Loyalhanna, Service Bridge Repairs
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 08
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 REFERENCES
1.2 SINGLE JOB PAYMENT ITEMS
1.2.1 Reimbursement For Actual Performance And Payment Bond Premiums
1.2.2 Mobilization and Demobilization
1.2.2.1 Payment
1.2.2.2 Unit of Measure
1.2.2.3 Payment Items
1.2.3 Playground Area Fence
1.2.3.1 Payment
1.2.3.2 Unit of Measure
1.2.3.3 Payment Items
1.2.4 Removal and Reinstallation of Gantry Crane Rails
1.2.4.1 Payment
1.2.4.2 Unit of Measure
1.2.4.3 Payment Items
1.2.5 Temporary Gantry Crane Rails and Rail Stops
1.2.5.1 Payment
1.2.5.2 Unit of Measure
1.2.5.3 Payment Items
1.2.6 Revise Deck Drain System, Monolith 5
1.2.6.1 Payment
1.2.6.2 Unit of Measure
1.2.6.3 Payment Item
1.2.7 Removal and Reinstallation of Utilities
1.2.7.1 Payment
1.2.7.2 Unit of Measure
1.2.7.3 Payment Item
1.2.8 Cleaning and Painting
1.2.8.1 Payment
1.2.8.2 Unit of Measure
1.2.8.3 Payment Items
1.2.9 Concrete Stair Repair, Monolith 5
1.2.9.1 Payment
1.2.9.2 Unit of Measure
1.2.9.3 Payment Item
1.2.10 Monolith 5 Supplemental Support Frame
1.2.10.1 Payment
1.2.10.2 Unit of Measure
1.2.10.3 Payment Item
1.2.11 Lighting Pole Support Pedestals
1.2.11.1 Payment
1.2.11.2 Unit of Measure
1.2.11.3 Payment Items
1.2.12 Service Bridge Electrical Work
SECTION 01 22 00.00 08 Page 1 Certified Final Document - Ammendment 1
1.2.12.1 Payment
1.2.12.2 Unit of Measure
1.2.12.3 Payment Item
1.3 UNIT PRICE PAYMENT ITEMS
1.3.1 Digital Progress Images
1.3.1.1 Payment
1.3.1.2 Measurement
1.3.1.3 Unit of Measure
1.3.1.4 Payment Items
1.3.2 Substrate Preparation
1.3.2.1 Payment
1.3.2.2 Measurement
1.3.2.3 Unit of Measure
1.3.2.4 Payment Items
1.3.3 Substrate Repair
1.3.3.1 Payment
1.3.3.2 Measurement
1.3.3.3 Unit of Measure
1.3.3.4 Payment Items
1.3.4 Wet Lay-up FRP System
1.3.4.1 Payment
1.3.4.2 Measurement
1.3.4.3 Unit of Measure
1.3.4.4 Payment Items
1.3.5 Concrete Demolition
1.3.5.1 Payment
1.3.5.2 Measurement
1.3.5.3 Unit of Measure
1.3.5.4 Payment Items
1.3.6 Latex Modified Concrete Deck Slab Overlay
1.3.6.1 Payment
1.3.6.2 Measurement
1.3.6.3 Unit of Measure
1.3.6.4 Payment Items
1.3.7 Concrete Placement
1.3.7.1 Payment
1.3.7.2 Measurement
1.3.7.3 Unit of Measure
1.3.7.4 Payment Items
1.3.8 Reinforcing Steel
1.3.8.1 Payment
1.3.8.2 Measurement
1.3.8.3 Unit of Measure
1.3.8.4 Payment Items
1.3.9 Seal Deck Joints
1.3.9.1 Payment
1.3.9.2 Measurement
1.3.9.3 Unit of Measure
1.3.9.4 Payment Items
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 CONTRACT COST BREAKDOWN
-- End of Section Table of Contents --
SECTION 01 22 00.00 08 Page 2
SECTION 01 22 00.00 08
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM A615/A615M (2016) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
1.2 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the SCHEDULE and described below.
All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.2.1 Reimbursement For Actual Performance And Payment Bond Premiums
Payment for reimbursement for actual performance and payment bond premiums will be made as specified in 00 73 00 SUPPLEMENTARY CONDITIONS, clause
PAYMENT FOR PERFORMANCE AND PAYMENT BONDS.
0001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS,
BASE CONTRACT
1001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS,
AWARDABLE OPTION 1
2001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS,
AWARDABLE OPTION 2
3001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS,
AWARDABLE OPTION 3
1.2.2 Mobilization and Demobilization
1.2.2.1 Payment
Payment will be made for costs associated with mobilization and demobilization, as defined in Section 00 73 00 SUPPLEMENTARY CONDITIONS, DFARS 252.236-7004 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION . Payment will only be made for Mobilization and Demobilization for Awardable
SECTION 01 22 00.00 08 Page 3
Options if demobilization is required between the previous Base or Awardable Option and the current Awardable Options or if demobilization is required during the period of the current Awardable Option. No payment will be made if no demobilization and remobilization occurs during a specific contract period.
1.2.2.2 Unit of Measure
Unit of measure: Job.
1.2.2.3 Payment Items
0003 PAYMENT FOR MOBILIZATION AND AND DEMOBILIZATION, BASE CONTRACT
1003 PAYMENT FOR MOBILIZATION AND AND DEMOBILIZATION, AWARDABLE
OPTION 1
2003 PAYMENT FOR MOBILIZATION AND AND DEMOBILIZATION, AWARDABLE
OPTION 2
1.2.3 Playground Area Fence
1.2.3.1 Payment
Payment will be made for costs associated with furnishing and installing the project safety fencing at the playground area along the dam access road and for removing the fence upon completion of the work as specified in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS. This item also includes removal of the fence after all contract work is completed.
1.2.3.2 Unit of Measure
Unit of measure: Job
1.2.3.3 Payment Items
0004 PLAYGROUND AREA FENCE
20187 REMOVE PLAYGROUND AREA FENCE
1.2.4 Removal and Reinstallation of Gantry Crane Rails
1.2.4.1 Payment
Payment will be made for costs associated with removal and reinstallation of the gantry crane rails, as specified in Section 02 41 00 DEMOLITION.
