W911WN-15-B-0005
W81ET450169815
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Re: Construction of the Charleroi Locks and Dam River Chamber Completion, Monongahela River, PA
This amendment is being issued to: 1) Provide responses to questions received, 2) Revise the Plans and Specifications, as indicated in the Summary of Changes of this amendment, 3) Revise the Price Schedule.4) Change Clauses 52.211-10, 52.211-5001 and Special Contract Requirements 00100-18, 00800-5, 00800-9, and 5) Incorporate the current Wage Determinations, General Decision Number PA150004, dated 07/03/2015 and PA150129, dated 06/19/2015.
The hour and date specified for receipt of bids remains unchanged at 11:00 am on August 3, 2015.
Bidders are requested to submit the conformed Price Schedule of this amendment w ith bids.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 78
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 23-Jul-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911WN-15-B-0005
X 9B. DATED (SEE ITEM 11)
03-Jun-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-Jul-2015
CODE
U.S. ARMY ENGINEER DISTRICT, PITTSBURGH
ATTN CELRP-RC-P
W S MOORHEAD FEDERAL BUILDING
1000 LIBERTY AVENUE ROOM 2203
PITTSBURGH PA 15222-4186
W911WN 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0001
The following specification sections have been revised and are attached to this amendment:
CERTIFIED FINAL VOLUME 1 – TECHNICAL SPECIFICATIONS
01 11 13.00 08 SUMMARY OF WORK - BASE CONTRACT AND AWARDABLE OPTIONS – Revised contract line item numbers, contract periods, and quantities to be paid within tables at end of section.
01 22 00.00 10 MEASUREMENT AND PAYMENT – Various bid item revisions and new bid items.
01 32 33.00 08 DIGITAL PROGRESS IMAGES – Revised to clarify requirements for professional photography.
01 35 00.00 08 SPECIAL PROCEDURES – Revised to clarify offloading responsibilities at the Victory Hollow site and to clarify loading restrictions on the original lock walls.
01 73 19.00 08 GOVERNMENT-FURNISHED PROPERTY– Revised to clarify number of items/pieces for floating mooring bitt anchorage frames, filling system bulkheads, and gate latches.
02 42 00.00 08 DISPOSAL OF MATERIALS – Revised to include hydraulic oil as a disposal item.
02 81 00.00 08 REMOVAL OF REGULATED AND HAZARDOUS WASTES – Revised to remove paragraph for water.
03 05 00.00 08 GOVERNMENT FURNISHED CONCRETE DURING CONTRACT OVERLAP PERIOD
WITH MONOLITHS M-22 TO M-27 CONTRACT – Revised to include Mix 1 for Secant Pile Wall within Awardable Option 2. Also revised to clarify concrete testing procedures/requirements during the overlap period.
03 05 10.00 08 OPERATION AND MAINTENANCE OF CONCRETE BATCH PLANT – Revised concrete production manager terminology.
03 11 13.00 08 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING – Revised requirements for the control tower and shelter concrete sample panels.
03 20 00.00 10 CONCRETE REINFORCING – Revised ASTM reference for zinc-coated bars.
03 30 00.51 08 CONCRETE: MIXTURE PROPORTIONING – Revised to add foundation dental concrete to Table C.
03 31 23.00 08 CONCRETE: DRILLED SHAFTS – Revised CSL testing requirements.
09 97 02 PAINTING: HYDRAULIC STRUCTURES – Editorial revision for paragraph numbering.
22 11 13.00 08 SERVICE WATER SYSTEM – Revised ASTM requirement for stainless steel threaded fittings. Revised pressure test requirements.
22 14 29.00 08 CULVERT, GALLERY AND SUMP DEWATERING SYSTEMS – Revised ASTM requirement for stainless steel threaded fittings. Revised pressure test requirements.
22 61 00.00 08 COMPRESSED AIR PIPING SYSTEMS – Revised ASTM requirement for stainless steel threaded fittings. Revised pressure test requirements.
26 90 00.00 08 CONTROL AND INSTRUMENTATION – Revised to clarify that control consoles are contractor furnished, not government furnished.
31 41 16 METAL SHEET PILING – Revised to include reference for rock compression and permeability data.
31 62 16.16 08 STEEL H-PILES AND KING PILES – Revised by adding a “Summary of Work” paragraph to clarify features of work that the specification section covers. Also revised to include reference for rock compression and permeability data.
31 62 16.23 08 COMBINATION WALL SYSTEM – Revised the “Summary of Work” paragraph to clarify features of work that the specification section covers. Also revised to include reference for rock compression and permeability data.
31 63 26.00 08 DRILLED SHAFTS – Revised to include reference for rock compression and permeability data.
35 01 41.10 08 ELECTRO-HYDRAULIC MITER GATE MACHINERY – Revised requirements for hydraulic actuators.
35 01 41.20 08 ELECTRO-HYDRAULIC VALVE MACHINERY – Revised requirements for hydraulic actuators.
35 20 16.33 MITER GATES – Revised to clarify gate latch device installation and fabrication requirements.
35 20 19.23 08 INSTALLATION OF FILLING AND EMPTYING VALVES AND BULKHEADS –
Revised the existing storage location for the emptying valves.
35 20 23.15 08 LOCK EXCAVATION AND BACKFILL – Revised to remove references to blasting.
