.
NOT FOR C
ONSTRUCTIO
N
MILLENNIUM PROJECT CONTRACT W912DS-10-D-0002
ARLINGTON NAT'L CEMETERY, ARLINGTON VA 22 JAN 2013 - INTERIM DESIGN
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00 QUALITY CONTROL
01 45 01 QUALITY CONTROL SYSTEM (QCS)
01 45 23 TESTING AND INSPECTION SERVICES
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 20 ENVIRONMENTAL PROTECTION
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
01 58 00 PROJECT IDENTIFICATION
01 62 35 RECYCLED / RECOVERED MATERIALS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
03 33 00 CAST-IN-PLACE ARCHITECTURAL CONCRETE
03 48 21 PRECAST CONCRETE BURIAL CRYPTS
03 48 24 PRECAST CONCRETE COLUMBARIUM UNITS
DIVISION 04 - MASONRY
04 73 01 COLUMBARIUM NICHE COVERS, MARBLE
DIVISION 05 - METALS
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 20 00 FINISH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 14 00 FLUID-APPLIED WATERPROOFING
07 21 00 THERMAL INSULATION
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 71 00 DOOR HARDWARE
08 91 00 METAL WALL LOUVERS
DIVISION 09 - FINISHES
PROJECT TABLE OF CONTENTS Page 1
NOT FOR C
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 00 CERAMIC TILE, QUARRY TILE, AND PAVER TILE
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 28 13 TOILET ACCESSORIES
DIVISION 13 - SPECIAL CONSTRUCTION
13 12 13.15 REFLECTING POOL
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 07 19.00 40 PLUMBING PIPING INSULATION
22 52 00 FOUNTAIN PLUMBING SYSTEMS
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 60 13.00 40 LOW-VOLTAGE MOTORS
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 51 16 RADIO AND PUBLIC ADDRESS SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 05 26.00 40 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY
28 20 01.00 10 ELECTRONIC SECURITY SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 05 19 GEOTEXTILE
31 11 00 CLEARING AND GRUBBING
31 63 16 AUGER-PLACED GROUT PILES
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 10 DRAINAGE LAYER
32 11 16.16 BASE COURSE FOR RIGID AND SUBBASE COURSE FOR FLEXIBLE
PAVING
32 12 10 BITUMINOUS TACK AND PRIME COATS
PROJECT TABLE OF CONTENTS Page 2
NOT FOR C
32 12 17 HOT MIX BITUMINOUS PAVEMENT
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS
32 17 24.00 10 PAVEMENT MARKINGS
32 92 19 SEEDING
32 93 00 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 05 23.15 JACKING AND BORING PIPE
33 11 00 WATER DISTRIBUTION
33 30 00 SANITARY SEWERS
33 40 00 STORM DRAINAGE UTILITIES
33 46 13 FOUNDATION DRAINAGE SYSTEM
33 46 16 SUBDRAINAGE SYSTEM
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 3
NOT FOR C
SECTION 01 11 00.00 50
SUMMARY OF WORK
07/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E 2114 (2008) Standard Terminology for Sustainability Relative to the Performance of Buildings
1.2 DEFINITIONS
Definitions pertaining to sustainable development are as defined in ASTM E 2114, Section 01 35 40.00 50 ENVIRONMENTAL MANAGEMENT and/or Section 01 57 20.00 50 ENVIRONMENTAL PROTECTION, and as specified.
a. "Environmentally preferable products" have a lesser or reduced effect on the environment in comparison to conventional products and services. This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.
b. "Sustainability" is the balance of environmental, economic, and societal considerations.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00.00 50 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Upon receipt of Government Furnished Equipment, the Contractor shall submit records in accordance with paragraph entitled, "Government Furnished Property," of this section.
