Technical Specifications Section 01 35 00.00 08 (Revised) Amendment 0001.pdf
PDF 69 KB Posted
- Attached to
- Lock Control System Modernization, Lock and Dam #5, Allegheny River, Freeport, PA Federal contract opportunity
- Solicitation number
- W911WN21B8005
About this file
This document provides details for a federal contract solicitation for lock control system modernization work at Allegheny Lock and Dam #5 on the Allegheny River in Pennsylvania. The solicitation seeks the removal of an existing DeviceNET control infrastructure and installation of a new interlocked control system communicating through Ethernet/IP and hardwiring. Key requirements include removing old PLCs and HMI units and supplying and installing new ones, upgrading VFDs and communication protocols, replacing limit switches and control heads, and integrating the new system with existing fiber optic cabling. Offerors must dispose of removed electrical equipment and construction waste. Work will occur near operating lock gates. The lock chamber currently operates seasonally on weekends. The contract value is estimated between $500,000 to $1,000,000 and is set aside for small businesses. The period of performance is 365 days after notice to proceed. The solicitation and attachments were issued by the U.S. Army Corps of Engineers, Pittsburgh District.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Results W911WN21B8005.pdf | ||
| Attendance Register Bid Opening 8-24-21.pdf | ||
| Amendment 0001 W911WN21B8005-0001.pdf | ||
| Davis Bacon Wage Rates 7-23-21 (new updated Attachment 4).pdf | ||
| Contract Drawings Sheets (Revised) Amendment 0001.pdf | ||
| Pre-Bid Sign-In Sheet Site Visit.pdf | ||
| Pre-Bid Contracting Discussion Site Visit.pdf | ||
| Pre-Bid Site Visit Agenda.pdf | ||
| Technical Specifications - Attachment 1.pdf | ||
| Contract Drawings - Attachment 2.pdf | ||
| Reference Drawings - Attachment 3.pdf | ||
| Bid Schedule.xlsx | XLSX spreadsheet | |
| Davis Bacon Wage Rates - Attachment 4.pdf | ||
| W911WN21B8005.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Allegheny Lock #5 Lock Control System Modernization
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 35 00.00 08
SPECIAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 SUBMITTALS
1.4 CONTRACTOR RESPONSIBILITIES
1.4.1 General
1.4.2 Licenses and Permits
1.5 DRAWINGS
1.5.1 Contract Drawings
1.5.2 Reference Drawings
1.6 WORK AREAS AND RESTRICTIONS
1.6.1 Work Areas
1.6.2 Laydown, Storage and Parking Areas
1.6.3 Access to Project Site
1.6.4 Public Use
1.6.5 Utilities
1.6.6 Other Contractors
1.7 FEDERAL HOLIDAYS
1.8 RESTRICTIONS TO RIVER TRAFFIC FOR CONSTRUCTION
1.8.1 Closure of the Lock Chamber
1.8.1.1 Temporary Lock Closures
1.9 EVACUATION OF LAND BASED EQUIPMENT AND MATERIALS
1.9.1 Withdrawal of Equipment and Materials
1.9.2 Plan of Action, Withdrawal of Land Based Equipment and
Materials
1.9.3 Compensation and Extension of Contract Period, Suspension of
Work
1.10 DAMAGE TO WORK
1.11 PROTECTION OF UTILITIES
1.12 INSPECTIONS AND ACCEPTANCE OF WORK
1.13 OPERATION OF GOVERNMENT FACILITY
1.13.1 Allegheny River Lock and Dam 5, Hours of Operation
1.13.2 Contractor's Work Hours
1.13.3 Coordination with Project Operations
1.14 SAFETY AND HEALTH REQUIREMENTS
1.15 CROSSOVER
1.16 GOVERNMENT-FURNISHED PROPERTY
1.16.1 Laptop
1.16.2 Control Heads
1.16.3 Miscellaneous
1.16.4 Delivery
1.17 CYBERSECURITY
PART 2 PRODUCTS
SECTION 01 35 00.00 08 Page 1
CERTIFIED FINAL DOCUMENTS - RTA W911WN-21-B-8005 - AMENDMENT 1
2.1 PRODUCTS AND PARTS OF STANDARD MANUFACTURE
PART 3 EXECUTION
3.1 SEQUENCE OF WORK
3.2 ANTITERRORISM (AT) AND PROJECT SPECIFIC SECURITY REQUIREMENTS
3.2.1 AT Level I Training
3.2.2 Access and General Protection/Security Policy and Procedures
3.2.3 Suspicious Activity Reporting Training
3.2.4 Contractor Employees Who Require Access to Government
Information Systems
3.2.5 OPSEC Training
3.2.6 Escort of Contractor Employees
3.2.7 Facility Clearance and Individual Clearances
3.2.8 Pre- screen candidates using E-Verify Program
3.2.9 Contract for Work on Federal Contracts
3.2.10 Threat Awareness Reporting Program
3.2.11 Changes in Security Requirements
3.2.12 Identification Of Employees
-- End of Section Table of Contents --
SECTION 01 35 00.00 08 Page 2
SECTION 01 35 00.00 08
SPECIAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
This section addresses the general requirements applicable to the performance of the work under this contract. These requirements are in addition to those specified in other sections of the contract.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
U.S. ARMY (DA)
DA AR 25-2 (2007; RAR 2009) Information Assurance
DA AR 380-49 (2013) Industrial Security Program
DA AR 380-67 (2014) Personnel Security Program
DA AR 381-12 (2016) Threat Awareness and Reporting Program
U.S. DEPARTMENT OF DEFENSE (DOD)
DOD 5220.22-M (2013) National Industrial Security Program Operating Manual (NISPOM)
U.S. DEPARTMENT OF HOMELAND SECURITY (DHS)
