W911YN17R0003_Solicitation_QA_10-10-17.docx

DOCX document 17 KB Posted

Attached to
MILCON project DBEH143000 Space Control Facility, Cape Canaveral AFS
Solicitation number
W911YN-17-R-0003
Issued by

About this file

Responses to Questions as of 10-10-17

View the file

Other files

File Type Posted
W911YN17R00030003.pdf PDF
W911YN17R0003_Solicitation_QA_11-29-17.docx DOCX document
W911YN17R00030002.pdf PDF
W911YN17R0003_Solicitation_QA_11-21-17.docx DOCX document
SKE-01.pdf PDF
W911YN17R0003_Solicitation_QA_11-7-17.docx DOCX document
W911YN17R00030001.pdf PDF
W911YN17R0003_Solicitation_QA_11-2-17.docx DOCX document
W911YN17R0003_Solicitation_QA_10-31-17.docx DOCX document
W911YN17R0003_Solicitation_QA_10-30-17.docx DOCX document
Pre-Proposal_Site_Visit_Minutes.pdf PDF
W911YN17R0003_Solicitation_QA_10-24-17.docx DOCX document
093013_Ceramic_Tiling_update1.pdf PDF
W911YN17R0003_Solicitation_QA_10-16-17.docx DOCX document
EXHIBIT_A_PERFORMANCE_RELEVANCY_QUESTIONNAIRE.doc DOC document
EXHIBIT_D_-_Proposal_Inquiry_Format.docx DOCX document
EXHIBIT_C_REFERENCE_QUESTIONNAIRE_PACKAGE.doc DOC document
W911YN17R0003.pdf PDF
EXHIBIT_B_SUBCONTRACTOR_INFORMATION_AND_CONSENT_FORM.doc DOC document
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911YN-17-R-0003

Solicitation Questions and Answers

Q1. Please advise if the Project Manager is required to be on site ‘full-time’ for the duration of the project.

A1. There is no written requirement found that requires the Project Manager to be on site at all times.

Q2. Please advise if the Site Superintendent is required to be on site ‘full-time’ for the duration of the project.

A2. The superintendent is required to be on site at all times when work is taking place and shall have full authority to act for the Contractor.

Q3. Please advise if the Quality Control Manager is required to be on site ‘full-time’ for the duration of the project.

A3. There is no written requirement found that specifically requires the QC Manager to be on site at all times. The Contractor shall adhere to Section 01 40 00 “Quality Requirements” and any and all quality requirements of the contract documents.

Q4. Please advise if the Safety Manager is required to be on site ‘full-time’ for the duration of the project.

A4. The Site Safety and Health Officer (SSHO) must be at the work site at all times to implement and administer the Contractor’s safety program and Accident Prevention Plan. The SSHO cannot be the QC Manager or Superintendent.

Q5. Will there be a signage schedule issued for room identification signs and dimensional letters, reference Spec Section 101419 & 101423.13?

A5. Specification section 101419 will no longer apply as FLANG has requested that no signage be applied to building exterior. Signage schedule for interior room identification will follow Architect’s room finish legend, confirm approval with Contracting Officer’s Representative (COR).

Q6. Standard Form 1442 (Block 13, Item B) indicates that an offer guarantee is required. Please provide the requirements of the offer guarantee and advise where it is to be included within the proposal.

A6. Please see 52.228-1 “Bid Guarantee”, and include with Volume 1 documents.

Q7. The requirements for Subfactor 1 “Experience and Capability” include the stipulation that resumes or experience cut sheets be limited to (2) pages each and that these pages are not part of the page count. Please advise the page limit for this Subfactor exclusive of the resumes or experience cut sheets that may be provided.

A7. There is no stated page limit.

Q8. Is there a means by which projects that may demonstrate experience with SCIF building on behalf of Government agencies, but that are also subject to Non-Disclosure Agreement(s), be considered in evaluation of the requested proposal?

A8. An offeror will need to provide sufficient information that allows for a meaningful evaluation to establish technical experience and capability are acceptable as described in the solicitation. Information provided needs to be verifiable.

Q9. Please clarify the number of projects to be submitted in Volume 2, Part 2, Exhibit A, Performance Relevancy Questionnaire. In Section 2.5.3.4, it states 3-5 projects, but on Exhibit A, Performance Relevancy Questionnaire, it states no more than 3 projects.

A9. Section 00120 paragraph 2.5.3.4 should read, “Prepare not more than three (3) of these documents.”

Q10. In Section 00120, 1.1 of the solicitation, please provide clarification on how the proposal will be evaluated: lowest price, technically acceptable or best value, technically acceptable?

A10. Lowest Price Technically Acceptable (LPTA). LPTA is in the “Best Value Continuum”, (see FAR Subpart 15.101).

Q11. Section 00110 –Proposal Content -Is there a page limit for Volume 1?

A11. There is no page limit.

Q12. Section 2.1.1 – Volume 2, Part 1 – Technical Capability Proposal -Is there a page limit for Subfactor 3 - Quality Control?

A12. There is no stated page limit.

Q13. Section 2.1.1 – Volume 2, Part 2 – Past/Present Performance Information -Is there a page limit for Past Performance information?

A13. There is no stated page limit.

Q14. Page 13, 2.5.2.2 – Subfactor 1 Experience & Capability -Can you please explain “experience cut sheets”?

A14. This should be taken to mean any sheet with experience and capability information for individuals that is not in standard resume format. There is no particular format required, but limit to two pages for each key individual.

Q15. Key Personnel Descriptions, page 24, Paragraph 36 -Are all 4 Key Personnel required to be onsite at all times?

A15. See answers to questions 1 through 4.

Q16. Section 00110, paragraph 2.5.2.1. reads, “Volume 2 Part 1 is comprised of four (4) subfactors”, however there are only three subfactors listed. Please clarify.

A16. Paragraph 2.5.2.1 should read, “three (3) subfactors”.