1.2.4.2 Unit of Measure
Unit of measure: Job
1.2.4.3 Payment Items
0005 REMOVE AND REINSTALL GANTRY CRANE RAILS, BASE CONTRACT
1004 REMOVE AND REINSTALL GANTRY CRANE RAILS, AWARDABLE OPTION 1
2004 REMOVE AND REINSTALL GANTRY CRANE RAILS, AWARDABLE OPTION 2
SECTION 01 22 00.00 08 Page 4
1.2.5 Temporary Gantry Crane Rails and Rail Stops
1.2.5.1 Payment
Payment will be made for costs associated with furnishing, installing, and removing temporary rail stops; and furnishing, installing, and removing temporary crane rails, as specified in Section 02 41 00 DEMOLITION.
1.2.5.2 Unit of Measure
Unit of measure: Job
1.2.5.3 Payment Items
0006 FURNISH, INSTALL AND REMOVE TEMPORARY CRANE RAILS AND RAIL
STOPS, BASE CONTRACT
1005 FURNISH, INSTALL AND REMOVE TEMPORARY CRANE RAILS AND RAIL
STOPS, AWARDABLE OPTION 1
2005 FURNISH, INSTALL AND REMOVE TEMPORARY CRANE RAILS AND RAIL
STOPS, AWARDABLE OPTION 2
1.2.6 Revise Deck Drain System, Monolith 5
1.2.6.1 Payment
Payment will be made for costs associated with installation of new deck drain systems as specified and as shown on the drawings.
1.2.6.2 Unit of Measure
Unit of measure: Job
1.2.6.3 Payment Item
0007 REROUTE PIPING AND INSTALL DRAINS - MONOLITH 5
1.2.7 Removal and Reinstallation of Utilities
1.2.7.1 Payment
Payment will be made for costs associated with Removal and Replacement/Reinstallation of all utilities affected by the required work as shown on the plans and reference drawings.
1.2.7.2 Unit of Measure
Unit of measure: Job
1.2.7.3 Payment Item
0008 REMOVE AND REINSTALL UTILITIES
1.2.8 Cleaning and Painting
1.2.8.1 Payment
Payment will be made for costs associated with lead-based paint removal and disposal, surface preparation and painting the recess frame, drains, and steel bridge structure as described in Section 09 97 02 PAINTING:
SECTION 01 22 00.00 08 Page 5
HYDRAULIC STRUCTURES. Payment under this item includes containment and disposal of removed materials.
1.2.8.2 Unit of Measure
Unit of measure: Job
1.2.8.3 Payment Items
0009 CLEAN AND PAINT RECESS FRAME AND DRAINS
002930 CLEAN AND PAINT SERVICE BRIDGE STRUCTURE, SPAN 6 - 7
10121 CLEAN AND PAINT SERVICE BRIDGE STRUCTURE, SPANS 7 - 8 AND 8 - 9
20176 CLEAN AND PAINT SERVICE BRIDGE STRUCTURE, SPANS 9 - 10 AND 10 -
1.2.9 Concrete Stair Repair, Monolith 5
1.2.9.1 Payment
Payment will be made for costs associated with repair of the concrete stairs in Monolith 5. Payment under this item includes repair of the stairs and replacement of the handrail.
1.2.9.2 Unit of Measure
Unit of measure: Job
1.2.9.3 Payment Item
0010 MONOLITH 5 CONCRETE STAIR REPAIR
1.2.10 Monolith 5 Supplemental Support Frame
1.2.10.1 Payment
Payment will be made for costs associated with furnishing and installing the supplemental support frame in Monolith 5 as specified and as shown on the drawings. Payment under this item includes furnishing and installing the supplemental support including fabrication and installation of brackets.
1.2.10.2 Unit of Measure
Unit of measure: Job
1.2.10.3 Payment Item
0017 MONOLITH 5 SUPPLEMENTAL SUPPORT FRAME
1.2.11 Lighting Pole Support Pedestals
1.2.11.1 Payment
Payment will be made for costs associated with construction of light pole supports, including demolition where required, constructing concrete pedestals, and furnishing and installing embedded conduits, junction boxes, and anchors as specified and as shown on the drawings.
SECTION 01 22 00.00 08 Page 6
1.2.11.2 Unit of Measure
Unit of measure: Job
1.2.11.3 Payment Items
3004 0023 LIGHTING POLE SUPPORT PEDESTALS, AWARDABLE OPTION 3BASE
CONTRACT
2011 LIGHTING POLE SUPPORT PEDESTALS, AWARDABLE OPTION 2
1.2.12 Service Bridge Electrical Work
1.2.12.1 Payment
Payment will be made for costs associated with furnishing and installing the electrical features on the Service Bridge as described in Section 26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL. Payment for constructing the pedestal bases is included Items LIGHTING POLE SUPPORT PEDESTALS. Electrical work in connection with the concrete repairs in the Work Bay in Monolith 5 are included in Item REMOVE AND REINSTALL
UTILITIES.
1.2.12.2 Unit of Measure
Unit of measure: Job
1.2.12.3 Payment Item
3003 SERVICE BRIDGE ELECTRICAL WORK
1.3 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the SCHEDULE and described below. The unit price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.3.1 Digital Progress Images
1.3.1.1 Payment
Payment shall constitute full compensation for all costs in connection with completing this item of work as specified in Section 01 32 33 DIGITAL
PROGRESS IMAGES.
1.3.1.2 Measurement
Measurement shall be based on monthly sets of progress photographs that are approved and accepted by the Contracting Officer or their designated representative.
1.3.1.3 Unit of Measure
Unit of measure: Sets.