HSPD-12 (2004) Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. DEPARTMENT OF DEFENSE (DOD)
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having an "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be
SECTION 01 35 00.00 08 Page 3 submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Local Road Condition Assessment Video; G, RO
Access Plan; G, RO
Plan Of Action, Withdrawal Of Land Based Equipment And Materials;
G, RO
SD-07 Certificates
AT Level I Training; G, RO IWatch Training; G, RO Threat Awareness Reporting Program
Opsec Training
1.4 CONTRACTOR RESPONSIBILITIES
1.4.1 General
Responsibilities of the Contractor include, but shall not be limited to, all planning, programming, administration, coordination, and management to ensure that all work is performed in accordance with all laws, regulations, codes or directives. The Contractor shall be responsible for ensuring that the work performed meets or exceeds the requirements of the contract. The Contractor shall perform all related Contractor administrative services necessary to perform the work, such as quality control, contractor financial control, and maintenance of accurate and complete records and files. The Contractor shall also be responsible for establishing and executing programs required to ensure that all work is performed in strict accordance with all health, safety and environmental laws, regulations, codes and directives, to protect the general public, as well as Contractor and Government employees.
1.4.2 Licenses and Permits
The Contractor shall be responsible for complying with all state or local contractor licensing or registration laws and permit requirements. The Contractor shall be responsible for furnishing qualified personnel for work which requires specialized registration or training.
1.5 DRAWINGS
1.5.1 Contract Drawings
The contract drawings provided reflect the work to be performed under this contract. In accordance with Section 00 70 00 CONDITIONS OF THE CONTRACT, DFARS 252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS, the Contractor shall check all drawings immediately upon receipt, and verify the figures, dimensions, and representation of the work. The Contractor shall compare all drawings and verify the figures before laying out the work. Dimensions marked on drawings shall, in general, be followed. Use of scaled measurements shall not be allowed. The Contractor shall promptly notify the Contracting Officer or designated representative of any discrepancies, and shall be responsible for any errors which might have been avoided by complying with this paragraph. Any omissions from the contract drawings, SECTION 01 35 00.00 08 Page 4 specifications, or incorrect description of details of the work which are manifestly necessary to carry out the intent of the contract drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or incorrectly described details of work, but shall be performed as if fully and correctly set forth and described in the contract drawings and specifications. Unless otherwise noted, dimensions and elevations, and other features shown on contract drawings are generally based on site surveys and measurements, and As-Built drawings. The Government cannot guarantee the accuracy of the dimensions, elevations, and features shown on the contract drawings which are based on the reference drawings, and it shall be the responsibility of the Contractor to verify all elevations and the dimensions shown by measurements in the field, at no additional cost to the Government.
1.5.2 Reference Drawings
The reference drawings included in the folio of contract drawings show original construction conditions of the original construction and the existing facilities and structures shown on the drawings. To the best knowledge of the Government, the reference drawings reflect the original work incorporated into this project, and do not reflect changes or new work since the date of the drawing. Unless otherwise noted, dimensions and elevations, and other features shown on reference drawings are generally based on As-Built conditions. Where known variations in actual construction occur between that shown on the reference drawings and that existing, it will be noted on the drawings or within the specifications, as practical. The Government cannot guarantee the accuracy of the dimensions, elevations, and features shown on the reference drawings, and it shall be the responsibility of the Contractor to verify all elevations and the dimensions shown by measurements in the field, at no additional cost to the Government. The Contracting Officer or designated representative shall be notified of any discrepancies prior to commencing work. It is noted that some of the As-Built conditions reflected by the reference drawings have since been modified. Such modifications to the As-Built conditions are described within the sections of these specifications where applicable.
