Amendment 0001 W911WN21B8005-0001.pdf
PDF 421 KB Posted
- Attached to
- Lock Control System Modernization, Lock and Dam #5, Allegheny River, Freeport, PA Federal contract opportunity
- Solicitation number
- W911WN21B8005
About this file
This amendment to the solicitation for the Lock Control System Modernization project at Allegheny Lock and Dam #5 provides responses to contractor questions and revises sections of the specifications and drawings. The upgrade involves replacing the existing DeviceNET infrastructure with a new interlocked control system using Ethernet/IP communication. Major requirements include installing new HMIs and PLC components, upgrading gate control VFDs to use Ethernet/IP, replacing limit switches, and integrating the system with existing fiber optic cabling. The contractor must also remove obsolete electrical equipment and dispose of construction waste appropriately. The period of performance is 365 days from notice to proceed. The solicitation is open only to small businesses and has a value between $500,000 to $1 million.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Results W911WN21B8005.pdf | ||
| Attendance Register Bid Opening 8-24-21.pdf | ||
| Contract Drawings Sheets (Revised) Amendment 0001.pdf | ||
| Technical Specifications Section 01 35 00.00 08 (Revised) Amendment 0001.pdf | ||
| Davis Bacon Wage Rates 7-23-21 (new updated Attachment 4).pdf | ||
| Pre-Bid Site Visit Agenda.pdf | ||
| Pre-Bid Sign-In Sheet Site Visit.pdf | ||
| Pre-Bid Contracting Discussion Site Visit.pdf | ||
| Technical Specifications - Attachment 1.pdf | ||
| Davis Bacon Wage Rates - Attachment 4.pdf | ||
| W911WN21B8005.pdf | ||
| Contract Drawings - Attachment 2.pdf | ||
| Reference Drawings - Attachment 3.pdf | ||
| Bid Schedule.xlsx | XLSX spreadsheet |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W81ET411127786
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
RE: Lock Control System Modernization, Allegheny Lock #5, Armstrong County, PA
The purpose of this amendment is to: 1) provide responses to questions received; 2) revise one (1) section of the Technical Specifications;
3) revise tw elve (12) Sheets of the Draw ings; and 4) update the applicable Davis Bacon Wage Determination identif ied in paragraph 00 73 00 - 01 Wage Rates in Addendum to Section 00 73 00.
The hour and date specified for receipt of bids remains unchanged, 11:00 am on 24 August 2021.
Details are specified in the Summary of Changes of this Amendment.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 11
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 18-Aug-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911WN21B8005
X 9B. DATED (SEE ITEM 11)
20-Jul-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
18-Aug-2021
CODE
U.S. ARMY ENGINEER DISTRICT, PITTSBURGH
ATTN CELRP-CT
W S MOORHEAD FEDERAL BUILDING
1000 LIBERTY AVENUE ROOM 2203
PITTSBURGH PA 15222-4186
W911WN 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911WN21B8005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0001
Reference: Technical Specifications, Lock Control System Modernization, Allegheny Lock #5, Certified Final, May 2021 (Attachment 1 to the Solicitation)
The following Section has been revised and are attached to this amendment, 01 35 00.00 08 SPECIAL PROCEDURES
Paragraph 1.15 CROSSOVER Second paragraph deleted and replaced in its entirety to give a more current status of the crossover conditions.
Reference: Contract Drawings, Allegheny River Basin, Allegheny Lock #5, Lock Control System Modernization, Certified Final, May 2021 (Attachment 2 to the Solicitation)
The following 12 Sheets have been revised and are attached to this amendment, SHEET E-401– ELECTRICAL SITE PLAN
Corrected drawing scale from 1/32” = 1’–0” to 1” = 50’.
SHEET E-402 – UPSTREAM PLAN
Corrected drawing scale from 1/8” = 1’–0” to 1/16” = 1’–0”.
SHEET E-403 – DOWNSTREAM PLAN
Corrected drawing scale from 1/8” = 1’–0” to 1/16” = 1’–0”.
SHEET E-404 – POWER HOUSE FLOOR PLAN
Corrected drawing scale from 1/4” = 1’–0” to 1/8” = 1’–0”.
SHEET E-505 – POWER HOUSE TRENCH CABLE ADDITIONS
Corrected drawing scale from 1/4” = 1’–0” to 3/4” = 1’–0”.