Submit the following items to the Contracting Officer:
Utility Outage Requests, G Utility Connection Requests, G
SECTION 01 11 00 Page 1
NOT FOR C
1.4 WORK COVERED BY CONTRACT DOCUMENTS
1.4.1 Project Description
The Millennium Project will be developed to increase burial space at Arlington National Cemetery (ANC). Construction includes casket burial sections, in-ground sites for ashes of cremated service members, and both columbarium niche courts and niche walls. The site will include two (2) Committal Service Shelters for service participants. Supporting facilities include water fountains, waterlines, sanitary sewer, storm drainage, underground electrical and communications/information systems, stream restoration, landscaping, retaining walls, perimeter fencing, vehicle and pedestrian access roads and walks, and security systems.
1.4.2 Location
The Millennium project is located on a 27-acre site consisting of Section 29 of the existing ANC and the old picnic grounds of Joint Base Fort Myer / Henderson Hall (JBM-HH).
1.5 WORK RESCHEDULING
There are a number of restrictions set in place for this project to ensure minimal interference with the numerous funerals and ceremonies that take place every year at the facility.
Contracting Officer reserves the right to change these restrictions at any time during the period of performance. The government will make every attempt to adequately forewarn the Contractor of pending changes with a goal to provide minimum 24 hour notification each time the new restrictions are invoked. Further allowance for two additional calendar days where excavation and subsurface activity abeyance shall be imposed.
Contractor shall allow for a maximum of three calendar days where construction activity is determined prohibitive. In most instances requiring work rescheduling the time periods will range from 10 minutes to 4 hour delay.
1.6 OCCUPANCY OF PREMISES
The buildings around the construction site will be occupied during performance of work under this Contract.
Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, use of approaches, and egress from the site.
1.7 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or
SECTION 01 11 00 Page 2
NOT FOR C
adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
c. Remove all temporary construction access/egress elements and return the any alteration made during the construction period to and acceptable finished quality level.
1.7.1 DAMAGE TO GOVERNMENT PROPERTY, INJURIES, OR DEATH
At the Government's discretion, the Contractor shall either repair or replace property, or reimburse the Government for property damage. the Contractor shall be aware that Government property - beyond standard structures and equipment - also includes headstones, monuments, floral decorations placed by visitors and next of kin, trees, beds, and turf (for example, wounded trees or scalped turf, as well as headstones, shall be repaired or replaced at no additional cost to the Government). The Contractor shall assume all liability for negligent injury or death to visitors and/or employees during the performance of this contract.
1.8 ON-SITE PERMITS
1.8.1 Utility Outage Requests and Utility Connection Requests
Notify the Contracting Officer at least 72 hours prior to starting excavation work. Contractor is responsible for marking and verifying all utilities not marked.
The Contractor shall verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed, but indicated in locations to be transversed by piping, ducts, and other work to be installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
Work shall be scheduled to hold outages to a minimum.
Utility outages and connections requiring less than two hours of interruption during the prosecution of work that affect existing systems shall be arranged for at the convenience of the Government. All such requests must be submitted in writing to the contracting officer 36 hours in advance.
Utility outages and connections requiring more than two hours of interruption during the prosecution of work that affect existing systems shall be arranged for at the convenience of the Government. All such requests must be submitted in writing to the contracting officer 7 calendar days in advance. All such outages shall be scheduled outside the regular working hours or on weekends.
In either case, no such work shall proceed without prior written approval by the contracting officer. It is the sole discretion of the Contracting Officer to permit or deny utility outage requests by the Contractor.
Contractor shall not be entitled to additional payment for utility outages and connections required to be performed outside the regular work hours.
Requests for utility outages and connections shall be made in writing to the Contracting Officer. Each request shall state the system involved, SECTION 01 11 00 Page 3
NOT FOR C
area involved, approximate duration of outage, and the nature of work involved.
1.8.2 Borrow and Excavation Permits
ACTIVITY SUBMISSION DATE SUBMISSION FORM
Excavation Permits three calendar days prior to work written
Permits shall be posted at a conspicuous location in the construction area.