1.6 WORK AREAS AND RESTRICTIONS
1.6.1 Work Areas
TAs required by Section 00 70 00 CONDITIONS OF THE CONTRACT , FAR 52.236-10 OPERATIONS AND STORAGE AREAS, all operations of the Contractor shall be confined to areas shown on the drawings required to accomplish the work under this contract and as authorized and approved by the Contracting Officer or designated representative. All work areas shall be coordinated with the Contracting Officer or designated representative prior to commencement of work. The Contractor shall submit an Access Plan for Government operating personnel to the Contracting Officer or designated representative.
1.6.2 Laydown, Storage and Parking Areas
An area at the site, as shown, will be reserved for Contractor parking, field offices, laydown, and storage. Storage areas at the site will be limited to areas identified in the contract and as required for performance of the work under this contract. No other areas will be made available at the project for storage of equipment and materials. Unless otherwise specified, storage will not be permitted on service bridges, SECTION 01 35 00.00 08 Page 5 bulkheads, decks and similar structures. All such work and storage areas and adjacent facilities shall be protected from damage by the Contractor's operations. Any damage caused by the Contractor's operations shall be repaired to the satisfaction of the Contracting Officer or designated representative at the Contractor's expense. The Contractor's use of such storage areas shall not interfere with operation of the facilities.
1.6.3 Access to Project Site
The Contractor will be permitted to cross the miter gates to access the River Wall. Construction loads on the miter gate walkways and grating/planking on the Land, Middle, and River Walls must not exceed 100 pounds per square foot. Larger loads may be acceptable pending the Government's review and approval.
1.6.4 Public Use
The Contractor's attention is directed to the fact that the work to be performed may be located in areas heavily used for recreational activities by the public. It shall be the responsibility of the Contractor to provide the controls necessary to prevent any interference by the public to his operations. The Government will cooperate with the Contractor in keeping the work areas clear so that the work may be performed with efficiency. The Contractor shall schedule his work to provide for these restrictions and all costs resulting therefrom shall be considered incidental to the costs of performing the work.
1.6.5 Utilities
Unless otherwise specified, the Government will not make any utilities or services available to the Contractor; and the Contractor shall be responsible for furnishing all utilities and services required for performance of the work under this contract.
1.6.6 Other Contractors
The Contractor is alerted to the fact that other contractors may be employed by the Government or local interests at, or in the vicinity of the site. See also Section 00 73 00 SUPPLEMENTARY CONDITIONS, clause WORK
UNDER OTHER CONTRACTS.
1.7 FEDERAL HOLIDAYS
The eleven Federal holidays observed are:
New Year's Day (January 1st) Martin Luther King Day (3rd Monday in January) President's Day (3rd Monday in February) Memorial Day (Last Monday in May) Juneteenth (June 19) Independence Day (July 4th) Labor Day (1st Monday in September) Columbus Day (2nd Monday in October) Veterans Day (November 11th) Thanksgiving Day (4th Thursday in November) Christmas Day (December 25th)
When one of the above designated holidays falls on a Sunday, the following Monday is observed as a legal holiday. When a legal holiday falls on a
SECTION 01 35 00.00 08 Page 6
Saturday, the preceding Friday is observed as a holiday. A list of Federal holidays, can be found at ht t ps: / / www. opm. gov/ pol i cy- dat a- over si ght / pay- l eave/ pay- admi ni st r at i on/ f act - sheet s/ hol i days- wor k- schedul es- and- pay Work shall be scheduled around the above listed Federal holidays except as specified herein or as approved by the Contracting Officer or designated representative.
1.8 RESTRICTIONS TO RIVER TRAFFIC FOR CONSTRUCTION
1.8.1 Closure of the Lock Chamber
1.8.1.1 Temporary Lock Closures
The Government will permit 1 closure of the Lock Chamber for up to 5 consecutive days and 8 closures of up to 2 consecutive days, Monday through Friday, except Federal holidays, for the purpose of changeover from existing equipment to new equipment. During these temporary lock closure, the Contractor will be permitted to perform work which requires closure of the Lock Chamber. At the end of the Temporary Lock Closure, the Contractor shall ensure that the Lock Chamber is fully operational.
Additional short term lock closures up to 4 hours in length can be approved at the lock Masters discretion. Temporary closures will not be permitted during the week of the 2022 Three River Regatta, on Federal holidays or the following holiday weekends:
Memorial Day Weekend, May 28 thru May 30, 2022 Fourth of July, July 2 thru July 4, 2022 Labor Day Weekend, September 3 thru September 5, 2022
The Contractor shall notify the Contracting Officer or designated representative at least 21 calendar days prior to anticipated requirement for temporary lock closures. The Government will review the Contractor's request for the temporary lock closures and will either approve or deny the Contractor's request depending on previously scheduled priority lockages or other critical events or issues at the site and may provide alternative temporary closure dates. Short term 4 hour closures approved by the lockmaster do not require 21 day approval and availability is determined by planned river traffic.