SHEET E-307 – CROSSOVER CABLE ADDITIONS
Removed graphic scale from section view on drawing and labeled “NTS”.
SHEET E-308 – RIVER WALL TRENCH DETAIL & ACTUATORS
Removed graphic scale from section views on drawing and labeled “NTS”.
SHEET E-609 – POWER ONE LINE
The existing drawing has been revised to show that VFD and Bypass Contactor are both fed by one breaker.
SHEET E-655 – R/W VFD CONTROL ENCLOSURE WIRING DIAGRAM (SHEET 1 OF 2)
The existing drawing has been revised to remove IC contacts and to show VFD powered at all times.
SHEET E-656 – R/W VFD CONTROL ENCLOSURE WIRING DIAGRAM (SHEET 2 OF 2)
The existing drawing has been revised to remove IC contacts and to show VFD powered at all times.
SHEET E-657 – L/W VFD CONTROL ENCLOSURE WIRING DIAGRAM (SHEET 1 OF 2)
The existing drawing has been revised to remove IC contacts and to show VFD powered at all times.
SHEET E-658 – L/W VFD CONTROL ENCLOSURE WIRING DIAGRAM (SHEET 2 OF 2)
The existing drawing has been revised to remove IC contacts and to show VFD powered at all times.
QUESTIONS AND ANSWERS
RESPONSES TO QUESTIONS RECEIVED (1 - 18)
Q1: Regarding the clauses incorporated by reference, is there CUI “Controlled Unclassified Information” in this contract?
A1: Yes, there is CUI in this contract.
Q2: Regarding the clauses incorporated by reference, is the contractor required to implement NIST SP 800-171?
A2: It is recommended that the Contractor implement NIST SP 800-171, but it is not required at this time.
Q3: Reference Specifications Section 01 45 00.00 08, Paragraph 3.4.3 Does the Specialized Personnel - Electrical Engineer QC listed in paragraph 3.4.3 need to be onsite at all times that the CQC Site System Manager is on site and are they allowed to have any other duties besides their CQC role while onsite?
A3: See specifications section 01 45 00.00 08 paragraph 3.4.3 for clarification. The paragraph specifically indicates that the Electrical QC shall not have other duties, be responsible to the CQC system manager and be onsite when their discipline work is occurring.
Q4: Specifications Section 40 60 00, Paragraph 2.18.1 refers to purchasing M&C software license updates. We assume this is an extended license for software already existing at the Lock that needs renewed. We are already purchasing PLC Programming Software (RSLOGIX5000) and HMI programming software (FACTORYTALK ME) for installation on the Government Furnished Laptop. You are obligated to FactoryTalk Plus HMI software because the new HMIs at CS1 and CS2 are called out as PANELVIEW PLUS7 in the BOM. We are uncertain what is meant by M&C software license. From the remaining description in 2.18, it sounds like this additional software is an alarming, reporting, and long term Historical Database package.
a. From the internet, there are several companies that call their software M&C.
b. We are not sure if you are just using the generic term M&C (Monitoring and Control).
c. We do not believe that either of the two software licenses that we intend to provide has ALL of the additional functionality listed in section 2.18.
d. The spec refers to a “central station computer”. (paragraph 2.18.4, a) We are not aware of this computer from the specifications or plans.
Questions (1-3)
1. Please provide the exact software name, manufacturer, and part number that you are requesting.
2. Please indicate where, which computer, this extended software license needs to be installed / is already installed.
3. Please indicate if we are required to modify this software in any way, such as: add new data points to monitor, create new reports, or create a new historical database.
A4:
1. FAR regulations prohibit us to name specific manufacturer’s/part numbers without prior justification and approval. The solicitation documents have been developed using the salient characteristics and requirements. If the contractor chooses the hardware outlined in this question, then the software outlined in this question is acceptable for installation on the Government Furnished laptop. All M&C (HMI) software requirements in specs are not necessarily needed to be implemented under this Contract, rather Contract drawings should serve as the primary functionality guidelines.
2. This software will only need to be installed on the Government Furnished laptop. Currently, the programming laptop has programming software installed, so all software/licensing will be the responsibility of the Contractor. The provisions outlined in paragraph 2.18.1 are to ensure that the programming software installed will be updated with necessary security patches and bug fixes for a period of 5 year at no additional cost to the government. The “Central Station Computer” is not used in this contract and reference to it in the specifications should be ignored.