35 49 23.23 08 COFFERBOX WALLS - Revised to include reference for rock compression and
CERTIFIED FINAL VOLUME 2 – ATTACHMENTS TO SPECIFICATIONS
31 41 16 METAL SHEET PILING – Added rock unconfined compression strength and rock
The following plans have been revised and are attached to this amendment:
W911WN-15-B-0005 CONTRACT DRAWINGS VOL 1
037-LCH-A0/50-A – General Index, Sheet 1 – Drawing numbers revised to indicate amendment 1.
037-LCH-A0/51-A – General Index, Sheet 2 – Drawing numbers revised to indicate amendment 1.
037-LCH-A0/53-A – General Index, Sheet 4 – Drawing numbers revised to indicate amendment 1.
037-LCH-A0/54-A – General Index, Sheet 5 – Drawing numbers revised to indicate amendment 1.
037-LCH-A0/55-A – General Index, Sheet 6 – Drawing numbers revised to indicate amendment 1.
037-LCH-A0/56-A – General Index, Sheet 7 – Drawing numbers revised to indicate amendment 1.
037-LCH-A0/57-A – General Index, Sheet 8 – Drawing numbers revised to indicate amendment 1.
037-LCH-A0/61-A – Reference Drawing Index, Sheet 4 – Revised to include additional reference drawings.
037-LCH-A4/97-A – Construction Sequence, Sheet 6 – Revised to add construction sequence restrictions.
037-LCH-A4/98-A – Construction Sequence, Sheet 7 – Revised to reflect changes made to drawing 037-
LCH-A4/97-A.
037-LCH-A11/30-A – Contractor Work Limits, Plan – Revised work limits to include the entire River Wall and portions of Upper and Lower Guard Walls.
037-LCH-A11/31-A - Contractor Work Limits, Floating Plant, Plan – Revised work limits to include the area riverward of the upper River Wall where the demonstrations are located.
037-LCH-A19/CB1-A – Middle Wall, Cofferbox, General Notes – Revised notes to clarify cofferbox restrictions.
037-LCH-A19/CB23-A – Middle Wall, Monoliths M-1 thru M-7 Cofferbox, Stage 2 Plan and Elevation – Revised notes and plan view to clarify stage for seal splice connection.
037-LCH-A19/CB24-A - Middle Wall, Monoliths M-1 thru M-7 Cofferbox, Stage 3 and 4 Plans – Revised stage 3 plan view to clarify stage for seal splice connection.
037-LCH-A19/CB25-A - Middle Wall, Monoliths M-11 thru M-16 Cofferbox, Stage 1 Plans – Revised notes to correct drawing reference. Revised plan views to remove king piles shown at future seal splice connections.
037-LCH-A19/CB26-A - Middle Wall, Monoliths M-11 thru M-16 Cofferbox, Stage 2 Plan and Elevation – Revised notes and plan view to clarify stage for seal splice connection.
037-LCH-A19/CB27-A - Middle Wall, Monoliths M-11 thru M-16 Cofferbox, Stage 3 and 4 Plans - Revised stage 3 plan view to clarify stage for seal splice connection.
037-LCH-A19/CB28-A - Middle Wall, Monoliths M-8 thru M-10 Cofferbox, Stage 1 Plans – Revised notes to correct drawing references.
037-LCH-A19/CB31-A - Middle Wall, Monoliths M-17 thru M-21 Cofferbox, Stage 1 Plans – Revised notes to correct drawing references.
037-LCH-A19/CB37-A – Middle Wall, Monolith M-7 Cofferbox, Framing Plan – Added plan callout to clarify stage for seal splice connection.
037-LCH-A19/CB38-A – Middle Wall, Monolith M-11 Cofferbox, Framing Plan – Added plan callout to clarify stage for seal splice connection.
037-LCH-A19/CB39-A – Middle Wall, Monolith M-16 Cofferbox, Framing Plan – Added plan callout to clarify stage for seal splice connection.
037-LCH-A19/CB55-A – Middle Wall, Cofferbox, Typical Details - Sheet 1- Revised to add missing note.
037-LCH-A19/RW1-A – River Wall, Temporary Support of Sheet Pile Monoliths R-8 to R-10 & R-13 to R- 18, Plan – Revised to identify demolition requirements prior to secant pile wall construction.
037-LCH-A19/RW2-A – River Wall, Temporary Support of Sheet Pile Monoliths R-26 to R-28 & R-33 to R- 35, Plan – Revised to identify demolition requirements prior to secant pile wall construction.
W911WN-15-B-0005 CONTRACT DRAWINGS VOL 2
037-LCH-A20/R6-A – River Wall, Monoliths R-33 thru R-35, Plan and Elevation – Revised check post callouts to clarify that check posts shown on monoliths R-33 and R-35 are new (not existing).
037-LCH-A20/CF12-A – Filling and Emptying System, Lock Floor, Sections and Details – Revised note for concrete hatching legend.
W911WN-15-B-0005 CONTRACT DRAWINGS VOL 3
037-LCH-A22/1-A – Gate Operating Machinery, General Arrangement, Plan – Revised cylinder diameter for hydraulic actuator in plan views.
037-LCH-A22/3-A – Gate Operating Machinery, Hydraulic Actuator Assembly, Plan and Sections – Revised cylinder diameter for hydraulic actuator in plan and section views.
037-LCH-A22/6-A – Gate Operating Machinery, Gate Connection Rod Clevis, Details – Revised threading callout.
037-LCH-A22/7-A – Gate Operating Machinery, Hydraulic Actuator Assembly, Details – Revised cylinder diameter for hydraulic actuator in plan and end views. Revised threading callout and notes. Added a note for weld testing requirements.
037-LCH-A22/8-A – Gate Operating Machinery, Hydraulic System, Schematic – Revised schematic and table to remove item 12.