1.9 EVACUATION OF LAND BASED EQUIPMENT AND MATERIALS
1.9.1 Withdrawal of Equipment and Materials
The Contractor is alerted the work area and storage areas identified on the drawings maybe located in the floodplain, located in close proximity to open water; such as rivers, lakes or streams; and maybe subject to high water events with little or no advance warning.
It shall be the Contractor's responsibility to withdraw any land-based equipment and materials that would be subject to damage by rising water stages from such affected areas, before they are subject to damage. The Contractor shall monitor the prevailing river, lake or stream conditions at the project site, referring to the nearest water level gauges, high water forecasts issued by the National Weather Services and the USGS Stream Gage Data, and shall determine when to withdraw equipment and materials. The withdrawal of equipment and materials shall ultimately be the Contractor's decision and will not be directed by the Government. It shall be the Contractor's responsibility to determine the time necessary to make a complete and safe withdrawal of identified items with due
SECTION 01 35 00.00 08 Page 7 consideration given to the location; amount of items; size of the items;
and Contractor's capability to remove the items. All equipment and material shall remain out of the impacted areas until after the high water conditions recede. The Contractor shall resume all work, and remobilize items from its evacuation location when the water conditions recede with a falling water condition forecasted.
1.9.2 Plan of Action, Withdrawal of Land Based Equipment and Materials
The Contractor shall prepare and submit a Plan of Action for withdrawal of land based equipment and materials at the site. The plan shall detail the procedures for withdrawal of equipment and materials in the event that suspension or impact of work is imminent. The Plan of Action shall include but is not limited to the following information:
- Procedure(s) For Monitoring Water Conditions
- Water Condition Which Affect Notification Actions
- Water Conditions Which Affect Withdraw
- Sequence and Duration of Withdraw
- Document Water Conditions Affecting Remobilization
- Sequence and Duration of Remobilization
The Plan of Action shall include a listing of key Contractor's Points of Contact and telephone numbers. The Plan of Action shall include the withdrawal of any subcontractor's equipment. The Contractor's Plan of Action shall be consistent with the applicable requirements for Emergency Planning as described in EM 385-1-1 . All key Contractor personnel including superintendents, foremen, safety officers, and QC personnel shall be given a copy of the Plan of Action and shall be thoroughly familiar with their duties under this plan. Subcontractors shall also be thoroughly familiar with their responsibilities and duties under the plan.
1.9.3 Compensation and Extension of Contract Period, Suspension of Work
The withdrawal of equipment is considered an incidental condition of work dictated by the nature of the work site. The Contractor's withdrawal of equipment and material shall not be construed as a direction on the part of the Government or Contracting Officer or designated representative, under the provisions of Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.242-14 SUSPENSION OF WORK, which shall not apply to this work condition. No compensation will be made to the Contractor for withdrawal of this equipment nor will any delay costs be made for the period during which work cannot be accomplished. In accordance with Section 00 70 00
CONDITIONS OF THE CONTRACT, FAR 52.249-10 DEFAULT (FIXED PRICE
CONSTRUCTION), the contract period may be extended equitably for the withdrawal of the equipment.
1.10 DAMAGE TO WORK
The responsibility for damage to any part of the permanent work shall be as set forth in Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.236-7 PERMITS AND RESPONSIBILITIES. However, if, in the judgment of the Contracting Officer or designated representative, any part of the permanent work performed by the Contractor is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer or designated representative and full compensation for such repairs will be made at the
SECTION 01 35 00.00 08 Page 8 applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer or designated representative, there are no contract unit or lump sum prices applicable to any part of such work, an equitable adjustment pursuant to the Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.243-4 CHANGES, will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or lump sum prices. Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer or designated representative at the Contractor's expense, regardless of the cause of such damage.
