01 22 00.00 15.pdf
PDF 26 KB Posted
- Solicitation number
- W911WN09R0009
About this file
Revised Technical Specs for Task Order as stated in Amendment 0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W911WN09D0020.pdf | ||
| W911WN09D0021.pdf | ||
| W911WN09D0019 Task Order 0001.pdf | ||
| W911WN09D0022.pdf | ||
| W911WN09D0019.pdf | ||
| W911WN09R0009 Amendment 0002.doc | DOC document | |
| 01 50 10.pdf | ||
| 01 11 00.pdf | ||
| PROJECT INFORMATION WORKSHEET.doc | DOC document | |
| W911WN09R0009 Amendment 0001.doc | DOC document | |
| Proposal Data Sheet.doc | DOC document | |
| Price Amend1.xls | XLS spreadsheet | |
| W911WN-09-R-0009.zip | ZIP file | |
| Initial Task Order Request.pdf | ||
| W911WN09R0009 Technical Specs for TO.pdf | ||
| W911WN09R0009.pdf | ||
| Technical Specifications.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tionesta Lake, Sewer Improvements
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 15
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 LUMP SUM PAYMENT ITEMS
1.1.1 Erosion and Sediment Control
1.1.1.1 Payment
1.1.1.2 Unit of Measure
1.1.1.3 Payment Item
1.1.2 36" Reinforced Concrete Pipe Culvert
1.1.2.1 Payment
1.1.2.2 Unit of Measure
1.1.2.3 Payment Item
1.1.3 Bituminous Overlay
1.1.3.1 Payment
1.1.3.2 Unit of Measure
1.1.3.3 Payment Item
1.1.4 Concrete Sidewalk
1.1.4.1 Payment
1.1.4.2 Unit of Measure
1.1.4.3 Payment Item
1.1.5 Project Sign
1.1.5.1 Payment
1.1.5.2 Unit of Measure
1.1.5.3 Payment Item
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 Monthly Progress Images
1.2.1.1 Payment
1.2.1.2 Measurement
1.2.1.3 Unit of Measure
1.2.1.4 Payment Item
1.2.2 Sanitary Sewer Line Replacement
1.2.2.1 Payment
1.2.2.2 Measurement
1.2.2.3 Unit of Measure
1.2.2.4 Payment Items
1.2.3 Precast Concrete Manholes
1.2.3.1 Payment
1.2.3.2 Measurement
1.2.3.3 Unit of Measure
1.2.3.4 Payment Items
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00.00 15 Page 1 W81ET4-8343-4006 Revised by Amendment No. 1
-- End of Section Table of Contents --
SECTION 01 22 00.00 15 Page 2
SECTION 01 22 00.00 15
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 LUMP SUM PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 Erosion and Sediment Control
1.1.1.1 Payment
Payment will be made for costs associated with furnishing, installing, maintaining and removing sediment and erosion controls measures as shown on the drawings and as specified in Section 01 57 23.00 10 STORM WATER
POLLUTION PREVENTION MEASURES.
1.1.1.2 Unit of Measure
Unit of measure: lump sum.
1.1.1.3 Payment Item
0001AC Erosion and Sediment Control
1.1.2 36" Reinforced Concrete Pipe Culvert
1.1.2.1 Payment
Payment will be made for costs associated with removal of the existing corrugated metal pipe culvert, furnishing and installing the new reinforced concrete pipe culvert with cast-in-place concrete headwall, removing and reinstalling existing guide rail as required, and restoring pavement. The payment will include clearing and grubbing, excavation, backfilling, endwall, dumped R-5 rock gutter, seeding, disposal of materials, and any other miscellaneous work associated with removal replacement of the culvert.
1.1.2.2 Unit of Measure
Unit of measure: lump sum.
1.1.2.3 Payment Item
0001AD 36" Reinforced Concrete Pipe Culvert and End Walls
SECTION 01 22 00.00 15 Page 3
1.1.3 Bituminous Overlay
1.1.3.1 Payment
Payment will be made for costs associated with preparing the existing pavement and construction the bituminous overlay as shown on the drawings and as specified in Section 32 22 16 BITUMINOUS PAVEMENT CONSTRUCTION. No separate payment will be made for repair of existing bituminous pavement at the culvert replacement and sewer line crossings, and all costs in connection therewith shall be included in the applicable contract price for the item to which the work pertains.
1.1.3.2 Unit of Measure
Unit of measure: lump sum.
1.1.3.3 Payment Item
0002AC Bituminous Overlay
1.1.4 Concrete Sidewalk
1.1.4.1 Payment
Payment will be made for costs associated with constructing the new concrete sidewalk as shown on the drawings and as specified in Section 32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS. The payment shall include removal of the existing sidewalk, constructing the new sidewalk, and restoring the area adjacent to the sidewalk as required.
1.1.4.2 Unit of Measure
Unit of measure: lump sum.
1.1.4.3 Payment Item
0002AD Concrete Sidewalk
1.1.5 Project Sign
1.1.5.1 Payment
Payment will be made for costs associated with furnishing, installing, maintaining and removing project sign as specified in Section 01 50 10
PROJECT SIGNS.