1.9 LOCATION OF UNDERGROUND FACILITIES
Obtain digging permits prior to start of excavation by contacting the Contracting Officer 14 calendar days in advance. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground, or paved surface where existing underground utilities or utilities encased in pier structures are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.9.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work. Contact Miss Utility 48 hours prior to excavating.
Contractor is responsible for marking all utilities not marked by Miss Utility.
1.10 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
The Contractor shall safeguard all Government property provided for Contractor use during the course of the contract. At the close of each work period, Government facilities, equipment, and materials furnished shall be secured.
1.10.1 Delivery Schedule
NOT USED.
1.10.2 Delivery Location
NOT USED
1.11 GOVERNMENT-INSTALLED WORK
The Contractor will be responsible to coordinate installation/testing of communication lines as well as installation of systems office furniture provided by third party vendors to the Government
The materials and equipment are located within 25 miles of the jobsite.
SECTION 01 11 00 Page 4
NOT FOR C
Notify the Contracting Officer in writing at least 14 calendar days in advance of the date on which the materials and equipment are required.
Materials and equipment will be available immediately after award of the contract.
1.12 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged shall remain the property of the Government.
The salvaged property shall be segregated, itemized, delivered, and off-loaded at the Government designated storage area located within 25 miles of the construction site.
Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 5
NOT FOR C
SECTION 01 14 00.00 50
WORK RESTRICTIONS
07/11
PART 1 GENERAL
1.1 SPECIAL SCHEDULING REQUIREMENTS
a. The Arlington National Cemetery will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the site.
b. Contractor is responsible to ensure that not contract work interferes with any funeral, ceremony, procession, or visitation to be delayed, altered, or otherwise impacted in such a way that the dignity or security of the event is compromised. The contractors site manager is responsible for staying abreast of all such upcoming events. A list of scheduled ceremonies will be provided each week prior to the event, and a list of scheduled funerals will be provide the day prior to the service. As a rule of thumb, work - especially with power equipment -within 1,000 feet of funeral or ceremony is not acceptable.
c. Work required to complete this scope takes place in very close proximity to the Tomb of the Unknowns. In this location the guard is changed every hour on the hour from October 1 to March 31 in an elaborate ritual. The guard is changed from April 1 through September 30 on the half hour. In accordance with para 1.1.d. the Contractor shall cease work accordingly during the ceremony.
d. All work involving use of tools or equipment which would interfere with any interment service conducted in the immediate vicinity of the work sites shall cease until the service has been competed. This scope of work takes place in the immediate vicinity of the Tomb of the Unknown Soldier. There is a changing of the guard ceremony that takes place every hour and lasts approximately 10 mins. All work within 200 feet of this ceremony shall cease during the ceremony.
e. Permission to interrupt any Activity roads, railroads, and/or utility service shall be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification. These site specific regulations will be discussed in more detail at the preconstruction conference. Information is also available upon request through the Contracting Officer's Representative and Owners Representative.
SECTION 01 14 00 Page 1
NOT FOR C
1.2.1.1 Subcontractors and Personnel Contacts
Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.2.1.2 Identification Badges and Installation Access
The Contractor shall carry passes issued by Arlington National Cemetery for all vehicles entering the Cemetery, whether company-owned or employee's private vehicles. The issued passes should be visibly displayed on the dashboard of the vehicle at all times. All vehicles with passes shall meet State of Virginia inspection, safety, licensing, registration, and insurance requirements. The Contractor Site Manager will maintain a list of all vehicles and individuals issued such passes. All Contractor employees shall also keep positive, photographic identification on their persons at all times.
The Contractor shall prohibit the use of Government issued passes by any persons other than the Contractor's employees.