1.11 PROTECTION OF UTILITIES
Notwithstanding the Section 00 73 00 SUPPLEMENTARY CONDITIONS, paragraph "PROTECTION OF UTILITIES", and Section 00 70 00 CONDITIONS OF THE
CONTRACT, FAR 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES,
EQUIPMENT, UTILITIES, AND IMPROVEMENTS, the Contractor shall locate and clearly identify all underground and above ground utility lines, wires, cables, pipes, poles, support lines, and culverts, within the Contractor's work area. The Contractor shall contact the Pennsylvania One Call System at telephone (800) 242-1776 at least three days prior to beginning any Construction activity and comply with all applicable provisions of the PA Underground Utility Line Protection Act, PA Act 287. The Contractor shall be responsible for any costs for the Pennsylvania One Call System. The Contractor shall conduct his operations such that the utilities are not damaged or disturbed. Any damage to utilities caused by the Contractor's actions shall be repaired by him at no additional expense to the Government. The Contractor shall store materials and equipment in a manner that does not interfere with utility company services or utility company access to the facilities. The Contractor shall relocate any equipment or stockpiles, at no additional cost to the Government, that interfere with utility company operations, emergency repairs, or standard maintenance services.
1.12 INSPECTIONS AND ACCEPTANCE OF WORK
Not withstanding other provisions of this contract, all materials and work to be performed under this contract shall be inspected and accepted by the Contracting Officer or designated representative . Inspections and acceptance will be performed on phases of the work, before the next definable sequential phase of work commences, OR may be performed at the completion of all of the work, as determined appropriate by the Contracting Officer or designated representative. The Contracting Officer or designated representative shall be the individual(s) solely authorized to reject materials, disapprove or approve any work in progress, or order or direct any revision or change to the plans and specifications as presently shown and stated.
1.13 OPERATION OF GOVERNMENT FACILITY
The Allegheny River Lock and Dam 5 facility shall remain in operation at all times. The Contractor shall perform his work in a manner which will not interfere with the operation of the facilities and the duties of Government personnel. Particular care shall be taken during all operations under this contract to prevent damage to any operating equipment or facilities at the project. The Contractor shall take all necessary precautions to ensure the safety of the workers in accordance with the applicable provisions of EM 385-1-1 . Contractor operations shall
SECTION 01 35 00.00 08 Page 9 be performed in such a manner to ensure that project personnel, navigation industry personnel and the public are protected at all times.
1.13.1 Allegheny River Lock and Dam 5, Hours of Operation
Allegheny River Lock and Dam 5 operates between the hours of 7:00 AM and
5:00 PM.
1.13.2 Contractor's Work Hours
Contractor's work hours shall be restricted to 7:00 AM to 5:00 PM, Monday through Friday, or as otherwise approved by the Contracting Officer or designated representative. During shut downs the contractor's work hours can be extend to 7:00 AM to 8:30 PM with 14 calendar days notice to the contracting officer or designated representative. The contractor shall coordinate with the Contracting Officer or designated representative to make sure Government personnel are present during major features of work.
1.13.3 Coordination with Project Operations
The Contractor shall perform all work in a manner that will not interfere with the duties of the Government operations personnel. Particular care shall be taken during all operations under this contract to prevent damage to any operating equipment or facilities at the project. The Contractor shall continuously maintain safe access to all areas of the project for operating personnel, during every phase of the work, unless otherwise directed by the Contracting Officer or designated representative.
1.14 SAFETY AND HEALTH REQUIREMENTS
Safety and Health Requirements shall conform to Section 01 35 26.00 08 GOVERNMENTAL SAFETY REQUIREMENTS, EM 385-1-1 , and the requirements of the Occupational Safety and Health Administration. Where provisions of EM 385-1-1 vary with OSHA requirements, the more stringent requirements shall be applied.
1.15 CROSSOVER
The lock chamber crossover is currently filled with water, silt and debris. To permit access, the Government will dewater as well as remove all silt and debris that exists prior to contractor access. The crossover will be accesible to the contractor on or before 1 March 2022. The contractor will be responsible for dewatering the crossover while they are working in the location. The crossover will be considered to be a permit required confined space.
The government was recently able to pump the water level down 39' (the crossover goes down 44.5') before hitting significant debris in the crossover chamber that made it impossible to pump it down any further.
This was achieved using one 2" pump (model LB-800 rated at ~30.0 gpm at
44.5 ft) and three 3" pumps (model LB-1500 rated at ~60 gpm at 44.5 ft), it is assumed that during the test we were notachieving full performance out of the pumps due to hose curvature, so those ratings may be lower.
Previous pump down detail is provided for informational purposes only and the contractor is responsible for assessing and determining the pumping needs as part of their means and methods to perform the work. The government was recently able to dewater the crossover down to about 1 foot of sediment/debris. This was accomplished using three 3" pumps (model LB-1500 rated at ~60 gpm at 44.5ft - the depth of the crossover). It is
SECTION 01 35 00.00 08 Page 10 assumed that during the test, the pumps were not achieving their full performance due to hose curvature, so actual ratings may have been lower.
