AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

FY17 Portage Lake Revetment Repair, Onekama Tow nship, Michigan

1. The draw ings and specifications are hereby changed as described on the follow ing pages.

2. The Bid Due Date is hereby changed from September 6, 2017 to September 7, 2017, at 2:00 p.m. Eastern Time, at w hich time bids w ill be publicly opened at the Corps of Engineers Contracting Office in Detroit, Michigan.

3. All other provisions, clauses, terms, conditions, and requirements remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 31-Aug-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911XK17B0006

X 9B. DATED (SEE ITEM 11)

07-Aug-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

31-Aug-2017

CODE

CONTRACTING BRANCH

USACE DETROIT DISTRICT

477 MICHIGAN AVENUE, 7TH FLOOR

DETROIT MI 48226-4523

W911XK 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W911XK17B0006

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 06-Sep-2017 02:00 PM to 07-Sep-2017 02:00 PM.

The following have been added by full text:

AMENDMENT NO. 0002

The following changes are hereby incorporated into the Solicitation and resulting contract.

CHANGES TO THE DRAWINGS

REPLACE

Drawing Sheet CO101 from the original solicitation.

WITH:

Drawing Sheet CO101 - Amd 0002.

DESCRIPTION OF CHANGE:

Updated dimensions of required and optional areas to be consistent with other sheets. Replaced references to concrete walk and with references to concrete cap. Added transition area and associated notes for Section H.

Drawing Sheet CO501 from the original solicitation.

WITH:

Drawing Sheet CO501 - Amd 0002.

DESCRIPTION OF CHANGE:

Deleted “North Side” on detail 5 as it pertains to entire project.

Drawing Sheet S-301 from the original solicitation.

WITH:

Drawing Sheet S-301 - Amd 0002.

DESCRIPTION OF CHANGE:

Updated stationing of required and optional areas to be consistent with other sheets.

W911XK17B0006

CHANGES TO THE SPECIFICATIONS

Section 31 41 17 Steel Sheet Piling

REPLACE

Section 31 41 17 from the original solicitation.

WITH:

Section 31 41 17 - Amd 0002.

DESCRIPTION OF CHANGE:

Changed paragraph 1.1 to remove anchor walls and to include special piles & pipe pile termination.

Changed paragraph 1.3 to define cases when a detailed design analysis is required for submittal.

(End of Summary of Changes)