Incumbent.pdf
PDF 51 KB Posted
- Attached to
- Facility Support Services, Shenango Lake Hermitage PA Federal contract opportunity
- Solicitation number
- W911WN08R0014
About this file
Incumbent contractor information
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W911WN08R0014-0003.pdf | ||
| W911WN08R0014-0002.pdf | ||
| 08R00140001.pdf | ||
| W911WN-08-R-0014 Shenango.pdf | ||
| Shenango Atch Exhibits.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED.
U.S. ARMY ENGINEER DISTRICT, PITTSBURGH
CONTRACTING DIVISION (ROOM 727)
W S MOORHEAD FEDERAL BUILDING
1000 LIBERTY AVENUE
PITTSBURGH PA 15222-4186
DELANEY LAWN MAINTENANCE
KENN DELANEY
8323 WILLIAMSON ROAD
MEADVILLE PA 16335
UNDER DPAS (15 CFR 700)
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
CODE 10. THIS ACQUISITION IS 11. DELIVERY FOR FOB
UNRESTRICTED
FAX: RFQ
X SET ASIDE: % FOR100
SEE SCHEDULE
SIC: 8744TEL: 14. METHOD OF SOLICITATION
IFB RFP
CODE 18a. PAYMENT WILL BE MADE BY CODEOFFEROR
SUCH ADDRESS IN OFFER
FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL SHEETS SUBJECT
30a. SIGNATURE OF OFFEROR/CONTRACTOR
TO THE TERMS AND CONDITIONS SPECIFIED HEREIN.
31a.UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30c. DATE SIGNED (TYPE OR PRINT)
33. SHIP NUMBER32a. QUANTITY IN COLUMN 21 HAS BEEN
PARTIAL FINAL
32c. DATE 36. PAYMENT
41c. DATE
42c. DATE REC'D (YY/MM/DD)
AUTHORIZED FOR LOCAL REPRODUCTION
41b. SIGNATURE AND TITLE OF
CERTIFYING OFFICER
32b. SIGNATURE OF AUTHORIZED GOVT.
REPRESENTATIVE
30b. NAME AND TITLE OF SIGNER
(TYPE OR PRINT)
SEE ADDENDUM
BLOCK IS MARKED
DESTINATION UNLESS
34. VOUCHER NUMBER 35. AMOUNT VERIFIED
CORRECT FOR
37. CHECK NUMBER
42d. TOTAL CONTAINERS
STANDARD FORM 1449 (10-95)
Prescribed by GSA
FAR (48 CFR) 53.212
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
12. DISCOUNT TERMS
1F1C9
TEL. 814-337-2868
W911WN
412-395-7465 412-644-5109
CEFC-AO-P
(No Collect Calls)
SIZE STANDARD: $23 Million
9. ISSUED BY
FACILITY
CODE
ADDENDA
ADDENDA
ARE
ARE
ARE NOT ATTACHED
ARE NOT ATTACHED
13b. RATING
17a.CONTRACTOR/
USAED PITTSBURGH DISTRICT
5720 INTEGRITY DRIVE
MILLINGTON TN 38054-5005
13a. THIS CONTRACT IS A RATED ORDER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
31b. NAME OF CONTRACTING OFFICER
EMAIL:pamela.broglio@usace.army.mil412-395-7464TEL:
31c. DATE SIGNED
19-Sep-2003
PAMELA D BROGLIO / CONTRACTING OFFICER
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER ALL ITEMS SET
0 COPIES
X
8(A)
SMALL DISADV. BUSINESS
SMALL BUSINESS
X
15. DELIVER TO CODE 16. ADMINISTERED BY CODE
SEE SCHEDULE SEE ITEM 9
X
19. ITEM NO. 20. SCHEDULE OF SUPPLIES/ SERVICES 21. QUANTITY 22. UNIT 23. UNIT PRICE 24. AMOUNT
See Schedule
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT
$1,331,223.21
SEE SCHEDULE
29. AWARD OF CONTRACT: REFERENCE
X OFFER DATED 06-Aug-2003 . YOUR OFFER ON SOLICITATION Written
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS: SEE SCHEDULE
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE
CONTRACT, EXCEPT AS NOTED
DACW59-03-D-0012-P00010 19-Sep-2003 DACW59-03-B-0005 08-Jul-2003
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
RONALD S MAZZEI
b. TELEPHONE NUMBER
412-395-7475
8. OFFER DUE DATE/LOCAL TIME
11:00 AM 07 Aug 2003
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
42b. RECEIVED AT (Location)
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
42a. RECEIVED BY (Print)
COMPLETE PARTIAL FINAL
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
W81ET470872857
1. REQUISITION NUMBER
W911WN-08-R-0014-0001, ATTACHMENT 1 PAGE 1 OF 16
W911WN-08-R-0014-0001
The following are the contract line items from years 3 and 4 only.