SECTION 01 22 00.00 08 Page 7
1.3.1.4 Payment Items
0002 DIGITAL PROGRESS IMAGES, BASE CONTRACT
1002 DIGITAL PROGRESS IMAGES, AWARDABLE OPTION 1
2002 DIGITAL PROGRESS IMAGES, AWARDABLE OPTION 2
3002 DIGITAL PROGRESS IMAGES, AWARDABLE OPTION 3
1.3.2 Substrate Preparation
1.3.2.1 Payment
Payment for this item shall constitute full compensation for all labor, equipment, material, and supply costs for surface preparation for the FRP system, and other incidentals as shown on the drawings and specified in Section 03 01 40.13 REPAIR AND RETROFIT OF REINFORCED CONCRETE BEAMS USING BONDED CFRP COMPOSITES and Section 03 01 40.15 REPAIR AND RETROFIT OF
REINFORCED CONCRETE SLAB USING BONDED GFRP COMPOSITES.
1.3.2.2 Measurement
The quantity of substrate preparation will be measured for payment to the nearest square foot, based on the area of the applied FRP system, as approved by the Contracting Officer or their designated representative.
1.3.2.3 Unit of Measure
Unit of measure: Square Feet
1.3.2.4 Payment Items
0011 MONOLITH 5 SUBSTRATE PREPARATION FOR GFRP
0014 MONOLITH 5 SUBSTRATE PREPARATION FOR CFRP
1.3.3 Substrate Repair
1.3.3.1 Payment
Payment for this item shall constitute full compensation for all labor, equipment, material, and supply costs for preparation and placement of substrate repairs to include removal of unsound concrete, repair and cleaning of reinforcement, application of corrosion inhibitor, sawcutting, restoration of the concrete section, and other incidentals as shown on the drawings and specified in Section 03 01 40.13 REPAIR AND RETROFIT OF REINFORCED CONCRETE BEAMS USING BONDED CFRP COMPOSITES and Section
03 01 40.15 REPAIR AND RETROFIT OF REINFORCED CONCRETE SLAB USING BONDED
GFRP COMPOSITES.
1.3.3.2 Measurement
The quantity of substrate repair and preparation will be measured for payment to the nearest cubic foot of area repaired, based on the area of distress established by visual means, sounding, and pressure washing as specified in these specifications and as approved by the Contracting Officer or their designated representative.
1.3.3.3 Unit of Measure
Unit of measure: Cubic Feet
SECTION 01 22 00.00 08 Page 8
1.3.3.4 Payment Items
0012 MONOLITH 5 SUBSTRATE REPAIR FOR GFRP
0015 MONOLITH 5 SUBSTRATE REPAIR FOR CFRP
1.3.4 Wet Lay-up FRP System
1.3.4.1 Payment
Payment for this item shall constitute full compensation for all labor, equipment, material, and supply costs for placement of the FRP system to include primer, putty, saturant, resin, fiber fabric, and other incidentals as shown on the drawings and specified in Section 03 01 40.13
REPAIR AND RETROFIT OF REINFORCED CONCRETE BEAMS USING BONDED CFRP
COMPOSITES and Section 03 01 40.15 REPAIR AND RETROFIT OF REINFORCED
CONCRETE SLAB USING BONDED GFRP COMPOSITES.
1.3.4.2 Measurement
The quantity of wet lay-up CFRP system will be measured for payment to the nearest square foot of each layer applied, based on the area of actual CFRP laminate installed.
1.3.4.3 Unit of Measure
Unit of measure: Square Feet
1.3.4.4 Payment Items
0013 MONOLITH 5 WET LAY-UP GFRP SYSTEM
0016 MONOLITH 5 WET LAY-UP CFRP SYSTEM
1.3.5 Concrete Demolition
1.3.5.1 Payment
Payment will be made for all work necessary for concrete removal and disposal as specified in 02 41 00 DEMOLITION and shown on the plans.
Payment for items associated with disassembly, assembly, and protection of the dogging devices shall be included under these items.
1.3.5.2 Measurement
Concrete Demolition will be measured for payment by square foot, cubic foot, or cubic yard, in the presence of the Contracting Officer or their designated representative, by field measurements to the nearest inch. The payment will be made at the applicable contract unit price per square foot or cubic foot for the payment items. Quantities will be computed to the nearest whole square foot.
1.3.5.3 Unit of Measure
Unit of Measure: Cubic Feet, Cubic Yard
1.3.5.4 Payment Items
The following items are measured by Cubic Feet:
0018 MONOLITH 6 AND PIER 7 CONCRETE DEMOLITION
SECTION 01 22 00.00 08 Page 9
0020 PARAPET CONCRETE DEMOLITION, BASE CONTRACT
00278 MISCELLANEOUS CONCRETE DEMOLITION, BASE CONTRACT
1006 PIERS 8 AND 9 CONCRETE DEMOLITION
2006 PIER 10, MONOLITHS 11 AND 12 CONCRETE DEMOLITION
2008 PARAPET CONCRETE DEMOLITION, AWARDABLE OPTION 2
2015 MISCELLANEOUS CONCRETE DEMOLOTION, OPTION 2
The following items are measured by Cubic Yard:
00234 CONCRETE BRIDGE DECK SLAB DEMOLITION, SPAN 6 - 7
1008 CONCRETE BRIDGE DECK SLAB DEMOLITION, SPANS 7 - 8 AND 8 - 9
20112 CONCRETE BRIDGE DECK SLAB DEMOLITION, SPANS 9 - 10 AND 10 - 11
1.3.6 Latex Modified Concrete Deck Slab Overlay
1.3.6.1 Payment
Payment will be made for all work necessary for concrete placement as specified in 03 01 00 REHABILITATION OF CONCRETE, and as shown on the plans. Contractor shall furnish all necessary materials to complete the work.
1.3.6.2 Measurement
The Latex Modified Concrete Deck Slab Overlay will be measured for payment by the cubic foot placed, in the presence of the Contracting Officer or their designated representative, by field measurements to the nearest inch. The payment will be made at the applicable contract unit price per cubic foot for the payment items. Quantities will be computed to the nearest cubic foot.