Contractor shall maintain an active and accurate daily attendance of all employees working on the job site. Contractor shall provide the Government with a hard copy of the list every time it is updated; remove Contractor employee names not actively working on the site and add new employees names accordingly. All Contractor employees working on the project not listed will be prohibited from the immediate work area. Government reserves the right to reject contractors from the list at any time and thereby prohibit them from the site.
The Contractor shall comply with all security rules, regulations, and restrictions nominally associated with operations of the Arlington National Cemetery operation.
The primary entrance to Arlington National Cemetery shall be Ord & Weitzel Gate unless otherwise directed by the Contracting Officer's Representative.
Contractor shall be provided with a key card or security code and shall ensure that personnel are available, as necessary, to man the gate outside of normal working hours to accommodate deliveries/Contractor personnel access during those times. Routing to project site must be coordinated with the Contracting Officer's Representative.
1.2.1.3 Personnel Entry Approval
Failure to obtain entry approval will not affect the contract price or time of completion.
1.2.1.4 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installations under the cognizance of Arlington National Cemetery except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
SECTION 01 14 00 Page 2
NOT FOR C
1.2.1.5 Contractor Conduct
Arlington National Cemetery has a zero tolerance policy on use, sale, and or distribution of all forms of alcohol and drugs.
The Contractor shall maintain a neat and professional appearance throughout its workforce including vehicles, equipment, work sites, staging areas, and employees.
Contractor employees shall behave with appropriate decorum, courtesy, and respect while within the grounds of the Cemetery. Shouting, cursing, angry outbursts, sleeping, intoxification, violence, or criminal acts of any kind will not be tolerated and is cause for immediate and permanent removal from the Cemetery premises. Criminal conduct is further subject to prosecution by the Government.
1.2.1.6 Uniforms
Complete uniforms shall be worn by all contract employees at all times.
Uniforms are selected by the Contractor, and shall provide a uniform appearance from one employee to the next including all visible outer clothing covering the head, torso, legs, and feet. Shorts are not permitted. Appropriateness of selected uniforms is otherwise subject to review by the Contracting Officers Representative.
1.2.2 Working Hours
Regular working hours shall consist of 8 hour period from 06:30 am to 04:30 PM, Monday through Friday, excluding Government holidays.
During the weekdays, Monday through Friday, deliveries to the jobsite will be restricted to the hours of 06:30 a.m. to 08:00 a.m. With 24 hour written notification by the Contractor deliveries on weekends and/or holidays and/or after regular working hours may be made available. All such deliveries shall be pre-approved by the contacting officer - but are not guaranteed.
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer. Schedule contract work such as to make utility cut overs after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
Alternative work/delivery periods for nights, weekends and holidays are available upon written request by the Contractor. Requests for additional work and/or regular extended hours shall require written approval from the Contracting Officer 7 days in advance of the proposed work period.
1.2.4 Exclusionary Period
No work shall be performed outside the previously stated hours without prior written approval of the Contracting Officer.
SECTION 01 14 00 Page 3
NOT FOR C
1.2.5 Occupied and Existing Building[s]
The Contractor will be working in an existing building and around existing buildings which are occupied. Do not enter the building[s] without prior approval of the Contracting Officer.
The existing buildings and their contents shall be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the local construction site during the construction period.
1.2.6 Utility Cut overs and Interruptions
a. Make utility cut overs and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, and natural gas shall be considered utility cut overs pursuant to the paragraph entitled "Work Outside Regular Hours."
d. Operation of Station Utilities: The Contractor shall not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and natural gas services. The Government will operate the control devices as required for normal conduct of the work. The Contractor shall notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.3 SECURITY REQUIREMENTS
Contract Clause "FAR 52.204-2, Security Requirements and Alternate II," applies.
The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 14 00 Page 4
NOT FOR C
SECTION 01 30 00.00 50
ADMINISTRATIVE REQUIREMENTS
07/11
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00.00 50 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View location map; G
Progress and completion pictures; G
SD-04 Samples
Color boards; G
1.2 VIEW LOCATION MAP
Submit to the Contracting Officer, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.3 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color 8MP minimum resolution in JPEG file format showing the sequence and progress of work.