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
3001 23 Each $1,986.14 $45,681.22
MOWING SERVICES, TYPE I
FFP
SHENANGO RECREATION AREA - SITE 1(A)
FOB: Destination
UNIT UNIT PRICE ESTIMATED AMOUNT
3002 23 Each $596.31 $13,715.13
MOWING SERVICES, TYPE I
FFP
SHENANGO RECREATION AREA - SITE 1 (B)
UNIT UNIT PRICE ESTIMATED AMOUNT
3003 23 Each $427.79 $9,839.17
MOWING SERVICES, TYPE I
FFP
CLARK RECREATION AREA - SITE 1 (C)
UNIT UNIT PRICE ESTIMATED AMOUNT
3004 23 Each $152.79 $3,514.17
MOWING SERVICES, TYPE I
FFP
COMPLEX & DAM AREA - SITE 2 (A)
UNIT UNIT PRICE ESTIMATED AMOUNT
3005 23 Each $81.95 $1,884.85
MOWING SERVICES, TYPE I
FFP
MANAGER'S OFFICE - SITE 2 (B)
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
3006 23 Each $735.57 $16,918.11
MOWING SERVICES, TYPE I
FFP
MAHANEY DAY USE - SITE 2 (C)
UNIT UNIT PRICE ESTIMATED AMOUNT
3007 10 Each $213.90 $2,139.00
MOWING SERVICES, TYPE II
FFP
MAHANEY OPEN AREAS AND FENCLINE - SITE 2 (D)
UNIT UNIT PRICE ESTIMATED AMOUNT
3008 10 Each $104.63 $1,046.30
MOWING SERVICES, TYPE II
FFP
LEFT ABUTMENT OF DAM - SITE 2 (E)
UNIT UNIT PRICE ESTIMATED AMOUNT
3009 2 Each $475.47 $950.94
MOWING SERVICES, TYPE II
FFP
ROAD SHOULDERS
UNIT UNIT PRICE ESTIMATED AMOUNT
3010 25 Acre $12.32 $308.00
REMOVAL OF GRASS CLIPPINGS
FFP
UNIT UNIT PRICE ESTIMATED AMOUNT
3011 1 Each $63.90 $63.90
PESTICIDE APPLICATION
FFP
DAM AND MAHANEY RECREATION - SITE 1
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
3012 1 Each $1,146.31 $1,146.31
PESTICIDE APPLICATION
FFP
SHENANGO RECREATION AREA - SITE 3
UNIT UNIT PRICE ESTIMATED AMOUNT
3013 1 Each $837.05 $837.05
PESTICIDE APPLICATION
FFP
OUTLYING PARKING LOTS/ACCESS AREAS - SITE 4
UNIT UNIT PRICE ESTIMATED AMOUNT
3014 1 Each $432.42 $432.42
PESTICIDE APPLICATION
FFP
DAM SITE - SITE 5
UNIT UNIT PRICE ESTIMATED AMOUNT
3015 10,000 Square Foot
$0.08 $800.00
PESTICIDE APPLICATION
FFP
POISON IVY CONTROL - MISCELLANEOUS SITES
UNIT UNIT PRICE ESTIMATED AMOUNT
3016 6,000 Square Foot
$0.08 $480.00
PESTICIDE APPLICATION
FFP
MISCELLANEOUS SITES
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
3017 1 Each $605.57 $605.57
LEAF REMOVAL
FFP
COMPLEX - SITE 1
UNIT UNIT PRICE ESTIMATED AMOUNT
3018 1 Each $856.75 $856.75
LEAF REMOVAL
FFP
DAM OVERLOOK - SITE 2
UNIT UNIT PRICE ESTIMATED AMOUNT
3019 1 Each $402.79 $402.79
LEAF REMOVAL
FFP
CLARK RECREATION AREA - SITE 3
UNIT UNIT PRICE ESTIMATED AMOUNT
3020 1 Each $942.62 $942.62
LEAF REMOVAL
FFP
SHENANGO RECREATION AREA - SITE 4
UNIT UNIT PRICE ESTIMATED AMOUNT
3021 1,230 Each $19.80 $24,354.00