1.3.6.3 Unit of Measure
Unit of Measure: Cubic Feet
1.3.6.4 Payment Items
0019 MONOLITH 6 AND PIER 7 LATEX MODIFIED CONCRETE DECK SLAB OVERLAY
1007 PIER 8 AND 9 LATEX MODIFIED CONCRETE DECK SLAB OVERLAY
2007 PIER 10, MONOLITHS 11 AND 12 LATEX MODIFIED CONCRETE DECK SLAB
OVERLAY
1.3.7 Concrete Placement
1.3.7.1 Payment
Payment will be made for all work necessary for furnishing and installing concrete, including reinforcement as specified in Sections 03 01 00 REHABILITATION OF CONCRETE, 03 20 01.00 10 CONCRETE REINFORCEMENT, and 03 20 01.00 10 CONCRETE REINFORCEMENT, and as shown on the plans.
1.3.7.2 Measurement
Concrete Placement will be measured for payment by the cubic foot placed or square foot placed, by the dimensions listed on the project drawings.
The payment will be made at the applicable contract unit price per cubic foot or square foot for the payment items. Quantities will be computed to the nearest cubic foot or square foot. Wasted concrete will not be measured for payment. Payment for Miscellaneous Concrete Repair Type 2
SECTION 01 22 00.00 08 Page 10 will include furnishing and installing anchorage and reinforcing steel.
1.3.7.3 Unit of Measure
Unit of Measure: Cubic Feet, Cubic Yard
1.3.7.4 Payment Items
The following items are measured by Cubic Feet:
0021 PARAPET CONCRETE REPAIR, BASE CONTRACT
00289 MISCELLANEOUS CONCRETE REPAIR, BASE CONTRACT
2009 PARAPET CONCRETE REPAIR, AWARDABLE OPTION 2
2016 MISCELLANEOUS CONCRETE REPAIR, OPTION 2
The following items are measured by Cubic Yard:
00245 CONCRETE BRIDGE DECK SLAB CONCRETE, SPAN 6-7
1009 CONCRETE BRIDGE DECK SLAB CONCRETE, SPANS 7-8 AND 8-9
20123 CONCRETE BRIDGE DECK SLAB CONCRETE, SPANS 9-10 AND 10-11
1.3.8 Reinforcing Steel
1.3.8.1 Payment
Payment will be made for costs associated with furnishing, transporting, delivering, and placing deformed steel bars for concrete reinforcement, which includes steel in laps as indicated or as required. No payment will be made for the additional steel in laps which are authorized for the convenience of the Contractor. Payment for reinforcing steel in Concrete Repair Type 2 will be included in the contract unit price for
MISCELLANEOUS CONCRETE REPAIR.
1.3.8.2 Measurement
Measurement of reinforcing steel will be based on the actual weight of materials as shown on the approved shop drawings and as approved by the Contracting Officer or their designated representative. The measured lengths will be converted to weights for the size of bars listed by the use of the nominal weights per linear foot specified in ASTM A615/A615M .
Steel in laps indicated on the drawings or required by the Contracting Officer or their designated representative will be paid for at the contract unit price. No payment will be made for the additional steel in laps which are authorized for the convenience of the Contractor.
1.3.8.3 Unit of Measure
Unit of Measure: Pounds.
1.3.8.4 Payment Items
0022 PARAPET REINFORCING STEEL, BASE CONTRACT
00256 CONCRETE BRIDGE DECK SLAB, SPAN 6 - 7, REINFORCING STEEL
1010 CONCRETE BRIDGE DECK SLAB, SPANS 7 - 8 AND 8 - 9, REINFORCING
STEEL
2010 PARAPET REINFORCING STEEL, AWARDABLE OPTION 2
20134 CONCRETE BRIDGE DECK SLAB, SPANS 9 - 10 AND 10 - 11,
REINFORCING STEEL
SECTION 01 22 00.00 08 Page 11
1.3.9 Seal Deck Joints
1.3.9.1 Payment
Payment will be made for costs associated with cleaning out and resealing the monolith joints at Monolith 5 and Monolith 6. The price shall include the cost of all labor, materials, and the use of all equipment and tools required to remove vegetation, existing joint material and other debris, clean the joints, and reseal the joints as shown on the drawings and as specified.
1.3.9.2 Measurement
The quantity of to be paid for shall be determined by actual measurement of the number of linear feet of in-place material that has been accepted by the Contracting Officer or their designated representative.
1.3.9.3 Unit of Measure
Unit of Measure: Linear Feet
1.3.9.4 Payment Items
00267 SEAL DECK JOINTS, BASE CONTRACT
1011 SEAL DECK JOINTS, AWARDABLE OPTION 1
20145 SEAL DECK JOINTS, AWARDABLE OPTION 2
3004 SEAL DECK JOINTS, AWARDABLE OPTION 3
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 CONTRACT COST BREAKDOWN
The Contractor must furnish within 30 calendar days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer or their designated representative as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items.
This contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.