037-LCH-A27/3-A – Piping, Compressed Air/Service Water System, Plan and Schematic – Revised to add expansion joint.
037-LCH-A27/47-A – Equipment Schedule – Added note to clarify piping expansion joint requirements.
037-LCH-A28/3-A – Valve Operating Machinery, Filling Valves Hydraulic Actuator, Plan, Section and Detail - Added a note for weld testing requirements.
037-LCH-A28/4-A – Valve Operating Machinery, Emptying Valves Hydraulic Actuator, Plan and Section – Revised to add callout on cylinder rod threading. Added a note for weld testing requirements.
037-LCH-A29/379-A – Electrical Systems, Cable Schedule, Sheet 4 of 5 – Revised to separate item REVA into two items REVA1 and REVA2.
W911WN-15-B-0005 CONTRACT DRAWINGS VOL 4
037-LCH-A37/19-A – Original River Wall, Demolition, Sections – Added a callout in Section A to clarify sequencing of demolition.
037-LCH-A37/21-A – River Wall, Tremie Removal Limits, Plans – Revised to include additional tremie concrete and sheet pile removal required prior to secant pile wall construction.
037-LCH-A83/15-A – Excavation and Grading, General Plan – Revised to identify excavation within the dewatered cofferdam.
037-LCH-A83/16-A – Excavation and Grading, Detailed Plan-Upstream of Dam – Revised to identify excavation within the dewatered cofferdam.
037-LCH-A83/17-A – Excavation and Grading, Detailed Plan-Downstream of Dam – Revised to identify excavation within the dewatered cofferdam.
037-LCH-A83/18-A – Excavation and Grading, Sections-Sheet 1 of 2 – Revised to identify excavation within the dewatered cofferdam.
037-LCH-A99/14-A – Victory Hollow Bridge, General Plan and Elevation – Revised notes to clarify restrictions for when the bridge repairs can be performed.
037-LCH-A99/16-A – Victory Hollow Bridge, West Abutment Concrete Repairs, Sections – Note added to clarify that all steel reinforcement for repairs shall be zinc-coated.
W911WN-15-B-0005 REFERENCE DRAWINGS VOL 5
037-LCH-99/13z – Added reference drawings R1 and R2.
QUESTIONS AND ANSWERS
Q1. Can the USACE provide an excel file of the bid form for the Charleroi River Chamber Contract?
A1. An Excel file of the bid form has been posted to FBO along with Amendment 0001.
Q2. Ref: Section 00700, 52.219-9, Alternate I. The Alternate allows the Contracting Officer to request a Small Business Subcontracting Plan prior to contract award – which then becomes a part of the resultant contract. What small business utilization goals are we are trying to meet? Are they truly “best effort” type goals or is there a penalty for failure to meet those goals?
A2. Please read the text of FAR Clauses 52.219-8 and 52.219-9 Alt I in their entirety. In an Invitation for Bid (IFB) solicitation, the bidder is expected to comply with both clauses and the U.S. policy of maximizing opportunities for small business in federal contracts. No goals are included in the solicitation. The apparent low bidder (if other than small business) will be requested by the Contracting Officer to submit a Subcontracting Plan tailored to the contract itself. The Plan should be developed with consideration to planned subcontracting and other potential work that could be subcontracted. The proposed Plan should be logical and reasonable, yet challenging, and comply with the FAR clauses. All 11 statutory assurances of clause 52.219- 9(d)(1-11) will need to be included as well as those in 52.219-9(e)(1-6). The plan will be reviewed by the Contracting Officer, the District Deputy for Small Business and the Small Business Administration (SBA) Procurement Center Representative (PCR) for acceptability prior to contract award.
Q3. Ref: Section 00800, 52.211-10. Is the term “current contract completion date” as used throughout this clause the same date (i.e. 1110 calendar days following NTP), or does that date change after each option is awarded? Can you shed clarity on required completion dates under the earliest start and latest start scenario for each option?
A3. The current contract completion date will change after each option is awarded. Extensions will be added to the current completion date at the time the Awardable Option is awarded.
Clause 52.211-10 has been revised with this amendment.
Q4. Ref: Section 00800, 00800-5. We think that the latest date (assuming no change orders) the contractor would be mobilized for this contract is 840 days after 31 March 2021 (or in July 2023). Is this correct? This, of course, does not include the 1 year warranty period.
A4. That is correct. The latest completion date, assuming no changes, would be 840 calendar days after acknowledgement of NTP for the latest Option 5 exercise date of 31 March 2021.
Q5. Plan Sheets A19/CB69 and A19/CB70 provide details for cofferbox seals that include embedded beams, a vertical seal beam, seal concrete, grout sock, and a seal beam plate.
What bid item or items is this work paid under?
A5. Construction of the items listed is to be paid under bid items 0008 and 1007. Removal of the items listed is to be paid under bid items 2021 and 3020.
Q6. What is required from the new contractor with respect to environmental protection requirements during the overlap period when J.B. Fay remains on site for monoliths 22 through 27?
Under 1.3.1 there is a statement that the (new) contractor shall have an approved Environmental Field Technician Compliance Representative (EFTCR) on site at all times that work is in progress including the period that the M22 through M27 contractor is responsible for environmental compliance at the batch plant and Victory Hollow site. This statement makes reference to both the batch plant and Victory Hollow. However, the contract bid items sheet lists bid items 0058 and 1039 which cover environmental costs for the Victory Hollow site only during the base contract and Option 1 respectively. Options 2 through 5 on the bid sheet list environmental compliance items both at the batch plant and at Victory Hollow, as bid items 2004, 2064, 3004, 3058, 4004, 4087, 5004 and 5090. Based on the bid sheet and description of the options, it seems the intent is to have the contractor’s EFTCR monitor activities at Victory Hollow only.