1.1.5.2 Unit of Measure
Unit of measure: lump sum.
1.1.5.3 Payment Item
0002AE Project Sign
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and
SECTION 01 22 00.00 15 Page 4 described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.2.1 Monthly Progress Images
1.2.1.1 Payment
This work is specified in Section 01 32 33 DIGITAL PROGRESS IMAGES.
Payment for this item shall constitute full compensation for all labor, equipment, material and supply costs for furnishing monthly digital progress images, as specified.
1.2.1.2 Measurement
Measurement will be made of the number of sets of photographs taken and delivered to the Contracting Officer as approved or directed by the Contracting Officer or his authorized representative. Each set shall consist of all specified hardcopies and electronic copies for each photographic session as specified in Section 01 32 33 DIGITAL PROGRESS
IMAGES.
1.2.1.3 Unit of Measure
Unit of measure: Set.
1.2.1.4 Payment Item
0001AB DIGITAL PROGRESS IMAGES
1.2.2 Sanitary Sewer Line Replacement
1.2.2.1 Payment
This work is specified in Section 33 30 00 SANITARY SEWERS. Payment will be made for costs associated with removing existing sewer lines and furnishing and installing new pipe, including connections to existing pipes and manholes. Payment shall include all costs of labor, equipment and supplies to complete the work as specified. The payment will include includes excavation, bedding, backfilling, seeding, pavement restoration, concrete for existing manhole drainage sloping, testing, disposal of materials, and all other work associated with replacement of the sewer line. The payment shall also include construction of the new in-line clean out and exploratory excavation at the air vents. If exploratory excavation indicates replacement of the air vents is necessary, payment for replacing the air vents will be made in accordance with Contract Clause "Changes".
1.2.2.2 Measurement
Sanitary sewer lines will be measured for payment by the linear foot of new pipe installed. Measurement will be made along the centerline of each pipe.
1.2.2.3 Unit of Measure
Unit of measure: Linear foot
SECTION 01 22 00.00 15 Page 5
1.2.2.4 Payment Items
0001AE 6" SDR35 PVC Sewer Line, Office Area 0002AA 6" SDR35 PVC Sewer Line, Campground Area
1.2.3 Precast Concrete Manholes
1.2.3.1 Payment
This work is specified in Section 33 30 00 SANITARY SEWERS. Payment will be made for costs associated with furnishing and installing new precast concrete manholes. Payment shall include all costs of labor, equipment and supplies to complete the work as specified. The payment will include includes excavation, bedding, backfilling, seeding, pavement restoration, frames and covers, testing, disposal of materials, and all other work associated with construction of the manholes.
1.2.3.2 Measurement
Manholes will be measured for payment by the number of manholes acceptably installed.
1.2.3.3 Unit of Measure
Unit of measure: Each
1.2.3.4 Payment Items
0002AB 4' Diameter Precast Concrete Manholes
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
SECTION 01 22 00.00 15 Page 6
| 01 22 00.00 15 - MEASUREMENT AND PAYMENT |
| 01 22 00.00 15 - MEASUREMENT AND PAYMENT |
| PART 1 GENERAL |
| 1.1 LUMP SUM PAYMENT ITEMS |
| 1.1.1 Erosion and Sediment Control |
| 1.1.1.1 Payment |
| 1.1.1.2 Unit of Measure |
| 1.1.1.3 Payment Item |
| 1.1.2 36" Reinforced Concrete Pipe Culvert |
| 1.1.2.1 Payment |
| 1.1.2.2 Unit of Measure |
| 1.1.2.3 Payment Item |
| 1.1.3 Bituminous Overlay |
| 1.1.3.1 Payment |
| 1.1.3.2 Unit of Measure |
| 1.1.3.3 Payment Item |
| 1.1.4 Concrete Sidewalk |
| 1.1.4.1 Payment |
| 1.1.4.2 Unit of Measure |
| 1.1.4.3 Payment Item |
| 1.1.5 Project Sign |
| 1.1.5.1 Payment |
| 1.1.5.2 Unit of Measure |
| 1.1.5.3 Payment Item |
| 1.2 UNIT PRICE PAYMENT ITEMS |
| 1.2.1 Monthly Progress Images |
| 1.2.1.1 Payment |
| 1.2.1.2 Measurement |
| 1.2.1.3 Unit of Measure |
| 1.2.1.4 Payment Item |
| 1.2.2 Sanitary Sewer Line Replacement |
| 1.2.2.1 Payment |
| 1.2.2.2 Measurement |
| 1.2.2.3 Unit of Measure |
| 1.2.2.4 Payment Items |
| 1.2.3 Precast Concrete Manholes |
| 1.2.3.1 Payment |
| 1.2.3.2 Measurement |
| 1.2.3.3 Unit of Measure |
| 1.2.3.4 Payment Items |
| PART 2 PRODUCTS Not Applicable |
| PART 3 EXECUTION Not Applicable |
File details come from the government source that posted it. Updated .