-- End of Section --
SECTION 01 22 00.00 08 Page 12
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 23.00 08
SURVEY AND ALIGNMENT CONTROL
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 MEASUREMENT AND PAYMENT
1.4 SUBMITTALS
1.5 DIFFERENTIAL GLOBAL POSITIONING SYSTEM (DGPS) EQUIPMENT
1.6 TOPOGRAPHIC SURVEYS
1.7 SURVEYING EQUIPMENT
1.8 QUALIFICATIONS
1.9 QUALITY ASSURANCE
1.10 EXISTING CONDITIONS
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 GENERAL SURVEY REQUIREMENTS
3.1.1 Survey Procedures and Equipment
3.1.2 Vertical and Horizontal Datums
3.1.3 Tolerances
3.2 SURVEY CONTROL
3.3 AFTER SUBGRADE CONSTRUCTION AND AFTER CONSTRUCTION SURVEYS
3.3.1 General
3.4 DATA SUBMISSION
3.5 DISCREPANCIES
3.6 METADATA SUBMISSION
3.7 MEASUREMENT AND PAYMENT
-- End of Section Table of Contents --
SECTION 01 32 23.00 08 Page 1
SECTION 01 32 23.00 08
SURVEY AND ALIGNMENT CONTROL
PART 1 GENERAL
1.1 SUMMARY
This section addresses the overall project survey control and procedure requirements to meet all survey/positional accuracy requirements for this contract.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
GERMAN INSTITUTE FOR STANDARDIZATION (DIN)
DIN 18723 (1990-07) Specification for Theodolite Accuracy
INTERNATIONAL ORGANIZATION FOR STANDARDIZATION (ISO)
ISO 17123-4 (2012) Optics And Optical Instruments - Field Procedures For Testing Geodetic And Surveying Instruments - Part 4:
Electro-Optical Distance Meters (EDM Measurements To Reflectors)
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-1-1005 (2007) Control and Topographic Surveying
EM 1110-2-1003 (2013) Hydrographic Surveying
1.3 MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work specified in this section and all costs in connection therewith shall be included in the costs of all the bid items.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
NOTE: Any submittals classified as "SD-01 Preconstruction Submittals" require approval prior to mobilization to the contract work site. All other submittals, classified as "SD-02" through "SD-11," require approval prior to commencing the particular task to which the submittal is associated.
SECTION 01 32 23.00 08 Page 2
SD-01 Preconstruction Submittals
Qualifications; G, RO
Survey Procedures and Equipment; G, RO
Submit all surveying procedures and equipment to the Government Survey Point of Contact prior to the start of any surveying work.
Existing Conditions; G, DO
SD-07 Certificates
Data Submission; G, RO
Submit survey logs to the District Survey Point of Contact and Contracting Officer or their designated representative.
After Subgrade Construction And After Construction Surveys; G, RO
Submit after subgrade construction and after construction surveys as required herein, including raw data collector files and all data and plotted drawings as specified herein, within 72 hours after collection of a survey data.
Metadata; G, DO
Submit metadata within 14 business days after completion of survey operations.
1.5 DIFFERENTIAL GLOBAL POSITIONING SYSTEM (DGPS) EQUIPMENT
The Contractor must have at least one Differential/Real-Time/RTK/RTN GPS/GNSS receiver, and shall conduct all GPS/GNSS surveys in accordance with EM 1110-2-1003 . All real-time positioning data submitted must include GPS/GNSS base files (RINEX or Trimble format), GPS/GNSS rover files, base-rover vectors, northing, easting, ellipsoid height, elevation, date and time each record (point) was collected. All GPS/GNSS Receivers shall be set to log satellite data to be included with data submittals.
Any RTN/VRS rovers used shall be set to log vector data.
1.6 TOPOGRAPHIC SURVEYS
The Contractor shall perform all topographic surveys in accordance with EM 1110-1-1005 , and shall conduct all topographic surveys utilizing RTK/RTN-GPS/GNSS or an "auto-lock" or robotic total station. A data collector that writes digital files shall be used in conjunction with the GPS/GNSS receivers or total station to record any and all field survey data. Record a three-dimensional raw electronic vector, and corresponding position for each data point. RTN/VRS field surveys are acceptable if and only if localization/checks on USACE-provided survey control is performed on each day RTN/VRS is used in the field. All raw digital data shall be included with submittals and shall be submitted in a format compatible with Trimble Business Center or Bentley InRoads.
1.7 SURVEYING EQUIPMENT
All total stations used in conjunction with this Contract shall have a valid calibration certificate ("valid" is defined as dated within that
SECTION 01 32 23.00 08 Page 3 past 12 months) from an independent instrument service facility, shall be capable of at least an "auto-lock" function that will automatically turn angles to a stationary tripod-mounted prism (higher performance capabilities such as robotic prism tracking are acceptable and recommended), be rated at an angular accuracy ( DIN 18723 ) of 3" (three seconds of arc) or less, and be rated at a distance measurement accuracy ( ISO 17123-4 ) of 2mm + 2ppm or less. All GPS/GNSS receivers used in conjunction with this contract shall be capable of creating data files that can be converted to a RINEX (Receiver INdependent EXchange) format.
All automatic/spirit levels used for control, geodetic, or Quality Control purposes in conjunction with this Contract shall be a digital level, eaning that they read the level rod automatically and be capable of writing a digital file of observations that contains BS/FS observations and date & time of observations. All level rods used for control, geodetic, or Quality Control purposes in conjunction with this contract shall be equipped with a bar code that matches the digital level it is to be used with.
1.8 QUALIFICATIONS
Any and all field surveys shall be performed under the direct physical on-site supervision of a surveyor with a minimum of five years of current and relevant experience and licensed in the Commonwealth of Pennsylvania, and in accordance with the laws and regulations of the Commonealth of Pennsylvania.
1.9 QUALITY ASSURANCE
Quality assurance will be conducted by the District Survey Office on a minimum of 10 percent of the Contractor's survey work. To accomplish this, the District survey office will either re-survey areas or observe the Contractor in conducting their surveys or inspect submitted raw and processed data.
1.10 EXISTING CONDITIONS
Before beginning any demolition work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions in the presence of the Contracting Officer or their designated representative showing the condition of structures and other facilities adjacent to areas of alteration or removal. Electronic photographs or videos will be acceptable as a record of existing conditions except for elevation data. Elevation data shall be submitted in drawing format. Include in the record the elevation of the top of concrete decks, possible conflicting utilities, the location and extent of existing cracks and other damage and description of surface conditions that exist before starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. All surveying shall be conducted by a Registered Professional Surveyor with appropriate equipment as outlined in this specification.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 GENERAL SURVEY REQUIREMENTS
Conduct all surveys required to demonstrate that the construction is in
SECTION 01 32 23.00 08 Page 4 compliance with the specified placement tolerances and the lines, grades, and elevations shown on the drawings.
3.1.1 Survey Procedures and Equipment
Submit all surveying procedures and equipment to the Government Survey Point of Contact prior to the start of any surveying work.