However, at Section 01 11 13.00 08 page 7, there is a listing of contract line items that lists the batch plant site for the base contract and option 1 as follows:
0010 (BASE CONTRACT) ENVIRONMENTAL COMPLIANCE MEASUREMENTS,
SAMPLING, TESTING AND REPORTING, CONCRETE BATCHPLANT 36
MONTHS
1010 (AWARDABLE OPTION ONE) ENVIRONMENTAL COMPLIANCE
MEASUREMENTS, SAMPLING, TESTING AND REPORTING, CONCRETE BATCH
PLANT 24 MONTHS
This adds to the confusion about the contractor’s environmental protection expectations at the batch plant during the contract overlap period. So here are two questions:
a. Is the M1 through M21 contractor to have the EFTCR monitor activities at both the batch plant and Victory Hollow, or only at Victory Hollow during the contract overlap period?
b. Given that the EFTCR is to function under the oversight of the Environmental
Senior Compliance Representative (ESCR) and seek advice of the ESCR, is it correct to assume that the ESCR must be in place and providing oversight throughout the contract overlap period at some level of involvement?
A6. The EFTCR for the Victory Hollow Site is included in the applicable bid items for
ENVIRONMENTAL COMPLIANCE MEASUREMENTS, SAMPLING, TESTING AND
REPORTING, VICTORY HOLLOW SITE and the EFTCR for the batch plant is included in the applicable bid items for ENVIRONMENTAL COMPLIANCE MEASUREMENTS, SAMPLING, TESTING AND REPORTING, CONCRETE BATCH PLANT. A new bid item (ENVIRONMENTAL FIELD TECHNICIAN COMPLIANCE REPRESENTATIVE) has been added to the Base Contract and each Option by Amendment 0001 for the EFTCR responsible for environmental monitoring of the overall construction.
Q7. In Options 2, 3 and Option 4, Bid Items 2049, 3042, 4038, 4039 & 4045-4049 do not have “Produce & Deliver Concrete” Bid Items. Please clarify where the cost for producing & delivering these concrete items are to be included in the bid form.
A7. Based on the Corps construction schedule, for Options 2 and 3, concrete for drilled shafts, tremie concrete, and non-cofferbox sheet pile support system (to be added by Amendment 0001) only may be produced by the M-22 to M-27 contractor, if the options are awarded prior to completion of that contract. In this case only the Deliver and Place Concrete payment items (2037, 2048, 2075 (Am 1), 3030, and 3041) will be used. If Options 2 and 3 are not awarded during the contract period for the M-22 to M-27 contract, this concrete will be produced by the River Chamber Completion (RCC) contractor, and the Produce concrete items (2036, 2047, 2074 (Am1), 3029, and 3040), and associated material items will be used to pay for the contractor-produced concrete. Concrete for Bid Items 2049, 3042, 4038, 4039 & 4045-4049 will be produced by the RCC contractor regardless of time of award of the Options, so these items include production, transportation, and placement. See also section 01 22 00.00 10 MEASUREMENT AND PAYMENT, paragraph Concrete Production, Delivery and Placement as revised by Amendment 0001.
Q8. Drawing A19/CB55 “Typical Upper Waler & Struct Connnection” refers to Note 6;
however, Note 6 does not exist on the drawing. Please clarify.
A8. Drawing A19/CB55 has been revised to include Note 6. The revised drawing is included in Amendment 0001.
Q9. Please confirm that the cost of materials for producing and delivering concrete in the Base Bid & Option 1 from the M22-M27 Monolith Contractor will be borne by the M22- M27 Monolith Contractor.
A9. All batch plant concrete for the Base Contract and Awardable Option 1 will be considered to be Government-furnished, which will include all costs of labor, equipment, and materials to produce the concrete and deliver it to the end of the fixed conveyor at the Stub Wall. The RCC contractor will not be responsible for any cost of labor, equipment or materials for producing this concrete and delivering it to the Stub Wall. This may also apply to batch plant tremie concrete for drilled shafts, tremie concrete, and non-cofferbox sheet pile support system for Awardable Options 2 and 3, depending on the time of award for these options.
Q10. Please provide points of contact for all the concrete materials utilized at the batch plant under the M-22 to M-27 contract.
A10. Specific points of contact are irrelevant as they are likely to change. However, phone numbers for all potential sources are included in the respective tables at the end of specification section 03 30 00.50 08, and materials that have been previously used and approved are annotated with asterisks.
Q11. Please clarify which concrete mix design will be used for BI #4038 Dental Concrete.
A11. The mix design for BI #4038 Dental Concrete is PennDOT Class AAA Ready-mix concrete. Specification Section 03 30 00.51 08, Table C has been revised and included in Amendment 0001.
Q12. Project Solicitation Section 00800: Special Contract Requirements. Clause 52.211-10 lists various scenarios for the start dates and completion dates of the options. There is a very wide range of possible start and completion dates given for each option. For example, if Option 1 is exercised, the contract completion date could be calendar day 1170 (1110 for base contract + 60 for Option 1) or as late as calendar day 1830 (1110 for base contract + 720 days for Option 1). Using this same logic for the other options the earliest completion of the project would be 2400 calendar days from NTP (1110 + 60 + 240 + 30 + 660 + 300) or as late as 4620 calendar days from NTP (1110 + 720 + 660 + 540 + 750 + 840). The difference between the late finish and the early finish is 2220 calendar days or 6.1 years. This wide range of possible start and finish dates creates serious risk for the Contractors and their bonding companies. This risk would include significant material, equipment, and labor escalations, and extended overhead at a minimum. Please consider revising this section to include milestone dates for each option to allow the contractors firm durations to base their bid on.