Take a minimum of 30 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer. Submit a view location sketch indicating points of view. Submit with the monthly invoice two sets of digital photographs each set on a separate CD-R, cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Photographs for each month shall be in a separate monthly directory and each file shall be named to indicate its location on the view location sketch. The view location sketch shall also be provided on the CD as digital file. All file names shall include a date designator. Cross reference submittals in the appropriate daily report. Photographs shall be provided for unrestricted use by the Government.
1.4 MINIMUM INSURANCE REQUIREMENTS (INSTALLATION REQUIREMENTS)
Note that insurance requirements spelled out in this paragraph are not meant to supersede or replace those put forth by FAR, DFAR, and/or the Contracting Officer in Division 00. These requirements merely represent minimum standards set forth by the installation. The Contractor shall be responsible for providing insurance as required in other sections of the contract. Procure and maintain during the entire period of performance
SECTION 01 30 00 Page 1
NOT FOR C
under this contract the following minimum insurance coverage:
a. Comprehensive general liability: $500,000 per occurrence
b. Automobile liability: $200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage
c. Workmen's compensation as required by Federal and State workers' compensation and occupational disease laws.
d. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers,
e. Others as required by the State of Virginia
1.5 SUPERVISION
Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.
1.6 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule prices, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work shall also attend.
1.7 PERIODIC PROGRESS MEETINGS
The Contractor must be agreeable to any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The Contracting Officer, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the Contracting Officer will apprise the Contractor of how the Government views the contactor's performance and the Contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.
1.8 FACILITY TURNOVER PLANNING MEETINGS (Red Zone - RZ)
Key personnel will meet to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start the turnover process at the Preconstruction Conference meeting and convene at the Facility Turnover Meetings once the project has reached approximately 75 percent completion or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first. The Contracting Officer's Representative will lead the meetings and guide discussions based on an agenda provided by the Government. The facility Turnover effort shall include the following:
a. Preconstruction Meeting - Contracting Officer's Representative (COR)
SECTION 01 30 00 Page 2
NOT FOR C
will provide the RZ Checklist and the Contractor, Client, and USACE Representatives will compare Contractor's schedule to RZ Checklist items.
b. Facility Turnover Meetings
1. Fill in the RZ Checklist including Contractor, Client, and USACE Checklist Items and assign a person responsible for each item and a due date. The Contractor's Representative will facilitate the assignment of responsibilities, fill out the NRZ Checklist, and discuss "Interim DD From 1354" requirements.
2. Review the Contractor's updated schedule. The Contractor shall develop a integrated plan for the completion of all Contractor, Client, and USACE Checklist items.
3. Confirm that all RZ Checklist items will be completed on time for the scheduled Facility Turnover.
1.9 AVAILABILITY OF CADD DRAWING FILES
After award and upon request, the electronic "Computer-Aided Drafting and Design (CADD)" drawing files will only be made available, as available in Government electronic record, to the Contractor for use in preparation of construction data related to the referenced contract subject to the following terms and conditions. Request specific drawing numbers of files required; the entire set of drawing files will not be provided.
Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government.
The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic CADD drawing files are not construction documents.
Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction drawings and data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.
SECTION 01 30 00 Page 3
NOT FOR C
1.10 ELECTRONIC MAIL (E-MAIL) ADDRESS
The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc. Multiple email address will not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 30 00 Page 4
NOT FOR C
SECTION 01 32 01.00 50
PROJECT SCHEDULE
07/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00.00 50 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Schedule; G
1.3 QUALITY ASSURANCE
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating (activity status) and preparation of reports. The authorized representative shall be experienced in scheduling and have previously developed, created, and maintained at least 2 electronic schedules for projects similar in nature and complexity to this project and shall be experienced in the use of the scheduling software that meets the requirements of this specification.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design and construction sequences, is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development.