3.1.2 Vertical and Horizontal Datums
Utilize North American Vertical Datum (NAVD) 1988 as the vertical/elevation reference datum. Utilize the State Plane Coordinate System (NAD 1983) of the State the project site is in as the horizontal reference datum.
3.1.3 Tolerances
Conduct topographic surveys utilizing procedures and methodology that meet or exceed accuracy tolerances of +/- 0.10 feet in the vertical and +/-
0.10 feet in the horizontal. Take complete notes in areas where obstructions are present, explaining the offset.
3.2 SURVEY CONTROL
a. Existing horizontal and vertical control to be used for all construction layout is shown on the contract drawings and is on the internet via the USACE Survey Monument Archival & Retrieval Tool (U-SMART) website at http://usmart.usace.army.mil .
b. b. All new work to be constructed under this Contract shall be constructed based on the survey control established by the Government (Pittsburgh District Geospatial Section) and provided to the Contractor. The Contractor shall verify that control points check within themselves prior to commencing work and utilize U-SMART to report any destroyed/disturbed control. If control points do not check within themselves or have been destroyed/disturbed, submit a request through the Contracting Officer for the USACE Pittsburgh District Geospatial Section to re-establish control. The request shall be made at least 14 calendar days prior to the intended use of the control. The Contractor shall establish any other temporary survey control as may be necessary to carry out the requirements of this Contract. Any and all temporary control set by the Contractor shall be based off the existing control as provided by the Government. Any questions or problems concerning the survey control shall be directed to the Pittsburgh District Geospatial Section through the Contracting Officer.
3.3 AFTER SUBGRADE CONSTRUCTION AND AFTER CONSTRUCTION SURVEYS
3.3.1 General
Take sufficient topography within the site to discern 1 foot contour intervals. Surveys shall also be taken after construction.
3.4 DATA SUBMISSION
Transfer all raw field survey data digitally onto compact disc (CD) or through the Resident Management System (RMS) in accordance with Section 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) in a
SECTION 01 32 23.00 08 Page 5 format compatible with Trimble Business Center, Bentley InRoads, or Autodesk Civil 3D.
Submit all survey data in the following formats:
a. Trimble JobXML (.jxl), Trimble Job (.job), or Bentley InRoads- or Autodesk Civil 3D- compatible format that shall contain all raw base/rover or backsight/standpoint/foresight vectors along with calculated coordinates/points/features.
b. Trimble-compatible (.T02, etc) or RINEX format GPS/GNSS data logs for every base or rover used in any Differential/Real-Time/RTK/RTN GPS/GNSS data collection.
c. Raw/unadjusted leveling data in .DAT format from any digital leveling.
d. Plotted and electronic plan view drawings in DXF format with accompanying LandXML that contains the DTM/TIN data. Drawings should show contour lines at a 1 foot interval and all other onsite features/structures. Submit a copy of the plan view drawings in PDF format. Please note that any and all necessary reference files shall be included as DXF or LandXML.
3.5 DISCREPANCIES
In the event of any discrepancies that cannot be resolved by the District Office Geospatial Section Quality Assurance review of the Contractor's data, the Contracting Officer may request an additional survey be performed by the Pittsburgh District Survey Section. The results of the Government survey will be considered in the final determination made by the Contracting Officer to resolve any conflicts.
3.6 METADATA SUBMISSION
Provide metadata file(s) for all geospatial data produced under this Contract that are compatible with ESRI ArcGIS applications. (Information on ESRI ArcGIS is available at the following link: http://www.esri.com .)
The metadata file(s) must comply with Federal Geographic Data Committee (FGDC) Content Standards for Digital Geospatial Metadata Version 2.0 or higher. If another metadata generation tool is used, the ".txt" or ".doc" file types will be sufficient, however the ".xml" alternative file type would be preferred.
Geospatial data is defined as information that identifies the geographic location and characteristics of natural or constructed features and boundaries on the earth. Geospatial data affected by these requirements are those generated for use in a:
Geographic Information System (GIS);
Land Information System (LIS);
Remote Sensing or Image processing system;
Computer-Aided Design and Drafting (CADD) system;
Automated Mapping/Facilities Management (AM/FM) system and Other computer systems that employ or reference data using either absolute, relative or assumed coordinates.
Provide digital FGDC compliant metadata file(s) for each deliverable product and data set outlined in these specifications.
SECTION 01 32 23.00 08 Page 6
Metadata standards can be found at http://www.fgdc.gov/metadata .