A12. The completion extension are not cumulative, but are based on either extension by adding a fixed number of days to the contract duration or adding a fixed number of days after the Option Notice to Proceed date. Clause 52.211-10 has been revised with this amendment.
Q13. Specification 26 90 00.00 08, paragraph 2.2.1 states “The control consoles shall be government furnished contractor installed…”
a. These consoles are not listed under any of the sections that state “Government Furnished Equipment”.
b. I am unclear if this is CS1 and CS4 which are titled “Control Console” or if this is Winsted Prestige Consoles as shown on drawing A29/281. Or neither, or both? Nothing on the drawings seems to indicate that any of these are government furnished.
c. There are several sections, for example, 2.2.3.2, that state “the consoles/tables shall each have an illuminated red target “mushroom head” emergency stop button… It is unclear if this item would be included with the government provided console, or if the contractor must retrofit the console with this equipment. This is only one example of equipment to be included with the consoles. There are other sections. Please clarify.
d. If any consoles are government provided, we assume these are being purchased under a separate contract. AIG would be interested in bidding on these consoles. Please consider AIG when this purchase request is issued.
e. If possible, please respond to me immediately and informally regarding these consoles. These components would be a major portion of the System Integration bid if they need to be included, and it would be burdensome to not start working on the bid until after July 7th when the amendment for questions and clarifications is being issued.
A13. The control consoles are not Government furnished and shall be provided by the contractor.
In Spec Section 26 90 00.00 08, 2.2.1 General, the first sentence “The Control Consoles shall be Government furnished Contractor installed to be located as shown on the drawings” has been deleted. This revision is included in Amendment 0001.
Q14. Drawing A19/CB22 Note 11 states that the seal for M-8 will be built inside Monolith M-7; however, the king pile and single sheet shown on other similar details, (see attached Drawing A19/CB25 clouded portion), is missing. Please clarify the seal detail @ M-7.
A14. Drawing A19/CB25 shows Stage 1 of the construction sequence. King piles and sheet piles associated with the seal should not be shown at this stage. Drawing A19/CB25 has been revised and is included in Amendment 0001.
Q15. The Price Schedule only addresses Mobilization and Demobilization as one CLIN under the Base Option. Please consider adding separate Mobilization & Demobilization CLINS for each Option to allow for bringing in new equipment and subcontractors as needed for individual options.
A15. Separate Mobilization & Demobilization CLINS for the Base and each Option have been added. This revision is included in Amendment 0001.
Q16. Please consider adding a CLIN (1 Job) in the base bid and each of the bid options for General Conditions.
A16. A CLIN for General Conditions will not be provided.
Q17. The project duration can extend from anywhere between six and eight years and there are no provisions in the specifications for labor and material escalations. Will the Corps be providing escalation percentages for labor and materials?
A17. No escalation percentages for labor and materials will be provided. This is a business judgment that bidders must make.
Q18. Due to the volume of documents and information to be distributed to the subcontractors and vendors, we request that the cutoff date for clarification requests be extended to July 17th.
A18. There is no extension to the cutoff date for bid questions.
Q19. For a project of this magnitude, very little onsite space is provided for the Contractor’s field offices. Can space at the Batch Plant be used to set up field offices? Can space be made available at the current Government field trailer compound?
A19. There is no available space at the batch plant for contractor offices due in large part to how that area is designed and permitted. There is also no space in the current Right Bank compound.
See note L12 on contract drawing A11/30 for available onsite space provided for a field office.
Q20. Please clarify when the warranty period begins for the base contract and each option, assuming that the options are awarded.
A20. The warranty period begins at substantial completion of the entire contract, which includes substantial completion of the base contract and any of the options that are awarded.
Q21. Due to the size and complexity of this project, we respectfully request a bid date extension of one month.
A21. The time and date specified for receipt of bids is not extended.
Q22. Spec section 015720.00 10 Environmental Protection, paragraph 1.11.6, b. states that the Environmental Field Technician “be onsite whenever the contractor is working”, However the bid items are only related to environmental monitoring at either Victory Hollow or the Batch Plant both of which are turned over to the Contactor at different times. Where are the costs for the full time environmental monitoring of construction to be carried?
A22. See response to question 6.
Q23. Please provide the USACE’s Design Memorandum for the project.
A23. The Design Memorandum will not be provided.
Q24. Please provide driving records, original logs, and all hammer information for previous and current projects constructed at this site.
A24. These records will not be provided. Suitable exploratory drilling and pile driving has already been performed for each new Middle Wall monolith solely for determining piling and casing lengths. See Reference Drawing Volume 6, series 10.
Q25. Please provide the points of contact information for the Geologist and Geotechnical Engineer for the project.
A25. See specification section 01 35 00.00 08, paragraph 1.13.1 for contact information to examine samples taken during previous geologic investigations. Points of contact for specific geologists and/or geotechnical engineers will not be provided. All communication with USACE must go through the Contracting office (POC: Carole Householder) during the solicitation period and through the Construction office (POC: Kirk McWilliams) after the contract is awarded.