RESTROOM/LOCKER ROOM/WASHHOUSE CLEANING
FFP
(COMFORT STATIONS WITHOUT SHOWERS)
UNIT UNIT PRICE ESTIMATED AMOUNT
3022 650 Each $25.70 $16,705.00
RESTROOM/LOCKER ROOM/WASHHOUSE CLEANING
FFP
(COMFORT STATIONS WITH SHOWERS)
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
3023 60 Each $37.70 $2,262.00
PROJECT OFFICES CLEANING
FFP
RANGER STATION
UNIT UNIT PRICE ESTIMATED AMOUNT
3024 60 Each $27.70 $1,662.00
PROJECT OFFICES CLEANING
FFP
MANAGER'S OFFICE
UNIT UNIT PRICE ESTIMATED AMOUNT
3025 30 Each $18.80 $564.00
PROJECT OFFICES CLEANING
FFP
CONFERENCE ROOM
UNIT UNIT PRICE ESTIMATED AMOUNT
3026 30 Each $26.80 $804.00
PROJECT OFFICES CLEANING
FFP
DISPLAY ROOM
UNIT UNIT PRICE ESTIMATED AMOUNT
3027 Each $0.00 $0.00
THIS LINE ITEM - NOT USED
UNIT UNIT PRICE ESTIMATED AMOUNT
3028 Each $0.00 $0.00
THIS LINE ITEM - NOT USED
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
3029 12 Each $314.39 $3,772.68
SHAMPOOING/STEAM CLEANING OF
FFP
CARPETED FLOORS
UNIT UNIT PRICE ESTIMATED AMOUNT
3030 12 Each $109.00 $1,308.00
WAXING OF UNCARPETED FLOORS
UNIT UNIT PRICE ESTIMATED AMOUNT
3031 1,500 Each $13.13 $19,695.00
SOLID WASTE REMOVAL
UNIT UNIT PRICE ESTIMATED AMOUNT
3032 12 Each $13.13 $157.56
ADDITIONAL SOLID WASTE REMOVAL
UNIT UNIT PRICE ESTIMATED AMOUNT
3033 12,000 Gallon $0.36 $4,320.00
RAW SEWAGE
UNIT UNIT PRICE ESTIMATED AMOUNT
3034 24,000 Gallon $0.36 $8,640.00
SLUDGE FROM SEWAGE TREATMENT PLANT
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
3035 3,300 Hours $23.69 $78,177.00
PARK ATTENDANT
UNIT UNIT PRICE ESTIMATED AMOUNT
3036 20 Acre $161.57 $3,231.40
CLEARING FOR FOOD PLOTS
UNIT UNIT PRICE ESTIMATED AMOUNT
3037 35 Acre $34.27 $1,199.45
PLOWING
UNIT UNIT PRICE ESTIMATED AMOUNT
3038 35 Acre $34.27 $1,199.45
DISCING
UNIT UNIT PRICE ESTIMATED AMOUNT
3039 35 Acre $49.26 $1,724.10
FERTILIZING
UNIT UNIT PRICE ESTIMATED AMOUNT
3040 30 Acre $84.26 $2,527.80
LIMING
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
3041 35 Acre $29.62 $1,036.70
SEEDING
UNIT UNIT PRICE ESTIMATED AMOUNT
3042 30 Acre $29.62 $888.60
MOWING HERBACEOUS VEGETATION
UNIT UNIT PRICE ESTIMATED AMOUNT
3043 1 Lump Sum
$1,087.23 $1,087.23
WAGE INCREASE-TASK ORDERS 0029-0034
FFP
FOB: Destination
MILSTRIP: W81ET470872857
PURCHASE REQUEST NUMBER: W81ET470872857
UNIT UNIT PRICE ESTIMATED AMOUNT
4001 23 Each $2,046.57 $47,071.11
EXERCISED
OPTION
MOWING SERVICES, TYPE I
FFP
SHENANGO RECREATION AREA - SITE 1(A)
UNIT UNIT PRICE ESTIMATED AMOUNT
4002 23 Each $621.49 $14,294.27
EXERCISED
OPTION
MOWING SERVICES, TYPE I
FFP