Subcontractors and suppliers working on the project shall also contribute
SECTION 01 32 01 Page 1
NOT FOR C
in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.
3.1.1 Approved Project Schedule
Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
3.1.2 Schedule Status Reports
Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
3.1.3 Default Terms
Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination, by the Contracting Officer, that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.
3.2 BASIS FOR PAYMENT AND COST LOADING
Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment. Lack of an approved schedule update, or qualified scheduling personnel, will result in the inability of the Contracting Officer to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the preliminary, initial and subsequent schedule updates. In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
The computer software system utilized to produce and update the Project Schedule shall be capable of meeting all requirements of this specification. Failure of the Contractor to meet the requirements of this specification will result in the disapproval of the schedule.
SECTION 01 32 01 Page 2
NOT FOR C
3.3.1 Critical Path Method
Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule. Prepare the Project Schedule using the Precedence Diagram Method (PDM).
3.3.2 Level of Detail Required
Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2.1 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities shall have Original Durations (OD) greater than 20 work days or 30 calendar days. Procurement activities are defined herein.
3.3.2.2 Procurement Activities
The schedule must include activities associated with the submittal, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.
3.3.2.3 Mandatory Tasks
The following tasks must be included and properly scheduled:
a. Submission, review and acceptance of design packages.
b. Submission of mechanical/electrical/information systems layout drawings.
c. Submission and approval of O & M manuals.
d. Submission and approval of as-built drawings.
e. Submission and approval of 1354 data and installed equipment lists.
g. Submission of TAB specialist design review report.
o. Other systems testing, if required.
p. Contractor's pre-final inspection.
q. Correction of punchlist from Contractor's pre-final inspection.
r. Government's pre-final inspection.
s. Correction of punch list from Government's pre-final inspection.
t. Final inspection.
SECTION 01 32 01 Page 3
NOT FOR C
3.3.2.4 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.2.5 Activity Responsibility Coding (RESP)
Assign responsibility Code for all activities to the Prime Contractor, Subcontractor or Government agency responsible for performing the activity. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements. Code all activities not coded with a Government Responsibility Code to the Prime Contractor or Subcontractor responsible to perform the work. Activities shall not have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record); ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE). Unacceptable code values are abbreviations of the names of subcontractors.
3.3.2.6 Activity Work Area Coding
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew, from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.
Activities shall not have more than one Work Area Code. Not all activities are required to be Work Area coded. A lack of Work Area coding will indicate the activity is not resource or space constrained.
3.3.2.7 Contract Changes/Requests for Equitable Adjustment (REA) Coding
(MODF)
Assign Activity code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by the Contracting Officer, with a Contract Changes/REA Code. Key all Code values to the Government's modification numbering system. Any activity or sequence of activities added to the schedule as a result of alleged constructive changes made by the Government may be added to a copy of the current schedule, subject to the approval of the Contracting Officer.
Assign Activity codes for these activities with a Contract Changes/REA Code. Key the code values to the Contractor's numbering system. Approval to add these activities does not necessarily mean the Government accepts responsibility and, therefore, liability for such activities and any associated impacts to the schedule, but rather the Government recognizes such activities are appropriately added to the schedule for the purposes of maintaining a realistic and meaningful schedule. Such activities shall not be Responsibility Coded to the Government unless approved. An activity shall not have more than one Contract Changes/REA Code.
SECTION 01 32 01 Page 4
NOT FOR C
3.3.2.8 Contract Line Item (CLIN) Coding (BIDI)
Code all activities to the CLIN on the Contract Line Item Schedule to which the activity belongs. An activity shall not contain more than one CLIN Item Code. CLIN Item code all activities, even when an activity is not cost loaded.