3. The software will at minimum need to be migrated to the new software. The existing system did not have physical interlocks, so adjustments will need to be made in the software to account for that.
Q5: We are required to replace (4) VFD buckets and (4) Bypass Contactor buckets in the MCC. The existing MCC has 8 doors and 8 sections for this equipment.
a. Drawing E-609, single line power drawing shows the VFD and Bypass Contactor as separate buckets, each with its own Breaker.
b. Drawing E-658 shows a single breaker feeding both the VFD and Bypass Contactor.
Questions (1-3)
1. Please indicate whether 1 breaker or 2 is correct.
2. Please indicate if we should provide a single door that covers both the VFD section and the BYPASS section, or if we should include 2 separate doors as with the current configuration.
3. Please modify the schematic on E-658 if you decide to have 2 Breakers.
A5:
1. The new system will utilize 1 breaker instead of 2. The one line diagram E-609 is updated, see the amendment W911WN21B8005-0001.
2. A single door to cover both sections is acceptable.
3. No change is needed to update E-658, the one line diagram E-609 is updated instead to show a single breaker.
See amendment W911WN21B8005-0001.
Q6: Drawing E-658. The input contactor to the VFD (IC) seems problematic. If you have the selector switch in BYPASS MODE, contactor IC is OFF. Therefore, the VFD is OFF. Therefore, the I/O board on the VFD is OFF. Therefore, the INPUT (BYPASS MODE) on the drive I/O will not correctly indicate to the PLC when the System is in BYPASS, nor the other input signals (BYPASS OPEN) and (BYPASS CLOSE). Our previous experience with USACE has been that Rockwell has removed contactor IC and the VFD is always energized. Some VFD’s have a separate “control power only” source, but this is not indicated on the current schematic.
Questions (1-2)
1. Please provide a corrected control scheme and/or drawing.
2. If the control system of the VFD is to be powered from separate 120VAC or 24VDC, please indicate the source.
A6:
1. The VFD drawings E-655 through E658 are updated to remove the IC contacts and have the VFD powered at all times. See amendment W911WN21B8005-0001.
2. Separate source is not necessary.
Q7: Drawing E-402, note 3 discusses the new limit switches. The current switches are simple proximity sensors. Note 6 describes new guarding for the switches to prevent damage from debris.
Questions (1-2)
1. Should the replacement switches be any type of generic proximity sensors, or are we obligated to provide “GO SWITCHES/TOPWORX brand” as typically required at new USACE locations?
2. Please indicate details of what type of protective guarding you require for these switches. We do not understand how to provide a watertight/weatherproof mounting AND maintain the capability to adjust the switches left and right.
A7:
1. FAR regulations prohibit us to name specific manufacturer’s/part numbers without prior justification and approval. The solicitation documents have been developed using the salient characteristics and requirements.
The parts chosen must match the outlined parameters in the specifications.
2. The protective guarding is to protect the switches from damage from debris in a flood event. The guarding can be made to be removed to adjust the position of the limit switches. Adjustments will not need to be large, so a guard that allows for coverage of the switches plus several inches on either side should be acceptable. The mounting/guarding does not need to be watertight/weatherproof as long as the limit switches are rated IP 68 or higher.
Q8: Specifications Section 25 05 11.00 28
Questions (1-4)
1. Is the sensitive data in this section considered to be CUI (Controlled Unclassified Information)?
2. Does UCIC-MCX consider the control network to be a single individual OT Subsystem as defined in Part 1.4(v)?
3. Will the control network be interconnected to any other OT Subsystem, OT Closed Restricted System, OT Restricted Interconnect System, or OT Connected System as defined in Part 1.4?
4. Is it acceptable for the control network to have a flat architecture without segmentation?
A8:
1. Yes, sensitive data outlined in Specification Section 25 05 11.00 28 is considered to be CUI along with all control layout drawings.
2. The system is an OT Closed Restricted System as defined in paragraph 1.4.
3. The system should not interconnect with any other systems under this contract.
4. Segmentation is required.
Q9: Regarding the replacement of the valve heads on the Auma Actuators, would the contractor be required to provide any additional AUMA parts, besides the Government Furnished Equipment, to complete this installation?