Q26. Specification Section 01 73 19.00 08, Page 6 states that 485 sheets of PS 27.5 that are 69 feet long will be furnished while pdf page 280 of Volume 2 attachments (page 20 of the Summary of Locations and Conditions of Charleroi LD GFM) stats that there are 595 sheets of PS 27.5. Please clarify the correct quantity of sheets that will be furnished.
A26. The correct quantity of sheets that will be furnished under this contract is 485 sheets. The original quantity at Victory Hollow was 595 sheets, however, 110 of those sheets have been furnished to the M22 to M27 contractor. Therefore, 485 sheets remain to be government furnished under this contract. This is noted in parentheses on page 20 of the Summary of Locations and Conditions of Charleroi LD GFM.
Q27. Can heavy equipment be placed on the existing middle wall structure?
A27. Materials and equipment are not permitted to be placed on the Original Middle and River Walls. Specification section 01 35 00.00 08, paragraph 1.9.3.1 has been revised to clarify this and is included in Amendment 0001.
Q28. Would the Corps consider adding a lump sum bid item for escalation of labor and materials on the awardable options?
A28. No lump sum bid item for escalation of labor and materials is or will be included on the awardable options.
Q29. Can the Corps provide considerations for addressing escalation of labor, materials and equipment?
A29. No considerations for addressing escalation of labor, materials, and equipment are provided. This is a business judgment that bidders must make.
Q30. The specifications state that mobilization will be paid at 60% at the time of mobilization and 40% at demobilization. Is demobilization considered to be the end of the base bid or at the end of the final option that has been awarded?
A30. See response to question 15.
Q31. When does the warranty period begin on the base bid and previously completed options?
A31. See response to question 20.
Q32. Would the Corps consider a Mobilization / Demobilization for each awardable option?
A32. See response to question 15.
Q33. Can the bid results for the Project M-22 to M-27 be provided to the bidders?
A33. The FedBizOpps (FBO) Notice for the Charleroi Locks, River Chamber Completion, Monoliths M-22 to M-27 – W911WN-14-B-0001 has been temporarily unarchived so that the Bid Abstract for that project can be viewed.
Q34. Can a bid item be added for general conditions in each awardable bid option?
A34. See response to question 16.
Q35. Can the cut-off for bid questions be extended by at least one week?
A35. There is no extension to the cutoff date for bid questions.
Q36. Do the specified sheet pile materials meet the specifications for yield strength?
A36. The Z-sheet piles of the cofferbox shall have a minimum yield strength as per drawing A19/CB1 and Specification Section 31 41 16 Paragraph 2.1. As per Specification Section 31 41 16 Paragraph 2.3, “The Contractor shall submit calculations or test results sealed by a Professional Engineer which demonstrate that the sheet pile, interlocks, and connections to the king pile for the cofferbox can resist a minimum of 3,300 psf differential pressure without exceeding a stress of 50 percent of the yield stress of the steel. Calculations and tests shall be representative of the required pressure, design conditions, and relative stiffness of the sheet pile and king piles.”
The government furnished sheet piling described in specification section 01 73 19.00 08, paragraph 1.5.6, meets the yield strength requirements described in note 5 on contract drawing
A19/CM1.
Q37. Where will the concrete be delivered from the batch plant in relation to the base bid and option 1 work? Will the Corps provide the conveyors required to get the concrete from the batch plant to each work area?
A37. See contract drawing A11/30, note L13. See specification section 03 05 00.00 08 Government Furnished Concrete During Contract Overlap Period with Monoliths M-22 to M-27 Contract. See Concrete Conveyor System sketch (section 01 54 00.00 08) included in Volume 2
- Attachments to the Specifications. Also see specification section 01 35 00.00 08, paragraph 1.7.4, for additional conveyor system information.
Q38. Please provide the window treatment placement schedule.
A38. See contract drawing A70/49, Special Items Schedule which indicates requirement for mini-blinds for control room windows. No window treatment schedule provided.
Q39. 03 30 00.00 08 3.4.1 – Please indicate the quantity of concrete verification cores that must be included in our pricing.
A39. Coring is required for several concrete field demonstrations - see specification section 03 30 00.20 08 for core quantities required for each demonstration. Per specification section 03 30
00.00 08, paragraph 3.4.1, concrete core samples may be required at the discretion of the Contracting Officer. The quantity of additional verification cores beyond what is required under the field demonstration requirements is unknown, as it depends on occurrences and issues that may arise during production work.
Q40. Per Dwgs. A22/15 and A22/16, Latch Device Insert Mark A22/15-1 and Latch Device Mount Mark A22/16-2 are required to be supplied under this contract (3 each per drawings). However, Division 1, Section 017319.0008, paragraph 1.5.10 indicates that two sets of these fabrications are furnished by the government. Note 2 on dwg A22/15 contradicts some of this information. Please confirm: this contract is responsible for installation of these devices for the upper and lower latches on Monolith M-3 (riverside and landside) and the lower latch on Monolith M-23. This contract is responsible for fabrication of 3 sets (A22/15-1 & A22/16-2).
A40. See revised paragraph 3.1.14 within specification section 35 20 16.33 that is included in Amendment 0001.
Q41. Per Dwg A20/M48, please confirm that the installed 6” SS pipe extending into the lower gate latch block out is threaded. Per Note 3 on that drawing, the coupling required for extension of that pipe is GFM. Is the additional pipe required also GFM?
A41. Yes, the pipe will be threaded and the additional pipe will be GFM.
Q42. Please confirm regarding Specification Section 352014.1008, Maintenance Bulkheads that the only embedded metals to be installed in this contract are for the bulkhead slots in Monolith M-1, R-10 and R-33. All other embeds for the bulkhead slots will have been installed in previous contracts.
