Responses_to_Questions_Page_4.xlsx
XLSX spreadsheet 21 KB Posted
- Solicitation number
- W911SF19R0009
About this file
Page 4
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_01_Solicitation_W911SF19R0009.pdf | ||
| Responses_to_Questions_Page_5.xlsx | XLSX spreadsheet | |
| Responses_to_Questions_Page_3.xlsx | XLSX spreadsheet | |
| Past_Performance_Questionnaire.doc | DOC document | |
| DD_Form_254.pdf | ||
| Page_2_Industry_Question_and_Answer_Solicitation_W911SF19R0009.docx | DOCX document | |
| Page_1_RESPONSES_TO_INDUSTRY_QUESTIONS.docx | DOCX document | |
| W911SF-19-R-0009_Q&A.pdf | ||
| SF33_.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| TRADOC Capability Manager - Armored Brigade Combat Team (TCM ABCT) - Solicitation #: W911SF-19-R-0009 | |||||
| Question / Clarification / Suggestion | Category | Citation | Comment / Question | ||
| General | |||||
| Question | Can the government provide us with the current contract name and contract number? In addition can you provide what the current contract price was at award? Has there been any additional funds added to the current contract? | Not during the solicitation phase | |||
| Section B | |||||
| Clarify | Section B CLIN 0002 Travel, Page 2 | Travel FFP | The CLIN indicates that it is a FFP CLIN but usually travel is a cost reimbursable CLIN. Request clarification? | Travel and Supply are cost CLINs | |
| Suggestion | Section B, CLIN 0002 Travel and PWS 1.6.12, Page 7 | Need basis for calculating travel cost. | Would the government consider providing a travel "plug" in order to compare apples to apples or provide the data necessary to calculate travel costs? | Yes see answer above | |
| Clarify | Section B, CLIN 0003, 10003, 20003 | The solicitation calls for Supplies under a FFP CLIN. Would the government consider providing a plug number? | Yes see answer above | ||
| PWS | |||||
| Question | PWS 1.6.13, Page 41 | Other Direct Costs. The contractor shall provide personal protective equipment for each contract employee within 60 days of start of work. All personnel must become familiar with and wear the protective clothing items according to technical manuals, operating environments, and per manufacturer. Mandatory items include safety helmets, safety boots, safety eyewear, hearing protection, work gloves, and protective over garments (as required); the contractor shall ensure that each contract employee procures a United States Passport within 60 days of start of work in order to conduct official travel to OCONUS locations in the estimated travel schedule above; the contractor shall provide Defense Base Act Insurance (DBAI) for insurance coverage of contract employees while performing official duties at OCONUS locations listed above. | Question 1) This para requires the contractor to provide personal protective equipment for each employee however we are unsure of the connection to the tasks within the PWS. Can the government please clarify this requirement? | ||
| Question 2) This paragraph references "official travel to OCONUS locations in the estimated travel schedule above" and a requirement for DBAI "while performing duties at the OCONUS locations listed above." Can the government provide the OCONUS locations for travel? | See page 2 of responses to questions | ||||
| Clarify | PWS 1.6.1, Page 36 and PWS 5.1, Page 45 | Quality Control: The Contractor shall develop and maintain an effective quality control plan to ensure services are performed in accordance with this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor’s Quality Control Program (QCP) is the means by which the contractor is assured that the work complies with the requirement of the contract. The contractor’s QCP is submitted as part of the Start of Work Briefing (SoWB) in accordance with task 5.1 on this PWS. If changes are made thereafter, three copies shall be submitted to the KO and COR within 5 working days of changes. After acceptance of QCP changes, the Contractor shall request the contracting officer’s acceptance of changes in writing. | PWS 5.1 Task 1 is Organizational Capabilities and Capabilities Integration. Can the government clarify this requirement within the solicitation? | ||
