Abstract_-_W911XK17B0006_Portage_Lake_Revetment.pdf

PDF 44 KB Posted

Attached to
Portage Lake Revetment Repair
Solicitation number
W911XK17B0006
Issued by

About this file

Abstract of Bids

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAGE OF PAGES

1 3

Robert W. Austin, Contracting Officer

DATE SIGNED

7A.

ITEM NO. 7B. DESCRIPTION OF OFFERED ITEM 7C.

QUANTITY D. UNIT E. UNIT PRICE F. ESTIMATED

AMOUNT D. UNIT PRICE E. ESTIMATED

AMOUNT D. UNIT PRICE E. ESTIMATED

AMOUNT

0001 Portage Lake Revetment Repair 1 JOB $1,634,488.00 $1,634,488.00 $2,950,000.00 $2,950,000.00 $1,836,000.00 $1,836,000.00

0002 Cover/Armor Stone 6,300 Ton $140.00 $882,000.00 $73.00 $459,900.00 $75.00 $472,500.00

0003 Underlayer Stone 1,900 Ton $134.00 $254,600.00 $78.00 $148,200.00 $70.00 $133,000.00

0004 Mattres Stone 8,100 Ton $121.00 $980,100.00 $60.00 $486,000.00 $42.00 $340,200.00

0005 Splash Stone 1,100 Ton $133.00 $146,300.00 $78.00 $85,800.00 $80.00 $88,000.00

0006 Sheet Pile Fill Stone 2,400 Ton $122.00 $292,800.00 $52.00 $124,800.00 $60.00 $144,000.00

$4,190,288.00 $4,254,700.00 $3,013,700.00

0007 Option 1 - Portage Lake Revetment Repair 1 JOB $433,213.00 $433,213.00 $600,000.00 $600,000.00 $330,000.00 $330,000.00

0008 Option 1 - Splash Stone 370 Ton $129.00 $47,730.00 $78.00 $28,860.00 $80.00 $29,600.00

0009 Option 1 - Sheet Pile Fill Stone 450 Ton $117.00 $52,650.00 $52.00 $23,400.00 $60.00 $27,000.00

$533,593.00 $652,260.00 $386,600.00

0010 Option 2 - Portage Lake Revetment Repair 1 JOB $976,239.00 $976,239.00 $1,100,000.00 $1,100,000.00 $834,000.00 $834,000.00

0011 Option 2 - Splash Stone 850 Ton $123.00 $104,550.00 $78.00 $66,300.00 $80.00 $68,000.00

0012 Option 2 - Sheet Pile Fill Stone 1,175 Ton $119.00 $139,825.00 $52.00 $61,100.00 $60.00 $70,500.00

$1,220,614.00 $1,227,400.00 $972,500.00

$5,944,495.00 $6,134,360.00 $4,372,800.00

3. DATE OPENED

9/7/17

2. DATE ISSUED

8/7/17

US Army Corps of Engineers Directorate of Contracting, Detroit Branch

ABSTRACT OF BIDS - CONSTRUCTION 1. SOLICITATION NUMBER

W911XK-17-B-0006

4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

SIGNATURE

5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS

A. HIRED LABOR

A. OFFEROR: A. OFFEROR:

NO. 2

A. OFFEROR:

Midwest Construction

Company

(Check A, B, or C and complete D, E, and F) NO. 1 NO. 3

Bid withdrawn and replaced with Offer No. 5

Luedtke Engineering Company

B. BID SECURITY (Type and Amount) Bond, 20%

C. AMENDMENTS ACKNOWLEDGED

Not Applicable

B. BID SECURITY (Type and Amount) Bond, 20%

C. AMENDMENTS ACKNOWLEDGED

0001, 0002

TOTAL AMOUNT OF BASE BID

B. REASONABLE CONTRACT

(Without Profit)

C. REASONABLE CONTRACT

(Including Profit)

6. NUMBER OF AMENDMENTS ISSUED

FY17 Portage Lake Revetment Repair Onekama Township, Michigan

X

BASE BID

OPTION 1

TOTAL AMOUNT OF OPTION 1

OPTION 2

TOTAL AMOUNT OF OPTION 2

TOTAL BID AMOUNT

BASE PLUS OPTION 1 AND OPTION 2

AUSTIN.ROBERT.WAYNE.JR.1186713296

Digitally signed by AUSTIN.ROBERT.WAYNE.JR.1186713296 DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, ou=USA, cn=AUSTIN.ROBERT.WAYNE.JR.1186713296 Date: 2017.09.11 11:17:00 -04'00'

2 3

3A.