A42. This statement is correct. The only embedded metals to be installed in this contract are for the bulkhead slots in monoliths M-1, R-10 and R-33. All other embeds for the bulkhead slots (i.e. at monolith M-25) will have been installed in a previous contract.
Q43. Please confirm the total weight of each maintenance bulkhead and the bulkhead lifting beam.
A43. Each maintenance bulkhead unit weighs approximately 62, 460 lbs as shown on reference drawing 037-LCH-34/6.2. Refer to Reference Drawing Volume 4, Section 31 – River Chamber Lock Bulkheads and Lifting Beam Fabrication. The approximate weight of the lifting beam is 22,600 lbs.
Q44. Per Volume 1 of the Technical Specifications, Section 01 22 00.00 10, Specifications Section/Bid Schedule Cross Reference the following specification sections do not have any Pay Item numbers assigned:
· 40 41 13.13 08, Heat Tracing for Piping
· 40 42 13.09 08, Utility Piping Insulation
· 40 95 00, Process Controls
· 44 01 50.10, Water Treatment Units, Operation, Monitoring & Reporting
Please provide information on where to allocate these items on the Bid Form.
A44. Heat Tracing and Piping Insulation are included in the contract prices for the Potable Water Distribution System and Sanitary Sewage Piping Systems as specified in Section 01 22 00.00 10 paragraph Piping Systems. The Specifications Section/Bid Schedule Cross Reference has been revised to clarify this.
A new payment item has been added to the Bid Schedule for Process Controls. Section 01 22
00.00 10 MEASAUREMENT AND PAYMENT and the Specifications Section/Bid Schedule Cross Reference have been revised to address this.
Operating, monitoring & reporting for the water treatment units is included in the applicable
ENVIRONMENTAL COMPLIANCE MEASUREMENTS, SAMPLING, TESTING AND
REPORTING, CONCRETE BATCH PLANT items. Section 01 22 00.00 10 MEASAUREMENT AND PAYMENT and the Specifications Section/Bid Schedule Cross Reference have been revised to clarify this.
All revisions described above are included in Amendment 0001.
Q45. Solicitation Paragraph 00800-4 Railroad Requirement Insurance: The following information is required in order to address the railroad insurance requirements. Calls to Norfork Southern indicate they will not release the information. Please provide:
a. Number of tracks.
b. Speed of trains.
c. Number of passenger train per day.
d. Number of freight trains per day.
e. Flagger rates & requirements.
A45. Information on traffic type, volume, and speed are not readily available to the Corps of Engineers. This information would be subject to change based on railroad business decisions and safety protocol. Refer to specification sections 01 35 00.00 08 SPECIAL PROCEDURES and 01 74 19.10 08 OPERATION OF VICTORY HOLLOW SITE for restrictions related to the rail crossing.
Q46. Given the complex analysis associated with a bidding a project of this size and duration, we respectfully request a 4-week extension to the bid date.
A46. The time and date specified for receipt of bids is not extended.
Q47. Spec section 015720.00 10 Environmental Protection, paragraph 1.11.6, b. states that the Environmental Field Technician “be onsite whenever the contractor is working”, However the bid items are only related to environmental monitoring at either Victory Hollow or the Batch Plant both of which are turned over to the Contactor at different times. Where are the costs for the full time environmental monitoring of construction to be carried?
A47. See response to question 6.
Q48. Bid Item 0069 Bridge Modifications: The technical specifications refer to sheet 037- LCH-99/13 (in the reference drawings) for design loading. Note 6 on 037-LCH-99/13 says “See Reference Drawings R1 and R2 for details of the existing bridge and approach span.”
Looking through the index in the plans, we cannot find where these sheets are located.
Please provide as-built information for the bridge & bridge weight necessary for jacking the bridge.
A48. Reference drawings R1 and R2 will be included in Amendment 0001.
Q49. Specification Section 31.32.16.23.08 Combination Wall System (king & sheet piles) Page 14 Paragraph 3.4.1 Tip Embedments states that the tip elevations for the piles shall be a minimum of 3 feet into rock. Specification Section 31.62.16.16.08 Steel H Piles and King Piles Page 13 Paragraph 3.3.9 Seating Piles states that each pile shall be driven to a minimum of 4 feet into rock and Page 14 Paragraph 3.4.1 Tip Embedments states that the tip elevations shall be a minimum of 4 feet onto rock. Please clarify the tip elevations of the king and sheet piles.
A49. A summary of work has been added to the beginning of specification sections 31 62
16.16.08 and 31 62 16.23 08 that clarifies to what feature(s) the specification section pertains.
These revisions are included in Amendment 0001.
Q50. Ref: Volume 1, Section 03 05 00.00 08, GOVERNMENT FURNISHED CONCRETE
DURING CONTRACT OVERLAP PERIOD WITH MONOLITHS M-22 TO M-27
CONTRACT, Clause 1.6.4.
This clause provides for additional hours of operation for the batch plant that can be requested from the Contracting Officer. Under what circumstances will such requests be approved? Is this just a matter of scheduling ahead of time or are there other criteria to be met?
Once the M-22 to M-27 Contractor has demobilized will we have greater flexibility in scheduling hours of operation of the batch plant?
A50. Circumstances that would permit a request for additional hours of operation at the batch plant pertain to larger tremie placements that, by their quantity, will require more than 8 hours to complete. Placement schedules will be provided one week in advance and coordinated with the other contractor. Once the batch plant is transferred to the River Chamber Completion Contractor (RCCC), the RCCC with have total control over the hours of operation.