| Clarify | PWS 5.4.1.10, Page 55 | The contractor shall provide training and leader development subject matter expertise to TCM ABCT TADSS contractors to monitor the distribution and support of existing and future System and Non-System TADSS devices in support of the ABCT User to include all ABCT Live, Virtual, Constructive, Gaming, and Simulations Systems, and review all future CPDs and CDDs to ensure training devices are properly considered within the context of system requirements. Concur or non-concur and provide written comments within 5 days. | Please clarify what is meant by provide training and leader development subject matter expertise to TCM ABCT TADSS contractors? | ||
| Question | PWS 5.1.2, Page 47 | Science and Technology Integration. Science and Technology Integration Contractor qualifications and prerequisites: Previous leadership and staff experience in operational planning, training, sustainment and logistics of tactically deployable Brigade Combat Teams (BCTs), and experience in a TRADOC organization conducting BCT specific DOTMLPF development or integration as a Soldier, Civilian or Contractor with experience in identifying future requirements for manpower, material, facilities, and services needed to support Army programs of record; a bachelor’s degree from an accredited college or university with a focus on leadership and management is preferred. | Since this is for Science and Technology Integration, is experience required in identifying requirements in each of these individual areas or is it acceptable to have requisite experience in at least one of these areas? | ||
| Recommendation | PWS 5.3.1, Page 50 | AMPV Mission Command and General Purpose Variants Integration. AMPV Mission Command and General Purpose Variant Integration Contractor qualifications and prerequisites: Previous technical experience in maintenance, training management, and tactical employment of wheeled or tracked vehicle systems while conducting DA operational training or deployment in a maneuver BCT, and previous experience serving in a TRADOC organization conducting maneuver BCT specific DOTMLPF development or integration, as a Soldier, DA Civilian or Defense Contractor; experience as a combat platform Master Gunner is required. | This requirement appears inconsistent with the tasks required. Recommend this requirement be deleted. | ||
| PWS 5.3.2, Page 51 | AMPV Medical Evacuation, Treatment, and Mortar Variants Integration. AMPV Medical Evacuation, Treatment, and Mortar Variants Integration Contractor qualifications and prerequisites: Previous technical experience in maintenance, training management, and tactical employment of wheeled or tracked vehicle systems while conducting DA operational training or deployment in a maneuver BCT, and previous experience serving in a TRADOC organization conducting maneuver BCT specific DOTMLPF development or integration, as a Soldier, DA Civilian or Defense Contractor; experience as a combat platform Master Gunner is required. | This requirement appears inconsistent with the tasks required. Recommend this requirement be deleted. | |||
| Questions | PWS 5.4.1, Page 53 | Battalion and Above DOTMLPF Analysis and Integration. Contractor qualifications and prerequisites: Previous experience in planning, resourcing, performing, and supervising ABCT DOTMLPF requirements while conducting DA operational training or deployment, and previous experience in a TRADOC organization conducting ABCT specific DOTMLPF development or integration, as a Soldier, DA Civilian or Defense Contractor. Experience in brigade-level troop leading positions and/or experience as a certified PME or functional training course instructor, developer, or manager is preferred. A bachelor’s degree in technical writing, English, communications, or a related field from an accredited college or university is required. | Q1) Recommend the requirement be reduced to a Bachelor's Degree without any field requirement or that the acceptable fields be expanded to any that include substantial writing requirements (for example, a person with a degree in History would have had to successfully written extensively as part of earning that degree). |
Q2) Request clarification regarding the requirement for "previous experience in planning, resourcing, performing, and supervising ABCT DOTMLPF requirements while conducting DA operational training or deployment". The use of the work "and" requires the person to have experience in each of the listed activities - this seems overly restrictive - request the government change "and" to "or".
Q3) Request clarification regarding the requirement for "experience in brigade-level troop leading positions". What are the acceptable positions to meet this requirement - (e.g. is Brigade Commander experience required or are personnel with staff experience at the Brigade level acceptable)?