Two of these pumps were used on the Land Wall side access and the third was used on the River Wall side access. The government will again pump down the crossover prior to Contractor access in order to clear out the remaining sediment/debris. Previous pump down details are provided for informational purposes only and the Contractor is responsible for assessing and determining the pumping needs as part as their means and methods to perform the work.
1.16 GOVERNMENT-FURNISHED PROPERTY
The following materials and fabricated items will be furnished by the Government at the specified location.
1.16.1 Laptop
Government furnished laptop will be stored in the powerhouse office
1.16.2 Control Heads
Sixteen new control heads, 8 filling control heads and 8 emptying control heads, are to be furnished to the contract for installation.
1.16.3 Miscellaneous
Sixteen handle wheels and sixteen umbilical cables to be provided by the Government and installed by the contractor at each control head location.
1.16.4 Delivery
All material is already on site at Lock and Dam five. The contractor will need to coordinate with government representative on site for access to storage location.
1.17 CYBERSECURITY
Cybersecurity is required for this contract. Cybersecurity requirements outlined must be field verified prior to the operational phase of commissioning. Refer to SECTION 25 05 11.00 28 CYBERSECURITY for more detailed requirements. A check list used by USACE for ISS compliance can be sent after contract award.
PART 2 PRODUCTS
2.1 PRODUCTS AND PARTS OF STANDARD MANUFACTURE
All materials, supplies and articles furnished so as to be incorporated into the work under this contract shall, whenever so specified and otherwise practicable, be standard products of recognized reputable manufacturers. Standard products of manufacturers other than those specified will be accepted when it is proven to the satisfaction of the Contracting Officer or designated representative, in accordance with the Section 00 70 00 CONDITIONS OF THE CONTRACT CLAUSES, FAR 52.236-5 MATERIAL AND WORKMANSHIP, that they are equal in performance, strength, durability, usefulness and convenience for the purpose intended. Any changes required in the details and dimensions shown on the drawings as a result of the substitution of standard products, other than those provided for, shall be properly made as approved by the Contracting Officer or designated
SECTION 01 35 00.00 08 Page 11 representative, and at the expense of the Contractor. All products specified by "similar or equal to" a particular brand name are for descriptive purposes only and are not to imply that the product is available from only that source. Each major piece of equipment furnished under the contract shall be provided with a substantial nameplate securely fastened or cast in place and clearly inscribed with the manufacturer's name, year of manufacture, principal rating data and other pertinent data.
PART 3 EXECUTION
3.1 SEQUENCE OF WORK
The work shall be prosecuted in such order of precedence as best suits the Contractor's construction schedule and the following restrictions. The Contractor shall perform the work in a diligent, effective manner, and shall schedule his operations in such a manner that the work is completed on time. In accordance with contained in Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.211-12 LIQUIDATED DAMAGES - CONSTRUCTION, the Contractor will be assessed the daily monetary damages for failure to complete the work in the allotted contract period.
3.2 ANTITERRORISM (AT) AND PROJECT SPECIFIC SECURITY REQUIREMENTS
This paragraph contains information for security requirements for work on Government Property. The purpose of these security requirements it to ensure that all Contractor or subcontractor employees working on this contract have received proper clearance for access to the Government property. Identification of Critical Infrastructure and submission of required employee information will be discussed at the Preconstruction Meeting. Required employee information shall be submitted to the Resident Engineer and Pittsburgh Office of Security and Law Enforcement, as applicable, at l east 15 cal endar days pr i or t o r equi r ed empl oyee access t o t he pr oj ect .
3.2.1 AT Level I Training
All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the Contracting Officer (if a COR is not assigned), within five calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website:
http://jko.jten.mil/courses/atl1/launch.html ; or it can be provided by the RA ATO in presentation form which will be documented via memorandum.
3.2.2 Access and General Protection/Security Policy and Procedures
The Contractor and all associated subcontractors' employees shall comply with applicable installation, facility, and area commander installation and facility access and local security policies and procedures (provided by the Government Representative). The Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation the USACE Security Office. The Contractor workforce must comply with all personal identity
SECTION 01 35 00.00 08 Page 12 verification requirements as directed by DoD, HQDA, and/or local policy.
In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes. The Contractor must submit the full name, Social Security Number (a valid state driver's license number with state of issue maybe used instead of a SSN), Date of Birth, Place of Birth, and Citizenship for all associated contractor or subcontractor employees to the USACE Security Office, Joseph Bali, 412-395-7162, Joseph.M.Bali@usace.army.mil, or Fax at 412-395-7504, all background check requests must include the contract number, USACE Contracting Officer or designated representative and USACE project name or location. The District retains the right to deny any contractor and subcontractor employee from working on one of its contracts based on final background investigation results.