Q51. Solicitation, Offer, and Award – Bid Date
a. We request that the bid date of Monday, August 3, 2015 be moved from Monday until a Friday. The complexity of the project requires questions and discussions with vendors and subcontractors regarding their quotes which are made difficult with a bid date immediately after a weekend.
b. We request that the bid date be extended until Friday, August 14, 2015 to allow more time to evaluate the complexity of the project and an award schedule extending over a five year period.
A51. The time and date specified for receipt of bids is not extended.
Q52. Subject: Solicitation Sec 00100-7 Award. The referenced section states that “Award will be made as a whole to on bidder”, but what is the basis for award? Is the award based on the Total Base Contract plus Awardable Options, on the Base Contract, or on some other combination of Base Contract and Awardable Options?
A52. Award will be based on the total Base plus all Awardable Options. Please reference FAR provision 52.217-5 “Evaluation of Options (Jul 1990)” included in Section 00100 of the solicitation. It states, “Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).”
Q53. Subject: 52.228-1 Bid Guarantee and 00100-5 Bid Bond Requirements. These two sections state that the penal sum of the bid bond “… shall be 20% of the bid amount...”
What is the “bid amount”, the Total Base Contract plus Awardable Options or some other value?
A53. The bid amount/price is the total Base contract plus all Awardable Options.
Q54. Subject: Escalation. Due to the long duration of the project (potentially 7.5 years), the uncertainty of the contract amount and details due to the Awardable Options, and the uncertainty of the future award of the Awardable Options, we request that an allowance and method for paying for escalation of materials, fuel, and labor be considered. The pricing of the awardable options, therefore the award of the project, will be heavily weighted on a bidder’s evaluation of the amount and risk of escalation on the cost of performing the work at a date further in the future then is asked of us on any other contract. We feel that the USACE would receive better prices with more competition if the USACE bore the risk of inflation or at least a portion of the inflation above a certain point.
A54. No escalation percentages for labor and materials will be provided. This is a business judgment that bidders must make. To the extent that an underlying concern of this question is the contract's duration, please see the answers to Questions 12, 145, and 151, which address the calculation of the option periods.
Q55. Subject: Pre Excavation – Awardable Options 1 -3. Based on drawing A19/CB1 the pre-dredged surface elevation is 711.00. Based on drawings A83/15-A83/19 the only area to be pre-dredged for the installation of the middle wall is the area for the base contract. It appears as though the area for Options 1-3 were overlooked or were they completed in the current contract that JB Fay has. Please advise.
A55. Pre-excavation downstream of station 2+55A for monolith construction is not required, as the alluvium elevation in this area is currently at approximate EL 711.00 +/-.
Q56. Please provide the USACE quantity calculations for all lump sum items.
A56. Quantity calculations will not be provided.
Q57. In which Bid Item should we include the costs associated with the Non-Cofferbox Sheet Pile Support System (Spec. Section 31 63 41.00 14)?
A57. See bid items 2025 through 2028.
Q58. The quantities for Rock Excavation (Bid Items Nos. 0023, 1019, 2033, 3026), suggest that the proposed rock sockets are over 41 feet deep, which seems excessive. Please confirm the quantities and units for these bid items and indicate where in the bid documents this information is provided. Also, please indicate what criteria we are to use, and how we are to determine adequate depth of rock socket during construction.
A58. The bid item quantities and units are correct. Shaft Final Tip Elevations are provided in the Middle Wall Drilled Shaft Reinforcement Schedule shown on contract drawing A20/D6.
Q59. Specification Section 03.05.00.00.08 Part 1 Paragraph 1 lists the concrete that will be produced and delivered to this contract by the M-22 to M-27 Monolith Contractor. There are similar bid items within this contract. Is it the USACE’s plan to have options awardable to that contract as well as similar bid items, (such as Bid Items 2037, 2047, 3029 and 3040), in this contract? Please clarify.
A59. Due to uncertainties in the schedule overlap, drilled shaft concrete and tremie concrete for Options 2 and 3 are listed as being furnished by the M-22 to M-27 contractor. Therefore, Items 2037, 2048, 3030, and 3041 are included for delivery and placement of the concrete. However, if placement of this tremie concrete and/or drilled shaft concrete occurs after completion of the M-22 to M-27 contract, the River Chamber Completion contractor will be required to also produce the concrete and deliver it to the end of the fixed conveyor. Items 2036, 2047, 3029 and 3040 are included for production of this concrete. This is also addressed in Section 01 22 00.00 10 MEASUREMENT AND PAYMENT, paragraph Concrete Production, Delivery and Placement, subparagraph Payment as revised by Amendment 0001. To the extent that an underlying concern of this question is the contract's duration, please see the answers to Questions 12, 145, and 151, which address the calculation of the option periods.
Q60. Ref: Solicitation. The Contract Documents do not indicate an escalation clause. Does the Government intend to include an escalation clause for materials, fuel, and/or labor given the long duration of this project, relative volatility in commodity prices in recent times, and the variability on award/completion dates for the Options?
A60. No escalation percentages for labor and materials will be provided. This is a business judgment that bidders must make.
Q61.Ref: Solicitation - Form 1442. Does the Government intend to check box 29 on Form 1442?
A61. Yes, the Government will check Box 29 on the SF 1442 at time of award.
Q62. Ref: Clauses 52.211-5001, 52.216-1 and Section 01 22 00.00 10. Clause 52.216-1 indicates the Government contemplates award as a Firm Fixed Price.