Q4) Request clarification regarding the reference to "certified PME" and the definition of "PME" within this context? PME often stands for Professional Military Education but not sure what is meant by certified or if a particular level of PME is required.
Question / Recommendation PWS 5.4.2, Page 55 Company and Below DOTMLPF Analysis and Integration. Doctrine, Organization, Training, Leadership, Personnel and Facilities Analyst. Infantry, Armor, or Cavalry leadership experience in an ABCT and experience in TRADOC conducting BCT specific DOTMLPF development or integration is required. In lieu of the above, a combination of three years of leadership assignments in BCTs and TRADOC as a Soldier, civilian, or contractor will be considered. A bachelor's degree in technical writing, English, communications, or a related field is required. Q1) Would the government consider a combination of three years of leadership assignments in BCTs and TRADOC as a Soldier, civilian, or contractor will be considered. A bachelor's degree in technical writing, English, communications, or a related field is required." ?
R1) Recommend the requirement be reduced to a Bachelor's Degree without any field requirement or that the acceptable fields be expanded to any that include substantial writing requirements (for example, a person with a degree in History would have had to successfully written extensively as part of earning that degree).
Question PWS 5, Page 44-45 Specific Tasks: Provide on-site services to the TCM ABCT and the Maneuver Center of Excellence at Ft. Benning, GA to address all DOTMLPF development and integration issues concerning PEO GCS managed systems. In addition, provide the Director of TCM ABCT the professional services required to assist in the combat development, test and evaluation, training and leader development integration, sustainment and logistics integration, and network/mission command systems integration in determining both material and non-material solutions for ABCT combat systems and personnel across all DOTMLPF domains. Work for all positions shall take place in TCM ABCT government furnished offices, classrooms, or other government directed locations as required for successful completion of the tasks. Exceptions shall be outlined in the vendor’s proposal and will be subject to government approval. The contractor shall provide the government the proposed plan for selection, retention, training, support, work-related travel planning and assistance, incentives, and timely replacement (when necessary), of specifically qualified personnel that meet position prerequisites for education, service, and experience in all task areas, and provides uninterrupted
| professional services support for the life of the task order. Replacement actions shall have minimal impact on task requirements. | There is inadequate information to analyse and calculate the level of effort required to perform the work. The level of effort is dependent on the frequency and length of time (based on complexity) required to perform each of the required activities. Is it the government's expectation that one qualified FTE be provided for each x.x.x level task described in paragraph 5 of the PWS. If that is the expectation, would an offer of fewer personnel be acceptable? If that is not the expectation, request the government provide the Level of Effort required or provide the demand data (i.e. frequency and average time to perform each of the required activities) so that an appropriate level of effort analysis can be executed. Without this, only the incumbent could effectively assess the LOE required/acceptable. | ||||
| Section L | |||||
| Question | A. Submission Instructions. #7, #8 Page 70 and C. EVALUATION CRITERIA Page 72, #1 | In the Submission Instructions talks to two volumes I - Technical and Volume II - Price there is no mention of Past Performance. Under the Evaluation Criteria it talks to Factor 1 Technical Capability, Factor 2 Price and Factor 3 Past Performance. Can the government add into the Submission instructions the Past Performance requirements as well as submission requirements like # 10 and 11? | See section M in the solicitation amendment | ||
| Clarify | A. Submission Instructions #11, Page 71 | 11. Volume II – Price Submission. The price submission should be clearly marked “Volume II, Price Submission, W911SF-19-R-0009.” It is to consist of the following: |
a. The offeror shall include a price proposal for the Contract Line Item Number (CLIN) Structure shown in Attachment 2.
b. For each period of performance, the proposal shall include the labor/pricing matrix (ces); a Discount rate (if applicable); the number of full time equivalents (FTEs); the number of total hours per labor category; and the total dollar value.
Period of Performance: The period of performance shall be for one (1) Base Period of 12 months and two (2) 12 month Option Periods.