3.7 MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work specified in this section and all costs in connection therewith shall be included in the costs of all the bid items
-- End of Section --
SECTION 01 32 23.00 08 Page 7
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 35 00.00 08
SPECIAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 SUBMITTALS
1.4 CONTRACTOR RESPONSIBILITIES
1.4.1 General
1.4.2 Licenses and Permits
1.5 DRAWINGS
1.5.1 Contract Drawings
1.5.2 Reference Drawings
1.5.3 Reference Datum
1.5.4 Existing Condition Photographs
1.6 ACCESS
1.6.1 Access to Dam from Water
1.6.2 Launching of Floating Plant
1.6.3 Loading of Construction Materials and Employees
1.6.4 Access to Employee Loading Area
1.6.5 Trash Boom
1.7 WORK AREAS AND RESTRICTIONS
1.7.1 Work Areas
1.7.2 Subcontractors and Personnel Contacts
1.7.3 Identification Badges
1.7.4 Access
1.7.5 Security Gate on Dam
1.7.6 Hauling Materials and Equipment
1.7.6.1 General
1.7.6.2 Hauling Permits
1.7.7 Laydown, Storage and Parking Areas
1.7.8 Public Use
1.7.9 Utilities
1.7.10 Other Contractors
1.7.11 Working Hours
1.8 FEDERAL HOLIDAYS
1.9 EXISTING SURVEY CONTROLS
1.9.1 Project Alignment
1.10 CONTRACTOR'S FLOATING PLANT
1.10.1 General
1.10.2 Equipment Requirements
1.10.3 Maintenance of Floating Plant
1.10.4 Mooring of Floating Plant
1.10.5 Suspension of Construction
1.10.5.1 Withdrawal of Equipment and Floating Plant
1.10.5.2 Plan of Action, Withdrawal of Equipment and Floating Plant
1.10.5.3 Compensation and Extension of Contract Period, Suspension of Work
SECTION 01 35 00.00 08 Page 1
1.10.6 Operation of Small Watercraft
1.11 BUSH RECREATIONAL AREA STAGING FACILITY
1.11.1 General
1.11.2 Security of Staging Facility
1.11.3 Suspension of Usage
1.11.3.1 Withdrawal of Equipment and Materials
1.11.3.2 Compensation and Extension of Contract Period, Suspension of Usage
1.12 PROTECTION AND MAINTENANCE OF ROAD TRAFFIC
1.13 DAMAGE TO WORK
1.14 PROTECTION OF UTILITIES
1.15 INSPECTIONS AND ACCEPTANCE OF WORK
1.16 OPERATION OF GOVERNMENT FACILITY
1.16.1 Coordination with Project Operations
1.16.2 Daily Operations, Releases
1.16.3 Operation of Discharge Controls
1.17 SAFETY AND HEALTH REQUIREMENTS
1.18 POOL LEVELS
1.19 SCAFFOLDING
1.19.1 Attachment to Existing Structure
PART 2 PRODUCTS
2.1 PRODUCTS AND PARTS OF STANDARD MANUFACTURE
PART 3 EXECUTION
3.1 SEQUENCE OF WORK
3.2 PROTECTION OF EXISTING FACILITIES
3.2.1 Dogging Devices
3.2.2 Concrete Surfaces
3.2.3 Inspection of Protective Measures
3.2.4 Removal of Protective Measures and Clean up
3.3 ANTITERRORISM (AT) AND PROJECT SPECIFIC SECURITY REQUIREMENTS
3.3.1 AT Level I Training
3.3.2 Access and General Protection/Security Policy and Procedures
3.3.3 Suspicious Activity Reporting Training
3.3.4 Contractor Employees Who Require Access to Government
Information Systems
3.3.5 OPSEC Training
3.3.6 Escort of Contractor Employees
3.3.7 Pre- screen Candidates Using E-Verify Program
3.3.8 Threat Awareness Reporting Program
3.3.9 Changes in Security Requirements
-- End of Section Table of Contents --
SECTION 01 35 00.00 08 Page 2
SECTION 01 35 00.00 08
SPECIAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
This section addresses the general requirements applicable to the performance of the work under this contract. These requirements are in addition to those specified in other sections of the contract. See also Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS for requirements for temporary facilities, traffic control, and project safety fencing.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
U.S. ARMY (DA)
DA AR 25-2 (2007; RAR 2009) Information Assurance
DA AR 381-12 (2016) Threat Awareness and Reporting Program
U.S. DEPARTMENT OF HOMELAND SECURITY (DHS)
HSPD-12 (2004) Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
EM 1110-2-1902 (2003) Slope Stability
EM 1110-2-2104 (1992; R 2003) Strength Design for Reinforced - Concrete Hydraulic Structures
EM 1110-2-2105 (1993) Design of Hydraulic Steel Structures
EM 1110-2-2502 (1989) Retaining and Flood Walls
EM 1110-2-2503 (1989) Design of Sheet Pile Cellular Structures Cofferdams & Retaining Structures
EM 1110-2-2504 (1994) Design of Sheet Pile Walls
SECTION 01 35 00.00 08 Page 3
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having an "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Propelling Unit Agreement; G, RO
The written agreement between the Contractor and the lessor documenting the requirement for required towboat or propelling unit to be on site within the specified time limit shall be provided to the Contracting Officer or their designated representative prior to mobilization of any floating plant to the work site.
Temporary Mooring Facilities; G, RO
The Contractor shall submit any proposed plans for development of temporary moorings to the Contracting Officer or their designated representative. Moorings shall be designed in accordance with the requirements herein.
Plan of Action, Withdrawal of Equipment and Floating Plant; G, RO
The Contractor shall prepare and submit a Plan of Action for withdrawal of equipment and floating plant in accordance with paragraph Plan of Action, Withdrawal of Equipment and Floating Plant.
Small Watercraft Operations Plan; G, RO
The Contractor shall develop and submit a plan for operation of small watercraft within the area of the dam.
Access Plan; G, RO
List of Contact Personnel; G, RO
Trash Boom Disassembly Plan; G, RO
SD-07 Certificates
AT Level I Training; G, RO
Threat Awareness Reporting Program
Suspicious Activity Reporting Training
OPSEC Training
Iwatch/Or/Corps Watch Briefing/Training; G, RO
SECTION 01 35 00.00 08 Page 4
1.4 CONTRACTOR RESPONSIBILITIES
1.4.1 General
Responsibilities of the Contractor include, but shall not be limited to, all planning, programming, administration, coordination, and management to ensure that all work is performed in accordance with all laws, regulations, codes or directives. The Contractor shall be responsible for ensuring that the work performed meets or exceeds the requirements of the contract. The Contractor shall perform all related Contractor administrative services necessary to perform the work, such as quality control, contractor financial control, and maintenance of accurate and complete records and files. The Contractor shall also be responsible for establishing and executing programs required to ensure that all work is performed in strict accordance with all health, safety and environmental laws, regulations, codes and directives, to protect the general public, as well as Contractor and Government employees.
1.4.2 Licenses and Permits
The Contractor shall be responsible for complying with all state or local contractor licensing or registration laws and permit requirements. The Contractor shall be responsible for furnishing qualified personnel for work which requires specialized registration or training.
