SECTION 01 33 16 DESIGN AFTER AWARD
ATTACHMENT A: TRACKING COMMENTS IN DRCHECKS
1 General
The Government and Contractor shall set up the project in Dr Checks. Throughout the design process, the parties shall enter, track, and back-check comments using the DrChecks system. Government reviewers enter design review comments into DrChecks. Designers of Record shall annotate comments timely and specifically to indicate exactly what action will be taken or why the action is not required.
Comments considered critical by the conference participants shall be flagged as such.
2 DrChecks Review Comments
The Contractor and the Government shall monitor DrChecks to assure all comments are annotated and agreed to by the designers and reviewers prior to the next submittal. The DrChecks comments and responses shall be printed and included in the design analysis for record.
2.1 Conference participants (reviewers) will expect coordination between Design Analysis calculations and the submitted design. Reviewers will also focus on the design submittal's satisfaction of the contract requirements.
2.2 The Designers of Record shall answer each comment in DrChecks with a formal response prior to the next submittal, clearly indicating what action will be taken and what drawing/spec will change. Designers of Record are encouraged to directly contact reviewers to discuss and agree to the formal comment responses rather than relying only on DrChecks and review meetings to discuss comments.
With the next design conference, reviewers will back-check answers to the comments against the submittal, in addition to reviewing additional design work.
2.3 Comments that, in the Contractor's opinion, require effort outside the scope of the contract shall be clearly indicated as such in DrChecks. The Contractor shall not proceed with work outside the contract until a modification to the contract is properly executed, if one is necessary.
3 DrChecks Initial Account Set-Up
To initialize an office's use of DrChecks, choose a contact person within the office to call the DrChecks Help Desk at 800-428-HELP, M-F, 8AM-5PM, Central time. This POC will be given an office password to distribute to others in the office. Individuals can then go to the hyperlink at {http://www.projnet.org} and register as a first time user. Upon registration, each user will be given a personal password to the DrChecks system.
3.1 Once the office and individuals are registered, the COE’s project manager or lead reviewer will assign the individuals and/or offices to the specific project for review. At this point, persons assigned can make comments, annotate comments, and close comments, depending on their particular assignment.
4 DrChecks Reviewer Role
The Contractor is the technical reviewer and the Government is the compliance reviewer of the designers design documents. Each reviewer enters their own comments into the Dr Checks system. To enter comments:
4.1 Log into DrChecks.
4.2 Click on the appropriate project.
4.3 Click on the appropriate review conference. An Add comment screen will appear.
4.4 Select or fill out the appropriate sections (particularly comment discipline and type of document for sorting) of the comment form and enter the comment in the space provided.
4.5 Click the Add Comment button. The comment will be added to the database and a fresh screen will appear for the next comment you have.
4.6 Once comments are all entered, exit DrChecks by choosing “My Account” and then Logout.
5 DrChecks Comment Evaluation
The role of the designers of record is to evaluate and respond to the comments entered by the Government reviewers and by the Contractor. To respond to comments:
5.1 Log into DrChecks.
5.2 Click on the appropriate project.
5.3 Under “Evaluate” click on the number under “Pending”.
5.4 Locate the comments that require your evaluation. (Note: If you know the comment number you can use the Quick Pick window on your home page in DrChecks; enter the number and click on go.)
5.5 Select the appropriate evaluation (concur, non-concur, for information only, or check and resolve) and add the response.
5.6 Click on the Add button. The evaluation will be added to the database and a fresh screen will appear with the next comment.
5.7 Once evaluations are all entered, exit DrChecks by choosing “My Account” and then Logout.
6 DrChecks Back-check
At the following design conference, participants will back-check comment annotations against newly presented documents to verify that the designers' responses are acceptable and completed. The Contractor and Government reviewers shall either enter additional back-check comments, as necessary or close those that are resolved as a result of the design conferences:
6.1 Log into DrChecks.
6.2 Click on the appropriate project.
6.3 Under “My Backcheck” click on the number under “Pending”.
6.4 If you agree with the designer’s response select “Close Comment” and add a closing response if desired.
6.5 If you do not agree with the designer’s response or the submittal does not reflect the response given, select “Issue Open”, enter additional information.
6.6 Click on the Add button. The back-check will be added to the database and a fresh screen will appear with the next comment.
6.7 Once back-checks are all entered, exit DrChecks by choosing “My Account” and then Logout. The design is completed and final when there are no pending comments to be evaluated and there are no pending or open comments under back-check.
ATTACHMENT B DESIGN SUBMITTAL DIRECTORY AND SUBDIRECTORY FILE
ARRANGEMENT
Organize electronic design submittal files in a subdirectory/file structure in accordance with the following table. The Contractor may suggest a slightly different structure, subject to the discretion of the government.
Design Submittal Directory and Subdirectory File Arrangement.
Directory Sub-Directory Sub-Directory or Files Files
Submittal/Package Name
Drawings PDF (subdirectory) Single PDF file with all applicable drawing sheets
- bookmarked by sheet number and name
MICROSTATION
(subdirectory)
Microstation project folder (with files) per the USACE Workspace. Include an Excel drawing index file with each drawing sheet listed by sheet #, name and corresponding dgn file name (Final Design & Release for Construction only)
Design Documentation Report
Individual PDF files containing design analysis and calculations for each discipline applicable to the submittal
Specifications PDF file with bundled specifications in UFGS format.
SPECSINTACT
(subdirectory)
All SpecsIntact files created for the project in the native software file format. (Final Design and Release for Construction Only)
-- End of Section