SHENANGO RECREATION AREA - SITE 1 (B)
UNIT UNIT PRICE ESTIMATED AMOUNT
4003 23 Each $442.90 $10,186.70
EXERCISED
OPTION
MOWING SERVICES, TYPE I
FFP
CLARK RECREATION AREA - SITE 1 (C)
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
4004 23 Each $167.90 $3,861.70
EXERCISED
OPTION
MOWING SERVICES, TYPE I
FFP
COMPLEX & DAM AREA - SITE 2 (A)
UNIT UNIT PRICE ESTIMATED AMOUNT
4005 23 Each $85.73 $1,971.79
EXERCISED
OPTION
MOWING SERVICES, TYPE I
FFP
MANAGER'S OFFICE - SITE 2 (B)
UNIT UNIT PRICE ESTIMATED AMOUNT
4006 23 Each $765.79 $17,613.17
EXERCISED
OPTION
MOWING SERVICES, TYPE I
FFP
MAHANEY DAY USE - SITE 2 (C)
UNIT UNIT PRICE ESTIMATED AMOUNT
4007 10 Each $221.45 $2,214.50
EXERCISED
OPTION
MOWING SERVICES, TYPE II
FFP
MAHANEY OPEN AREAS AND FENCLINE - SITE 2 (D)
UNIT UNIT PRICE ESTIMATED AMOUNT
4008 10 Each $107.15 $1,071.50
EXERCISED
OPTION
MOWING SERVICES, TYPE II
FFP
LEFT ABUTMENT OF DAM - SITE 2 (E)
UNIT UNIT PRICE ESTIMATED AMOUNT
4009 2 Each $489.32 $978.64
EXERCISED
OPTION
MOWING SERVICES, TYPE II
FFP
ROAD SHOULDERS
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
4010 25 Acre $13.58 $339.50
EXERCISED
OPTION
REMOVAL OF GRASS CLIPPINGS
UNIT UNIT PRICE ESTIMATED AMOUNT
4011 1 Each $71.45 $71.45
EXERCISED
OPTION
PESTICIDE APPLICATION
FFP
DAM AND MAHANEY RECREATION - SITE 1
UNIT UNIT PRICE ESTIMATED AMOUNT
4012 1 Each $1,171.49 $1,171.49
EXERCISED
OPTION
PESTICIDE APPLICATION
FFP
SHENANGO RECREATION AREA - SITE 3
UNIT UNIT PRICE ESTIMATED AMOUNT
4013 1 Each $857.19 $857.19
EXERCISED
OPTION
PESTICIDE APPLICATION
FFP
OUTLYING PARKING LOTS/ACCESS AREAS - SITE 4
UNIT UNIT PRICE ESTIMATED AMOUNT
4014 1 Each $450.05 $450.05
EXERCISED
OPTION
PESTICIDE APPLICATION
FFP
DAM SITE - SITE 5
UNIT UNIT PRICE ESTIMATED AMOUNT
4015 10,000 Square Foot
$0.11 $1,100.00
EXERCISED
OPTION
PESTICIDE APPLICATION
FFP
POISON IVY CONTROL - MISCELLANEOUS SITES
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
4016 6,000 Square Foot
$0.11 $660.00
EXERCISED
OPTION
PESTICIDE APPLICATION
FFP
MISCELLANEOUS SITES
UNIT UNIT PRICE ESTIMATED AMOUNT
4017 1 Each $635.79 $635.79
EXERCISED
OPTION
LEAF REMOVAL
FFP
COMPLEX - SITE 1
UNIT UNIT PRICE ESTIMATED AMOUNT
4018 1 Each $947.40 $947.40
EXERCISED
OPTION
LEAF REMOVAL
FFP
DAM OVERLOOK - SITE 2
UNIT UNIT PRICE ESTIMATED AMOUNT
4019 1 Each $417.90 $417.90
EXERCISED
OPTION
LEAF REMOVAL
FFP
CLARK RECREATION AREA - SITE 3
UNIT UNIT PRICE ESTIMATED AMOUNT
4020 1 Each $992.98 $992.98
EXERCISED
OPTION
LEAF REMOVAL
FFP
SHENANGO RECREATION AREA - SITE 4
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