3.3.2.9 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities based upon the phase of work in which the activity occurs. Code activities to a Construction Phase. Code fast track construction phases proposed by the Contractor to allow filtering and organizing the schedule by fast track design and construction packages. If the contract specifies construction phasing with separately defined performance periods, identify a Construction Phase Code to allow filtering and organizing the schedule accordingly. Each activity shall be identified with a single project phase and have only one Phase of Work code.
3.3.2.10 Category of Work Coding (CATW)
Assign Category of Work Code to all Activities based upon the category of work to which the activity belongs. Category of Work Code must include, but is not limited to: construction submittal approvals, Acceptance, Procurement, Fabrication, Delivery, Weather Sensitive Installation, Non-Weather Sensitive Installation, Start-Up, Test and Turnover. Assign a Category of Work Code to each activity. Each activity shall have only one Category of Work Code.
3.3.2.11 Definable Features of Work Coding (FOW1, FOW2, FOW3)
Assign a Definable Feature of Work Code to appropriate activities based on the definable feature of work to which the activity belongs. Definable Feature of Work is defined in Specification Section 01 45 00.00 50 QUALITY CONTROL. An activity shall not have more than one Definable Feature of Work Code. Not all activities are required to be Definable Feature of Work Coded.
3.3.3 Scheduled Project Completion and Activity Calendars
The schedule interval shall extend from NTP date to the required contract completion date. The contract completion activity (End Project) shall finish based on the required contract duration in the accepted contract proposal, as adjusted for any approved contract time extensions. The first scheduled work period shall be the day after NTP is received by the Contractor. Schedule activities on a calendar to which the activity logically belongs. Activities may be assigned to a 7 day calendar when the contract assigns calendar day durations for the activity such as a Government Acceptance activity. If the Contractor intends to perform physical work less than seven days per week, schedule the associated activities on a calendar with non-work periods identified including weekends and holidays. Assign the Category of Work Code - Weather Sensitive Installation to those activities that are weather sensitive.
Original durations must account for anticipated normal adverse weather.
The Government will interpret all work periods not identified as non-work periods on each calendar as meaning the Contractor intends to perform work during those periods.
SECTION 01 32 01 Page 5
NOT FOR C
3.3.3.1 Project Start Date
The schedule shall start no earlier than the date on which the NTP was acknowledged. Include as the first activity in the project schedule an activity called "Start Project"( or NTP). The "Start Project" activity shall have an "ES" constraint date equal to the date that the NTP was acknowledged, and a zero day duration.
3.3.3.2 Schedule Constraints and Open Ended Logic
Constrain completion of the last activity in the schedule by the contract completion date. Schedule calculations shall result in a negative float when the calculated early finish date of the last activity is later than the contract completion date. Include as the last activity in the project schedule an activity called "End Project". The "End Project" activity shall have an "LF" constraint date equal to the contract completion date for the project, and with a zero day duration or by using the "project must finish by" date in the scheduling software. The schedule shall have no constrained dates other than those specified in the contract. The use of artificial float constraints such as "zero fee float" or "zero total float" are typically prohibited. There shall only be 2 open ended activities:
Start Project (or NTP) with no predecessor logic and End Project with no successor logic.
3.3.3.3 Early Project Completion
In the event the Preliminary or Initial project schedule calculates an early completion date of the last activity prior to the contract completion date, identify those activities that it intends to accelerate and/or those activities that are scheduled in parallel to support the Contractor's "early" completion. The last activity shall have a late finish constraint equal to the contract completion date and the schedule will calculate positive float. The Government will not approve an early completion schedule with zero float on the longest path. The Government is under no obligation to accelerate activities for which it is responsible to support a proposed early contract completion.
3.3.3.4 Recognized Holidays
The following Government Holidays are recognized and must be reflected in the schedule as non-working days: New Year's day, Martin Luther King Jr's Birthday, President's day, Memorial day, Independence day, Labor day, Columbus day, Veteran's day, Thanksgiving day, and Christmas day.
Permission to work on…