ITEM NO 3B. DESCRIPTION OF OFFERED ITEM 3C.

QUANTITY 3D. UNIT D. UNIT PRICE E. ESTIMATED

AMOUNT D. UNIT PRICE E. ESTIMATED

AMOUNT D. UNIT PRICE E. ESTIMATED

AMOUNT

0001 Portage Lake Revetment Repair 1 JOB $2,271,000.00 $2,271,000.00 $1,684,900.00 $1,684,900.00 $1,885,150.00 $1,885,150.00

0002 Cover/Armor Stone 6,300 Ton $69.15 $435,645.00 $117.00 $737,100.00 $80.00 $504,000.00

0003 Underlayer Stone 1,900 Ton $59.75 $113,525.00 $85.00 $161,500.00 $70.00 $133,000.00

0004 Mattres Stone 8,100 Ton $56.40 $456,840.00 $115.00 $931,500.00 $65.00 $526,500.00

0005 Splash Stone 1,100 Ton $77.75 $85,525.00 $90.00 $99,000.00 $75.00 $82,500.00

0006 Sheet Pile Fill Stone 2,400 Ton $43.60 $104,640.00 $60.00 $144,000.00 $50.00 $120,000.00

$3,467,175.00 $3,758,000.00 $3,251,150.00

0007 Option 1 - Portage Lake Revetment Repair 1 JOB $647,300.00 $647,300.00 $350,700.00 $350,700.00 $340,000.00 $340,000.00

0008 Option 1 - Splash Stone 370 Ton $84.20 $31,154.00 $90.00 $33,300.00 $75.00 $27,750.00

0009 Option 1 - Sheet Pile Fill Stone 450 Ton $65.20 $29,340.00 $60.00 $27,000.00 $50.00 $22,500.00

$707,794.00 $411,000.00 $390,250.00

0010 Option 2 - Portage Lake Revetment Repair 1 JOB $1,197,000.00 $1,197,000.00 $690,000.00 $690,000.00 $800,000.00 $800,000.00

0011 Option 2 - Splash Stone 850 Ton $68.05 $57,842.50 $90.00 $76,500.00 $75.00 $63,750.00

0012 Option 2 - Sheet Pile Fill Stone 1,175 Ton $52.50 $61,687.50 $60.00 $70,500.00 $50.00 $58,750.00

$1,316,530.00 $837,000.00 $922,500.00

$5,491,499.00 $5,006,000.00 $4,563,900.00 Note: Italicized text indicates that a typographic error (decimal location) was corrected from the bid form.

C. AMENDMENTS ACKNOWLEDGED

B. BID SECURITY (Type and Amount)

Marine Tech LLC Architectural Consulting Group

0001, 0002 0001, 0002

B. BID SECURITY (Type and Amount)

C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED

Bond, 20%

A. OFFEROR:

Bond, 20%

NO. 4 NO. 5FY17 Portage Lake Revetment Repair Onekama Township, Michigan

BASE BID

TOTAL AMOUNT OF BASE BID

INSTRUCTIONS - Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 14 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419s for contract items in excess of 14 and attach additional Continuation Sheets (OF 1419A) as needed.