A9: The contractor should consult with AUMA to ensure that no additional parts are necessary, but to our knowledge everything necessary should be included in the GFE.
Q10: Cross Passageway Pumping. Although the USACE is going to perform the initial pumping and cleaning of the Cross Passageway, the Contractor will have to pump the Cross Passageway on a couple of occasions, since demolition will have to take place after the cable upgrades are complete.
Questions (1-2)
1. Can the water in the Cross Passageway be pumped directly into the Lock Chamber?
2. Can the Contractor request the date for the initial pumping and cleaning from the USACE? If cleaned by the USACE prior to the Contractor requiring access, a high water event could deposit debris and silt that will have to be removed from the Cross Passageway prior to the required access by the Electricians.
A10:
1. Pumping water from the crossover into the lock chamber is acceptable.
2. The USACE pumping/cleaning schedule is subject to availability and is anticipated this will be performed prior to the Contractor arriving on site. Should a high water event occur after the USACE cleanout and prior to Contractor access, USACE will address the need for additional debris clearing at that time.
Q11: Specifications Section 01 45 00.00 08, Paragraph 3.4.2 and 3.4.3
Questions (1-2)
1. Please confirm that the CQC Site System Manager can also have the role of SSHO (Site Safety and Health Officer).
2. Does the Specialized Personnel - Electrical Engineer QC listed in paragraph 3.4.3 need to be onsite at all times that the CQC Site System Manager is on site?
A11:
1. Per 01 35 26.00 08 paragraph 1.6.1.1.1 and section 01 45 00.00 08 paragraph 3.4.2 the role of SSHO and CQC manager can be filled by the same person. If one person is filling both roles they must meet the qualifications for both.
2. Per section 01 45 00.00 08 paragraph 3.4.3 the Electrical Engineer QC is required to “be on site be physically present at the construction site during work on the specialized personnel's areas of responsibility”
Q12: Is there a designated lay-down area for the contractor’s trailers and materials and if so, can the location and size of the area be identified?
A12: The contractor laydown/parking/storage area is outlined on drawing E-401. The area is approximately 19’ x 170’.
Q13: Can temporary power from the existing facility electrical service be made available for use by the Contractor or will a temporary electrical service be required?
A13: Contractor is responsible for all utilities. See Specifications SECTION 01 35 00.00 08 paragraph 1.6.5
Q14: In regard to the crossover pumping, can the Government provide an estimate on how many gallons a minute we will need to pump, and if this will be a sustained pumping throughout our entire onsite work or just at times?
A14: An initial pump out is underway to functionally dewater the crossover. Once complete, specification SECTION 01 35 00.00 08 paragraph 1.15 will be updated with the specifications of pumps used (current pump specs from previous attempts are listed). Crossover will only need to be dewatered while work is necessary in the crossover. The specifications has been revised to provide a more current status of the crossover conditions. See amendment W911WN21B8005-0001.
Q15: - In regard to the crossover pumping, if we utilized electric pumps, are we able to use the Government electricity or do we have to provide our own?
A15: Contractor is responsible for all utilities. See Specifications SECTION 01 35 00.00 08 paragraph 1.6.5.
Q16: I’m looking for clarification on the Interlock Cabinet. I don’t recall seeing this cabinet. Is this the new cabinet, that was briefly mentioned, that the vendor is to provide?
A16: That is correct, the Interlock Control Panel is a new enclosure to be provided by the Contractor.
Q17: If the answer to question 16 is yes. Is this cabinet to be located in the Power House?
A17: That is correct. See DWG# E-404 for proposed location on the second floor of the Power House. Note that existing air lines/equipment may need to be relocated.
Q18: We believe the scale is incorrect on some of the drawings. Below are the drawings and what we think the correct scales are.
- E-402 & E-403 (Scale on Drawings is 1/8”=1’, should be 1/16”=1’)
- E-404 (Scale on Drawing is ¼”=1’, should be 1/8”=1’)
A18: Scales have been updated. See Amendment W911WN21B8005-0001
(End of Questions and Answers)
SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS
The following have been modified:
SECTION 00 73 00
ADDENDUM TO SECTION 00 73 00 – SUPPLEMENTARY CONDITIONS
00 73 00 - 01 WAGE RATES
The wage rates identified in the below General Decision Number, Attachment 4, are incorporated into this solicitation and any resultant contract. The rates apply to all performed work.