Base Year –21 February 19 to 20 February 2020 Option Year I – 21 February 19 to 20 February 2021
| Option Year II – 21 February 19 to 20 February 2022 | It appears there is no Attachment 2 posted in FBO. Can the government please provide Attachment 2? T | Yes- | |||
| Submission of Offerors, 2 , Page 68 | SUBMISSION OF OFFERS 2. Offers are to be received by MICC-Fort Benning no later than 1 :00 PM Eastern Time, Tuesday 5 February 2019. All proposals should be submitted via-email. All questions regarding this solicitation shall be submitted in writing via email to Susanne H. Johnson, @ susanne.h.johnson.civ@mail.mil and Vernessa Hampton, @ vernessa.hampton.civ@mail.mil. The deadline for the submittal of all questions and/or comments is 4 February 2019 no later than 1:00 PM Eastern Standard Time, in writing via email only. | Questions are due to be submitted by 4 February 2019 and the bid responses are due on 5 February 2019. Can the government please clarify if this is correct or is it the governments intent to provide an extension? | Yes see amendment | ||
| Question | A. Submission Instruction, #10, Page 70 and 72 and C. Evaluation Criteria (1), Page 72 | A. Submission Instructions 10. Volume I - Technical Submission. The technical submission should be clearly marked “Volume I - Technical Submission, W911SF-19-R-0009.” Volume I shall consist of a written narrative that is the offeror’s proposed solutions to the requirement contained in the Performance Work Statement (PWS) for this contract. The technical discussion shall be practical, straightforward, specific, concise, and complete. Volume I is not to include price information. A list of attachments, exhibits, tables, and figures of prospective employees as required, shall be provided. The table of exhibits, tables, and figures will “NOT” count against the 20-page limitation. C. EVALUATION CRITERIA |
(1) The Government reserves the right to evaluate the lowest priced proposal first, and if it is acceptable, award to that offeror. In the event that the lowest price proposal is not acceptable, the second lowest proposal will be evaluated, and so on. The Evaluation Criteria will consist of factors, and sub factors. Each offeror’s proposals will be evaluated using three (3) evaluation factors.
Factor 1: Technical Capability Sub factor 1: Staffing Approach Sub factor 2: Management Approach Sub factor 3: Experience Factor 2: Price
| Factor 3: Past Performance | Can the government provide the missing evaluative criteria information in Section L so the offeror can ensure a responsive Factor 1 Technical Capability submission? | See section M of the solicitation | |||
| Question | Evaluation Criteria, C, (1), Page 72 | Factor 3: Past Performance | Could the government provide the evaluation criteria for Volume III, Factor 3, Past Performance? | See section M of the solicitation | |
| Section M | |||||
| Question | RFP Evaluation Criteria, Section C. (2), Page 72 - 73 | FACTOR AND RATING TECHNIQUES |
(2) Factor 1 - Technical Capability Subfactor 3: Experience. The minimum standard:
Offeror has at least six (6) years experience in the type of service industry required by this PWS.
Contracted employees shall possess the required qualifications specified in the
PWS.
Question B. Basis for Award, #4, Page 72 4. Offers received for less than the stated number of items listed in the Pricing Schedule will be considered ineligible for award. The Government intends to evaluate proposals and award without discussions with offerors. The Government reserves the right to conduct discussions if
| the Contracting Officer determines discussions to be necessary. | The paragraph reference a Pricing Schedule that was not included in the solicitation. Can the government please provide the pricing schedule? | Please see Section B of the solicitation | |||
| Clarify | B. Bases of Award, Page 71 | 1. A single award will be made to the responsible offeror submitting the proposal that is determined to offer the lowest price technically acceptable (LPTA) to the Government (i.e., which provides the greatest overall benefit to the Government in response to the requirement, price and non-price evaluation factors considered). As such, the Government may award to other than the lowest priced or technically outstanding proposal. | Can the government please clarify the basis of award LPTA or best value? | Please see section M of the solicitation |