1.5 DRAWINGS
1.5.1 Contract Drawings
The contract drawings provided reflect the work to be performed under this contract. In accordance with Section 00 73 00 SPECIAL CONTRACT REQUIREMENTS, DFARS 252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS, the Contractor shall check all drawings immediately upon receipt, and verify the figures, dimensions, and representation of the work. The Contractor shall compare all drawings and verify the figures before laying out the work. Dimensions marked on drawings shall, in general, be followed. Use of scaled measurements shall not be allowed. The Contractor shall promptly notify the Contracting Officer or their designated representative of any discrepancies, and shall be responsible for any errors which might have been avoided by complying with this paragraph. Any omissions from the contract drawings, specifications, or incorrect description of details of the work which are manifestly necessary to carry out the intent of the contract drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or incorrectly described details of work, but shall be performed as if fully and correctly set forth and described in the contract drawings and specifications. Unless otherwise noted, dimensions and elevations, and other features shown on contract drawings are generally based on site surveys and measurements, and As-Built drawings. The Government cannot guarantee the accuracy of the dimensions, elevations, and features shown on the contract drawings which are based on the reference drawings, and it shall be the responsibility of the Contractor to verify all elevations and the dimensions shown by measurements in the field, at no additional cost to the Government.
1.5.2 Reference Drawings
The reference drawings included in the folio of contract drawings show original construction conditions of the original construction and the
SECTION 01 35 00.00 08 Page 5 existing facilities and structures shown on the drawings. To the best knowledge of the Government, the reference drawings reflect the original work incorporated into this project, and do not reflect changes or new work since the date of the drawing. Unless otherwise noted, dimensions and elevations, and other features shown on reference drawings are generally based on As-Built conditions. Where known variations in actual construction occur between that shown on the reference drawings and that existing, it will be noted on the drawings or within the specifications, as practical. The Government cannot guarantee the accuracy of the dimensions, elevations, and features shown on the reference drawings, and it shall be the responsibility of the Contractor to verify all elevations and the dimensions shown by measurements in the field, at no additional cost to the Government. The Contracting Officer or their designated representative shall be notified of any discrepancies prior to commencing work. It is noted that some of the As-Built conditions reflected by the reference drawings have since been modified. Such modifications to the As-Built conditions are described within the sections of these specifications where applicable.
1.5.3 Reference Datum
Note that the reference drawings are based on Legacy vertical datum, and that the contract drawings are based on NAVG88 vertical datum which is approximately 0.45 feet less than that shown on the reference drawings.
1.5.4 Existing Condition Photographs
The existing condition photographs attached to this specification depict features of the site as of July 2016. Photographs are solely for the Contractor's reference and do not indicate any work to be performed under this contract.
1.6 ACCESS
1.6.1 Access to Dam from Water
It is noted that the work required in this contract may require the use of floating plant to access the dam. A staging area with servicing dock has been constructed at the Bush Recreation Area, approximately two miles upstream of the dam. This launching area provides year-round access to the lake. The Contractor may be permitted to moor floating plant to the dam while the pool is below Elevation 940.0 feet (NAVD88). The floating plant shall be temporarily moored at the identified mooring area near the Bush Recreation Area staging facility while the pool is at or above Elevation 940.0 feet. The Contractor may not permanently moor the floating plant at the Bush Recreation Area staging facility. Use of the staging area and service dock facility shall be only during daylight hours, Monday thrrough Friday. The Contractor will not be permitted to use the staging area facility on Saturdays or Sundays or on Federal Holidays.
1.6.2 Launching of Floating Plant
The Contractor shall use the Bush Recreation Area staging facility for launching and assembly of floating plant, ferry barge, and equipment. The staging facility is surrounded by a fence with lockable gates. The gates shall be locked at all times
SECTION 01 35 00.00 08 Page 6
1.6.3 Loading of Construction Materials and Employees
The Contractor will be permitted to use the staging facility for loading of construction materials and employees. Once the floating plant is moored to the dam, the Contractor will be permitted to dock a small watercraft at the floating boat docks along the left bank upstream of the dam to transport employees to the floating plant from the main parking and laydown areas at the dam site. Due to the elevation of the boat dock anchorages, the small watercraft must be removed from the boat dock by the time the pool reaches Elevation 935.0 feet (NAVD88) or higher. The Contractor shall either temporarily moor the watercraft within the mooring area at the Bush Recreation Area staging facility or remove the watercraft from the pool while the pool is at or above Elevation 935.0 feet.
Launching of small watercraft can be completed by using the gravel road near the parking area at the dam site, as shown on the drawings. Note that the launch area is upstream of the floating trash boom, so the small watercraft must pass through the floating trash boom.
1.6.4 Access to Employee Loading Area
The Contractor shall be responsible for providing a safe means of access to the floating boat dock upstream of the dam.
1.6.5 Trash Boom
Access to the dam with marine-based equipment will require disassembly of a portion of the dam trash boom. The Contractor shall be responsible for developing a trash boom disassembly plan for approval. Prior to each disassembly, the Contractor shall remove all debris from against the trash boom for the length of the proposed opening plus a distance of 25 feet from either side of the proposed opening. The plan shall address method of assembly and disassembly. The trash boom shall remain fully-assembled and operational at all times except to permit passage to and from the dam by the Contractor. The trash boom shall be reassembled immediately after each passage. The Contractor shall repair all damage to the floating trash boom resulting from work related to this contract at no additional cost to the Government. The existing trash boom consists of polyethylene encased polystyrene floating segments with steel channel ballast attached to the bottom of the units. Connections between segments utilize stainless steel cotter pins and are designed to be disconnected and moved easily. The floating segments are approximately 10 feet long. The trash boom is "Tuffboom" manufactured by Worthington Products, Canton, OH. The trash boom extends from the left abutment to the right abutment upstream of the dam.
1.7 WORK AREAS AND RESTRICTIONS
1.7.1 Work Areas
As required by Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.236-10 OPERATIONS AND STORAGE AREAS, all operations of the Contractor shall be confined to areas shown on the drawings required to accomplish the work under this contract and as authorized and approved by the Contracting Officer. All work areas shall be coordinated with the Contracting Officer or their designated representative prior to commencement of work. The Contractor shall submit an access plan for Government operating personnel to the Contracting Officer or their designated representative.
The Contractor's use of these areas shall not interfere with the
SECTION 01 35 00.00 08 Page 7
Gover…