RFI Questions and Answers W911SG26BA005.pdf
PDF 127 KB Posted
- Attached to
- Replace Repair Roof Bldg. 2414
- Solicitation number
- W911SG26BA005
About this file
This is a Request for Information (RFI) Questions and Answers document for federal contract W911SG26BA005, concerning roof replacement and repair work on Building 2414 at Fort Bliss.
The document addresses eight questions from prospective contractors regarding project scope, site access, and technical specifications. Key clarifications include: core samples for roof composition analysis must be obtained by the contractor as part of their bid; drone authorization requires FAA registration and approval from both Fort Bliss and El Paso International Airport, with processing taking one to three weeks; additional site visits require 48-hour advance coordination with the Contracting Officer Representative and the Contract Specialist, with contractors responsible for providing their own equipment such as ladders; the laundry wall box and center drain represent a removal and replacement of existing equipment with contractor-provided materials; fire alarm strobe light deficiencies existing prior to construction are not the contractor's responsibility, though any damage caused during construction must be replaced by the contractor; roof component dimensions are specified as 5-inch minimum drip edge, 6-inch minimum gutter and downspout sizes, with gravel stop not required; submission tabs F, G, and H should be emailed to shawn.t.munro.mil@army.mil by bid opening time but need not be included in the physical sealed bid package; and the R-38 insulation requirement is specified as overall rather than average. The document serves to provide prospective bidders with clarifications necessary for accurate estimate preparation.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI QUESTIONS AND ANSWERS
W911SG26BA005
Replace Repair Roof Bldg. 2414
1.) Have core samples been taken? If so, are pictures available?
ANSWER: No, core samples have not been taken. Refer to Statement of Work secƟon 1.4.6.1.9.
which reads, “Contractor to include the cost of roof cores to determine the exisƟng system composiƟon and thickness.”
2.) Is flying a drone permiƩed?
ANSWER: The process for obtaining drone authorizaƟon can take between 1 and 3 weeks.
Requestor shall create an account, register with FAA at FAADroneZone, hƩps://faadronezone-access.faa.gov/#/, provide a FAA Part 107 CerƟficaƟon and request airspace authorizaƟon. Both
Fort Bliss and El Paso InternaƟonal are required to review and approve this request.
3.) Can a second site visit be performed to get on the lower roof secƟons using exterior extended ladder? No interior roof hatch access required.
ANSWER: AddiƟonal Site Visits need to be coordinated with the COR via the Contract Specialist with a 48 hour noƟce. Ladders are not provided by the Government.
4.) 313 Laundry: Statement of Work Item 1.4.6.2.6 states to provide “new washing machine wall box with center drain”. Is there an exisƟng wall box and center drain that we are replacing or installing new?
ANSWER: Yes, there is an exisƟng wall box. This is a removal of the exisƟng and installaƟon of new wall box (Contractor provided).
5.) Fire Alarm System Strobe Lights: Some of the strobe lights are missing and others may not be funcƟonal. Factor new strobe lights for missing strobe lights in the bid or factor addressing as a future change order?
ANSWER: Once the project is Awarded and prior to construcƟon, the fire alarm system shall be tested in the presence of Fort Bliss Fire and the COR to confirm that the system is operaƟonal and idenƟfy any missing or non-funcƟoning devices. Contractor is not responsible for any devices that are missing or non-funcƟonal prior to construcƟon. Any devices that are damaged during construcƟon shall be replaced by the Contractor.
6.) To complete our esƟmate accurately, please provide the following dimensions:
Drip edge size: 5-inch min, confirm size with manufacturer for use with 6-inch guƩer.
GuƩer size: 6-inch minimum.
Downspout size: 6-inch minimum.
Gravel stop size: Not required for this project.
These dimensions cannot be determined from the contract drawings because the applicable details are not drawn to scale. Providing this informaƟon will allow us to obtain accurate material pricing and prepare a complete esƟmate.
ANSWER: See answers in red.
7.) Tabs F, G & H are staƟng to submit Email. Can you please clarify what email address we need to send this informaƟon and if we need to also include it in our bid package?
ANSWER: Tabs F, G, & H can be emailed to shawn.t.munro.mil@army.mil. In an effort to reduce waste, these tabs do not need to be included in the physical sealed bid. The referenced tabs do need to be emailed by the date and Ɵme of bid opening though.
8.) Is the R-38 average or overall?
ANSWER: Overall.