3.2.3 Suspicious Activity Reporting Training
The Contractor and all associated sub-contractors shall receive a iWatch/or/Corps Watch briefing/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR not later than five calendar days after the completion of the training.
3.2.4 Contractor Employees Who Require Access to Government Information Systems
All contractor employees with access to a government info system must be registered in the Army Training Certification Tracking System (ATCTS) at commencement of services, and must successfully complete the DOD Information Assurance Awareness prior to access to the information systems and then annually thereafter in accordance with personnel security standards listed in DA AR 25-2 (Information Assurance), an appropriate background investigation will be conducted prior to accessing the Government information systems
3.2.5 OPSEC Training
All new Contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all Contractor employees must complete annual OPSEC awareness training. The Contractor shall submit certificates of completion for each affected Contractor and subcontractor employee, to the Contracting Officer or designated representative within 5 calendar days after completion of training. OPSEC awareness training is available at the following websites: https://www.iad.gov/ioss/ or http://www.cdse.edu/catalog/operations-security.html ; or it can be provided by the District Security and Law Enforcement Officer in presentation form which will be documented via memorandum.
3.2.6 Escort of Contractor Employees
All Contract employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in
SECTION 01 35 00.00 08 Page 13 areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.
3.2.7 Facility Clearance and Individual Clearances
The Prime Contractor Company must have a Facility Clearance (FCL) at the appropriate level (in accordance with DOD 5220.22-M and DA AR 380-49 ) prior to the start of the contract awarded period of performance.
Contractor personnel performing work under this contract must have the required security clearance, per DA AR 380-67 , at the appropriate level at the start of the period of performance. Security Clearances and FCL requirements are required to be maintained for the life of the contract in accordance with the DD Form 254 attached to the contract. If no FCL is attached, the supporting Government Contracting Activity will sponsor the prime contract company in obtaining the FCL.
3.2.8 Pre- screen candidates using E-Verify Program
The Contractor must pre -screen candidates using the E -verify Program ( http://www.dhs.gov/e-Verify ) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the Contracting Officer or designated representative no later than 3 business days after the initial contract award.
3.2.9 Contract for Work on Federal Contracts
All Contractor and subcontractor employees working on this contract who require access to identified Pittsburgh District critical infrastructure are required to have a favorable background investigation in accordance with HSPD-12.
This background investigation shall be completed by the Pittsburgh Office of Security & Law Enforcement, who will make the final determination on an employee's suitability for work on Government property, and who shall have the right to deny a Contractor or subcontractor employee from working on a contract based on results of the background investigation.
Background investigations are defined in two parts as described below:
a. Prior to any Contractor employees accessing the work site, an initial background check (LEXUS/NEXUS) shall be completed. To accomplish this, the prime Contractor shall submit a complete list of employees who will be working on Government property (prime Contractor employees and any subcontractor employees) to include Name, Social Security Number, Date of Birth and Place of Birth. This list shall be submitted to the Pittsburgh Office of Security & Law Enforcement who will conduct this initial criminal check based on the information provided. The Pittsburgh Office of Security & Law Enforcement will notify the Contracting Officer or designated representative of the results within five working days of receiving the information. If no issues are found, approval to begin work will be provided in writing by the Administrative Contracting Officer or designated representative to the Contractor upon receipt of the results from the Pittsburgh Office of Security & Law Enforcement. At that time, Contractor employees receiving a favorable background check will be permitted access to the work site.
SECTION 01 35 00.00 08 Page 14
b. In addition to the requirements of subparagraph a, those contractors who are awarded contracts that are sensitive or require access to a USACE computer network shall also submit an investigation package for each Contractor and subcontractor employee requiring such access. This investigation package shall include:
1) SF-85, Questionnaire for Non-sensitive Positions (See E-Quip form attached).
2) FD-258, Contractor Fingerprint Card (1 card for digital prints, 2 for ink prints) (Note: Prints must be taken by a trained/qualified individual; ORI block on FD-258 must be USOPM000Z) (Contractor Fingerprint Cards (FD-258) may be obtained by contacting the Pittsburgh Office of Security & Law Enforcement.)
At the submission and initiation of this in-depth background investigation by the Office of Personnel Management (OPM), this information will be provided to the Contracting Officer or designated representative who will inform the Contractor that the employee(s) is cleared for interim access. Contractor employees permitted access to Government property shall be limited to those individuals that have been specifically identified and approved. The Contractor shall report any change(s) in personnel at least 5 working days prior to individual(s) needing access to the site. The Contractor shall provide the same information as listed above for any new employees.
Employee information submitted to the Pittsburgh Office of Security and Law Enforcement and results of investigations will be retained in encrypted form and in a secure location until 90 calendar days after completion of the contract. The records will be destroyed at the end of this period.