General Decision Number: PA20210002 07/23/2021
Superseded General Decision Number: PA20200002
State: Pennsylvania
Construction Types: Heavy, Highway
Counties: Allegheny, Armstrong, Beaver, Bedford, Blair, Butler, Cambria, Cameron, Centre, Clarion, Clearfield, Clinton, Crawford, Elk, Erie, Fayette, Forest, Franklin, Fulton, Greene, Huntingdon, Indiana, Jefferson, Lawrence, McKean, Mercer, Mifflin, Potter, Somerset, Venango, Warren, Washington and Westmoreland Counties in Pennsylvania
HEAVY AND HIGHWAY CONSTRUCTION PROJECTS (excluding sewer grouting projects and excluding sewage and water treatment plant projects) https://sam.gov/wage-determination/PA20210002/8
00 73 00 - 02 PAYMENT FOR PERFORMANCE AND PAYMENT BONDS
a. In order to ensure that sufficient funds have been set-aside for payment of performance and payment bond premiums, bidders shall insert in Bid Schedule Item No. 0001, an appropriate not-to-exceed dollar amount. Failure of bidders to insert a not-to-exceed dollar amount in Bid Schedule Item No. 0001 will cause the bid to be rejected as non-responsive.
b. The Contractor shall be reimbursed the actual bond costs only, as established by evidence of full payment to the surety, up to the dollar amount set forth in Bid Schedule Item No. 0001. In no case will the Contractor be reimbursed an amount which exceeds the dollar amount set forth in Bid Schedule Item No. 0001.
c. The Government will reimburse only the Prime Contractor for actual paid bond premiums. The Government will not reimburse any subcontractor's paid bond premiums.
00 73 00 - 03 REQUIRED INSURANCE
a. The Contractor shall procure and maintain during the entire performance period of this contract, the following minimum insurance. (See also Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.228-5 Insurance – Work On A Government Installation (JAN 1997).)
Type Bodily Injury Amount Property Damage
Comprehensive General Liability $500,000 Per Occurrence $100,000
Automobile Liability $200,000 Each Person --
$500,000 Per Occurrence $ 20,000 Workmen’s Compensation and Employers Liability $100,000
b. The Contracting Officer will notify the Contractor of any noncompliance with the foregoing provisions. The Contractor shall, after receipt of such notice, immediately comply. Such notice, when delivered to the Contractor or his representative at the site or mailed to the Contractor's address, will be deemed sufficient for the purpose. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until the Contractor complies. No part of the time lost due to any such stop orders shall be made the subject of a claim for extension of time or for excess costs or damages by the Contractor. Compliance with the provisions of this article by subcontractors will be the responsibility of the Contractor.
c. Longshoreman and Harbor Worker's Insurance MAY be required for this work. Please consult with your insurance carrier and applicable statutes (33 USC 901, et. seq.).
00 73 00 - 04 SAFETY AND HEALTH REQUIREMENTS MANUAL
A copy of the current US Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1 and its changes are available at https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1- 1.pdf?ver=2015-04-09-142531-467
The Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
00 73 00 - 05 WORK UNDER OTHER CONTRACTS
Attention is directed to the fact that other Contractors may be employed by the Government or by local interests at or in the vicinity of the work covered by these specifications. All Contractors shall have equal rights to the use of all roads and grounds so far as practicable and this Contractor shall cooperate with other Contractors so that the work may be performed with the maximum efficiency. Should a disagreement occur between Contractors as to the use of?
facilities or in other matters, the decision of the Contracting Officer shall govern. (See also the Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.236-8 Other Contracts (APR 1984).)
00 73 00 - 06 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with FAR clause 52.249-10 entitled "Default (Fixed-Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied.
(1) The weather experienced at the project site during the contract period must be found to be unusually severe; that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. This delay must be beyond the control and without the fault or negligence of the Contractor.
b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all-weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
14 13 9 9 9 8 8 7 7 6 9 13
c. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more on the Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b. above, the Contracting Officer will convert any qualifying delays to work days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with FAR clause 52.249-10 entitled, "Default (Fixed-Price Construction)".
d. The anticipated adverse weather work days listed above are based on days with precipitation greater than 0.1 inch and/or maximum temperature below 32 degrees F. The numbers shown represent the number of work days (not calendar days) normally expected to have these particular weather conditions based on historical data. The actual number of days will vary. This information is furnished for computation of possible time extensions due to weather delays and is not intended to imply that no work can be done on these days. The Contractor shall make his own determination of the effect of these conditions on his operations under this contract, and schedule his work accordingly.