ABSTRACT OF BIDS - CONSTRUCTION

CONTINUATION SHEET

1. SOLICITATION NUMBER

W911XK-17-B-0006

3. CONTRACT ITEMS

0001, 0002

4. OFFERS (Continued)

NO. 6

A. OFFEROR:

Roen Salvage Company B. BID SECURITY (Type and Amount)

Bond, 20%

A. OFFEROR:

2. PROJECT TITLE

TOTAL BID AMOUNT - BASE PLUS OPTION 1 AND OPTION 2

OPTION 1

TOTAL AMOUNT OF OPTION 1

OPTION 2

TOTAL AMOUNT OF OPTION 2

3 3

3A.

ITEM NO 3B. DESCRIPTION OF OFFERED ITEM 3C.

QUANTITY 3D. UNIT D. UNIT PRICE E. ESTIMATED

AMOUNT D. UNIT PRICE E. ESTIMATED

AMOUNT D. UNIT PRICE E. ESTIMATED

AMOUNT

0001 Portage Lake Revetment Repair 1 JOB $2,730,163.35 $2,730,163.35 $1,891,000.00 $1,891,000.00 $1,922,228.00 $1,922,228.00

0002 Cover/Armor Stone 6,300 Ton $72.20 $454,860.00 $57.00 $359,100.00 $68.19 $429,597.00

0003 Underlayer Stone 1,900 Ton $76.12 $144,628.00 $48.00 $91,200.00 $56.53 $107,407.00

0004 Mattres Stone 8,100 Ton $60.94 $493,614.00 $48.00 $388,800.00 $51.52 $417,312.00

0005 Splash Stone 1,100 Ton $69.99 $76,989.00 $48.00 $52,800.00 $56.53 $62,183.00

0006 Sheet Pile Fill Stone 2,400 Ton $43.02 $103,248.00 $48.00 $115,200.00 $45.16 $108,384.00

$4,003,502.35 $2,898,100.00 $3,047,111.00

0007 Option 1 - Portage Lake Revetment Repair 1 JOB $649,024.57 $649,024.57 $440,000.00 $440,000.00 $429,231.00 $429,231.00

0008 Option 1 - Splash Stone 370 Ton $69.98 $25,892.60 $48.00 $17,760.00 $56.53 $20,916.10

0009 Option 1 - Sheet Pile Fill Stone 450 Ton $43.02 $19,359.00 $48.00 $21,600.00 $45.16 $20,322.00

$694,276.17 $479,360.00 $470,469.10

0010 Option 2 - Portage Lake Revetment Repair 1 JOB $1,649,332.00 $1,649,332.00 $750,000.00 $750,000.00 $897,191.00 $897,191.00

0011 Option 2 - Splash Stone 850 Ton $67.25 $57,162.50 $48.00 $40,800.00 $56.53 $48,050.50

0012 Option 2 - Sheet Pile Fill Stone 1,175 Ton $55.49 $65,200.75 $48.00 $56,400.00 $45.16 $53,063.00

$1,771,695.25 $847,200.00 $998,304.50

$6,469,473.77 $4,224,660.00 $4,515,884.60

ABSTRACT OF BIDS - CONSTRUCTION

CONTINUATION SHEET

1. SOLICITATION NUMBER

W911XK-17-B-0006

INSTRUCTIONS - Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 14 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419s for contract items in excess of 14 and attach additional Continuation Sheets (OF 1419A) as needed.

2. PROJECT TITLE 4. OFFERS (Continued) FY17 Portage Lake Revetment Repair Onekama Township, Michigan

NO.7 NO. 8 NO. 8

A. OFFEROR: A. OFFEROR: A. OFFEROR:

Dean Marine & Excavating Inc The King Company Great Lakes Dock & Materials, LLC B. BID SECURITY (Type and Amount) B. BID SECURITY (Type and Amount) B. BID SECURITY (Type and Amount)

Bond, 20% Bond, 20% Bond, 20%

3. CONTRACT ITEMS

C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED

0001, 0002 0001, 0002 0001, 0002

TOTAL BID AMOUNT - BASE PLUS OPTION 1 AND OPTION 2

BASE BID

TOTAL AMOUNT OF BASE BID

OPTION 1

TOTAL AMOUNT OF OPTION 1

OPTION 2

TOTAL AMOUNT OF OPTION 2