3.2.10 Threat Awareness Reporting Program
All new contractor employees will complete annual Threat Awareness and Reporting Program (TARP) Training provided by a Counterintelligence Agent, IAW DA AR 381-12 . The Contractor shall submit certificates of completion for each affected contractor and subcontractor employee(s) or a memorandum for the record, to the Contracting Officer or designated representative, within 5 calendar days after completion of training. Authorized webbased TARP training for CAC card holders is available at the following website:
https://www.us.army.mil/suite/page/655474 .
3.2.11 Changes in Security Requirements
Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, US Army Force Protection Measures, regulation or policy changes, etc. Changes to any security requirements shall be added to the contract by modification.
The Pittsburgh District Office of Security & Law Enforcement may be contacted by phone or e-mail at the following number/address:
Joseph Bali; Phone 412-395-7162; e-mail Joseph.M.Bali@usace.army.mil
3.2.12 Identification Of Employees
The Contractor shall be responsible for furnishing an identification
SECTION 01 35 00.00 08 Page 15 badge/card to each employee prior to the employee working on-site and for requiring each employee engaged on the work to display identification.
Identification shall consist of name tags with the name of the Contractor and the employee's name. As a minimum, a valid state driver's license or other government-issued photo identification card is required for positive identification.
SECTION 01 35 00.00 08 Page 16
-- End of Section --
SECTION 01 35 00.00 08 Page 17
| 01 35 00.00 08 - SPECIAL PROCEDURES |
| 01 35 00.00 08 - SPECIAL PROCEDURES |
| PART 1 GENERAL |
| 1.1 SUMMARY |
| 1.2 REFERENCES |
| 1.3 SUBMITTALS |
| 1.4 CONTRACTOR RESPONSIBILITIES |
| 1.4.1 General |
| 1.4.2 Licenses and Permits |
| 1.5 DRAWINGS |
| 1.5.1 Contract Drawings |
| 1.5.2 Reference Drawings |
| 1.6 WORK AREAS AND RESTRICTIONS |
| 1.6.1 Work Areas |
| 1.6.2 Laydown, Storage and Parking Areas |
| 1.6.3 Access to Project Site |
| 1.6.4 Public Use |
| 1.6.5 Utilities |
| 1.6.6 Other Contractors |
| 1.7 FEDERAL HOLIDAYS |
| 1.8 RESTRICTIONS TO RIVER TRAFFIC FOR CONSTRUCTION |
| 1.8.1 Closure of the Lock Chamber |
| 1.8.1.1 Temporary Lock Closures |
| 1.9 EVACUATION OF LAND BASED EQUIPMENT AND MATERIALS |
| 1.9.1 Withdrawal of Equipment and Materials |
| 1.9.2 Plan of Action, Withdrawal of Land Based Equipment and Materials |
| 1.9.3 Compensation and Extension of Contract Period, Suspension of Work |
| 1.10 DAMAGE TO WORK |
| 1.11 PROTECTION OF UTILITIES |
| 1.12 INSPECTIONS AND ACCEPTANCE OF WORK |
| 1.13 OPERATION OF GOVERNMENT FACILITY |
| 1.13.1 Allegheny River Lock and Dam 5, Hours of Operation |
| 1.13.2 Contractor's Work Hours |
| 1.13.3 Coordination with Project Operations |
| 1.14 SAFETY AND HEALTH REQUIREMENTS |
| 1.15 CROSSOVER |
| 1.16 GOVERNMENT-FURNISHED PROPERTY |
| 1.16.1 Laptop |
| 1.16.2 Control Heads |
| 1.16.3 Miscellaneous |
| 1.16.4 Delivery |
1.17 CYBERSECURITY
| PART 2 PRODUCTS |
| 2.1 PRODUCTS AND PARTS OF STANDARD MANUFACTURE |
| PART 3 EXECUTION |
| 3.1 SEQUENCE OF WORK |
| 3.2 ANTITERRORISM AT AND PROJECT SPECIFIC SECURITY REQUIREMENTS |
| 3.2.1 AT Level I Training |
| 3.2.2 Access and General Protection/Security Policy and Procedures |
| 3.2.3 Suspicious Activity Reporting Training |
| 3.2.4 Contractor Employees Who Require Access to Government Information |
| 3.2.5 OPSEC Training |
| 3.2.6 Escort of Contractor Employees |
| 3.2.7 Facility Clearance and Individual Clearances |
| 3.2.8 Pre-†screen candidates using E-Verify Program |
| 3.2.9 Contract for Work on Federal Contracts |
| 3.2.10 Threat Awareness Reporting Program |
| 3.2.11 Changes in Security Requirements |
| 3.2.12 Identification Of Employees |