00 73 00 - 07 COPYING, DISSEMINATION OR DISTRIBUTION OF INFORMATION.
Those who disseminate information contained in the solicitations and/or drawings must ensure that the recipients have a legitimate need for the information and maintain a record of each recipient. Legitimate need means recognized business entities seeking to do business, or having business, with the Government as prime contractors, subcontractors or suppliers. You shall maintain a record of the following information on each recipient: Business name and address, the Unique Entity Identifier (formerly DUNS) Number, and name and telephone number of person receiving the information
00 73 00 - 08 SUBMISSION OF CONTRACT DOCUMENTATION
Provide contract documentation in an electronic format to the greatest extent practicable. Contract documentation to be submitted electronically includes, but is not limited to, the following:
Submittals, including ENG 4025 transmittal form Meeting Minutes Construction Photographs Correspondence Requests for Information Payroll Documents Statement and Acknowledgement Forms (SF 1413) Request for Additional Classification (SF 1444) Progress Payment Requests and Supporting Documentation Contract Modification Documentation, including SF 30, Contractor’s Offer, Cost/Pricing Audit Report, and Certificate of Current Cost or Pricing Data Contractor Quality Control Reports (with attachments) Accident Reports Schedules and Schedule Updates Closeout Documentation, including Release of Claims
Electronic files must be of sufficient quality that all information is legible. Electronic format shall be in Adobe.PDF format, unless otherwise specified or directed by the Contracting Officer. Whenever possible, PDF files shall be generated from original documents so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Files exceeding 30 pages shall be indexed and bookmarked to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.
Email electronic documents to an email address as directed by the Contracting Officer or their designated representative. Provide large electronic documents over 8.0 GB on an optical disc or for documents up to 8.0 GB through an electronic file sharing system which will be invitation from the Contracting Officer or their designated representative through a file sharing application. The file sharing system to be used is the Department of Defense (DoD) Secure Access File Exchange (SAFE) Web Application. The DoD SAFE site is located at the following website: https://safe.apps.mil/.
The Contractor shall be prepared to provide up to five (5) additional paper hard copies of any contract document at the discretion of the Contracting Officer, at no additional cost to the Government. In addition to the electronic file format described above, the following list of documents shall be provided in their original format because law or other regulations require signed originals be kept in accordance with FAR 4.805 -- Storage, Handling, and Disposal of Contract Files:
Advance Payment Bond Bid Bond including Annual Bid Bond Performance Bond including Annual Performance Bond Payment Bond Patent Infringement Bond Any performance security instruments Certificate of Insurance Novation/Change of Name Agreement Assignment of Claims Any document containing a raised seal. Examples include
Notarized documents Architecture Drawings
Paper Payroll Documents Physical signatures on contracts and modifications
SF 1442
SF 30
00 73 00 - 09 WORK PERFORMED BY CONTRACTOR
Within ten (10) calendar days after award of the contract, the successful bidder will be required to furnish a description of the work which he intends to perform with his own organization, the percentage of the total work this represents, and the estimated cost thereof.
00 73 00 - 10 CONTRACTOR QUALITY CONTROL
Section 01 45 00.00 08, QUALITY CONTROL, of this specification requires that the Contractor's Quality Control System Manager or person responsible for Contractor Quality Control complete the Corps of Engineers' "Construction Quality Management for Contractors" course not later than 90 calendar days after receipt of the Notice to Proceed. The course consists of approximately 12 hours of classroom instruction and is offered periodically by the Pittsburgh District. For additional information on scheduling and location of the training, contact U.S. Army Engineer District, Pittsburgh, Theresa BonAnno, U.S. Army Engineer District, Pittsburgh, Upper Ohio Area Office, 3510 Grand Avenue, Pittsburgh, Pennsylvania 15225, telephone (412) 395-7677. Certification of course completion is valid for 5 years. Completion of training offered by other Corps of Engineers Districts will be acceptable provided a valid certification is presented.
00 73 00 - 11 ELECTRONIC EMAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 calendar days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use e-mail to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple e-mail addresses are not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this e-mail address.
(End of Addendum)
(End of Summary of Changes)