4021 1,230 Each $19.99 $24,587.70
EXERCISED
OPTION
RESTROOM/LOCKER ROOM/WASHHOUSE CLEANING
FFP
(COMFORT STATIONS WITHOUT SHOWERS)
UNIT UNIT PRICE ESTIMATED AMOUNT
4022 650 Each $25.99 $16,893.50
EXERCISED
OPTION
RESTROOM/LOCKER ROOM/WASHHOUSE CLEANING
FFP
(COMFORT STATIONS WITH SHOWERS)
UNIT UNIT PRICE ESTIMATED AMOUNT
4023 60 Each $37.99 $2,279.40
EXERCISED
OPTION
PROJECT OFFICES CLEANING
FFP
RANGER STATION
UNIT UNIT PRICE ESTIMATED AMOUNT
4024 60 Each $27.99 $1,679.40
EXERCISED
OPTION
PROJECT OFFICES CLEANING
FFP
MANAGER'S OFFICE
UNIT UNIT PRICE ESTIMATED AMOUNT
4025 30 Each $18.99 $569.70
EXERCISED
OPTION
PROJECT OFFICES CLEANING
FFP
CONFERENCE ROOM
UNIT UNIT PRICE ESTIMATED AMOUNT
4026 30 Each $26.99 $809.70
EXERCISED
OPTION
PROJECT OFFICES CLEANING
FFP
DISPLAY ROOM
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
4027 Each $0.00 $0.00
EXERCISED
OPTION
THIS LINE ITEM - NOT USED
UNIT UNIT PRICE ESTIMATED AMOUNT
4028 Each $0.00 $0.00
EXERCISED
OPTION
THIS LINE ITEM - NOT USED
UNIT UNIT PRICE ESTIMATED AMOUNT
4029 12 Each $315.93 $3,791.16
EXERCISED
OPTION
SHAMPOOING/STEAM CLEANING OF
FFP
CARPETED FLOORS
UNIT UNIT PRICE ESTIMATED AMOUNT
4030 12 Each $109.96 $1,319.52
EXERCISED
OPTION
WAXING OF UNCARPETED FLOORS
UNIT UNIT PRICE ESTIMATED AMOUNT
4031 1,500 Each $13.32 $19,980.00
EXERCISED
OPTION
SOLID WASTE REMOVAL
UNIT UNIT PRICE ESTIMATED AMOUNT
4032 12 Each $13.32 $159.84
EXERCISED
OPTION
ADDITIONAL SOLID WASTE REMOVAL
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
4033 12,000 Gallon $0.55 $6,600.00
EXERCISED
OPTION
RAW SEWAGE
UNIT UNIT PRICE ESTIMATED AMOUNT
4034 24,000 Gallon $0.55 $13,200.00
EXERCISED
OPTION
SLUDGE FROM SEWAGE TREATMENT PLANT
UNIT UNIT PRICE ESTIMATED AMOUNT
4035 3,300 Hours $24.24 $79,992.00
EXERCISED
OPTION
PARK ATTENDANT
UNIT UNIT PRICE ESTIMATED AMOUNT
4036 20 Acre $167.87 $3,357.40
EXERCISED
OPTION
CLEARING FOR FOOD PLOTS
UNIT UNIT PRICE ESTIMATED AMOUNT
4037 35 Acre $39.31 $1,375.85
EXERCISED
OPTION
PLOWING
UNIT UNIT PRICE ESTIMATED AMOUNT
4038 35 Acre $39.31 $1,375.85
EXERCISED
OPTION
DISCING
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
4039 35 Acre $54.30 $1,900.50
EXERCISED
OPTION
FERTILIZING
UNIT UNIT PRICE ESTIMATED AMOUNT
4040 30 Acre $89.30 $2,679.00
EXERCISED
OPTION
LIMING
UNIT UNIT PRICE ESTIMATED AMOUNT
4041 35 Acre $32.14 $1,124.90
EXERCISED
OPTION
SEEDING
UNIT UNIT PRICE ESTIMATED AMOUNT
4042 30 Acre $32.14 $964.20
EXERCISED
OPTION
MOWING HERBACEOUS VEGETATION
File details come from the government source that posted it. Updated .