SEE ADDENDUM
(No Collect Calls)
W911SA20Q3084 09-Jun-2020
b. TELEPHONE NUMBER 8. OFFER DUE DATE/LOCAL TIME
10:00 AM 18 Jun 2020
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA X ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W911SA9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
SHANNON A BAKER
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
0011470948-0001
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESSX
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
MICC - FT MCCOY
BLDG 1108 SOUTH R ST
FORT MCCOY WI 54656-5153
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE 16. ADMINISTERED BY
SEE SCHEDULE
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
FAX:
TEL: SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$30,000,000
NAICS:
484210
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF131
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
Section SF 1449 - CONTINUATION SHEET
SUPPLEMENTAL INFORMATION
1. This requirement will be awarded as a firm fixed price (FFP), Indefinite Delivery/Indefinite Quantity (IDIQ) contract. The Government reserves the right to order the maximum quantities and is only obligated to order the minimum guarantee. It is the unilateral right of the Government to exercise the option year(s) of this contract.
2. The guaranteed minimum for the base year is $5,000.00. There is not a minimum guarantee for the option periods. The first task order is estimated to start on or about 1 July 2020.
3. An Award for this requirement will be made pursuant to FAR 13.5, Simplified Procedures for Certain Commercial Items.
4. Quotes shall be email emailed to shannon.a.baker2.civ@mail.mil. Quotes are due to the Government on or before the time listed above in central time. Offeror shall submit a signed SF 1449, completed information from the supplemental section and a completed Price Schedule (if applicable).
5. Period for acceptance of offers. The offeror agrees to hold the prices in its offer firm for 90 calendar days from the date specified for receipt of offers.
6. Site visit: There will no site visit for this requirement because of the COVID-19 restrictions. Please see photo site visit attachment.
The POC for the solicitation is Shannon Baker, shannon.a.baker2.civ@mail.mil
7. Written questions must be furnished to the Government no later Tuesday June 15, 2020 @ 10:00 AM
Central Standard Time (CST); in order to ensure a timely response is provided by the solicitation closing date. All questions are to be submitted in writing at the time indicated in the solicitation or they may not be addressed before solicitation closing date; therefore, offerors are advised to submit questions as soon as possible. Please provide your company name, telephone, point of contact, e-mail address, and solicitation number on all questions. The Government will respond to questions via the issuance of an amendment which incorporates the question and the Government’s response.
8. DUNS NUMBER ______________________________.
9. TAXPAYER ID #______________________________.
10. CAGE CODE __________________________________.
11. This requirement is eligible for payment through the GFEBS Supplier Self-Services (SUS) Program.
Information on this program can be found in the SUS Attachment. Please indicate if you will participate in this program, if your company receives award.
Yes___________ No ___________
12. In accordance with DFAR Clause 252.216-7006, “Ordering,”:
a. Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the contract schedule. Such orders may be issued prior to the expiration of the contract.
b. All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control
c. (1) If issued electronically, the order is considered “issued” when a copy has been posted to the
Electronic Data Access system, and notice has been sent to the Contractor.
(2) If mailed or transmitted by facsimile, a delivery order or task order is considered “issued” when the Government deposits the order in the mail or transmits by facsimile. Mailing includes transmittal by U.S. mail or private delivery services.
(3) Orders may be issued orally only if authorized in the schedule.
13. SYSTEM for AWARD MANAGEMENT (SAM) REGISTRATION: An Active SAM Registration is required of all Department of Defense contractors. SAM registration enables electronic funds transfer of contract payments. If your company is not already actively registered, please register in the SAM database at www.sam.gov. If your company is currently registered and close to expiring, begin/complete the process for SAM registration renewal.
a. A DUNS number is required for SAM registration. If your company does not have a DUNS #, obtain one by calling 800-333-0505.
a. Whether your company is a current or new registrant in the SAM database, your registration must indicate that you are a provider of NAICS 484210, or a NAICS of similar business size, under the Goods – Services section of the registration to be eligible to receive a contract for this solicitation.
b. If the prospective awardee for this request for quotes is not actively registered in the SAM database by close of solicitation, including NAICS 484210, or a NAICS of similar business size, under the Goods – Services section, depending on mission requirements, the government reserves the right to proceed to award to the next otherwise successful actively registered offeror.
14. Contract Administrator: TBD at time of award.
If you have questions pertaining to this contract after contract award (i.e. questions regarding delivery, invoice procedures, etc.), please request assistance from the Contract Administrator. Be sure to include the contract number in your request for assistance. Requesting contract administration assistance from any other individual could result in a delayed response.
15. Contracting Officer: TBD at time of award.
16. Contracting Officer’s Representative (COR): To Be Determined at the time of Award.
17. Ordering Officer:
a. There will be a designated Ordering Official under this contract, authorized to make purchases up totheir designated authority of $25,000, per single maintenance known requirement, against thisIndefinite Delivery/Indefinite Quantity Contract (IDIQ).
Projects under this threshold will not be issued on an individual task order STANDARD FORM 1449, however, all requirements of the contract award, and all policies and procedures will be applicable to projects ordered by the designated official.
b. The ordering officials will administer and be the main POC for all orders placed under their authority.
The ordering officer POC(s): Charles Hilt, 608-388-5209, charles.a.hilt.civ@mail.mil
(1) All ordering officers may use the Government-wide purchase card, commonly referred to as the Government "credit card," as an alternative method of ordering and paying for purchases made under this contract. Purchase card orders are subject to all terms and conditions of this contract, unless otherwise stated in this provision or another provision in this contract.
(2) The purchase card is specifically designed for use by the Federal Government. The purchase card is like a typical commercial credit card. However, the authorization limitations of the purchase card are more specific, i.e., only for a particular contract, monthly limitations, certain categories of products or services, etc. The purchase card will be exclusively used for official Government purchases in accordance with the prices, terms, and conditions of this contract. The purchase card order limitation shall be $25,000. With respect to ordering authority, only designated Ordering Officers may use the purchase card as a means of purchasing items on this contract.
3) Credit limits for the purchase card for ordering officers is $25,000. These credit limits for the purchase card are the responsibility of the credit card holder and the approving office.
(4) The contractor shall accept payment via credit card for projects authorized by the ordering officers and that have followed the required policies and procedures within this solicitation and resultant contract.
(5) Invoices for orders placed by the ordering officer will be submitted directly to the ordering officer, and progress payments will still be authorized if applicable, the same as would be authorized for Task Order issued on the Standard Form 1449.
18. The Government intends to evaluate offers and award a contract without discussions. Therefore, the offeror’s initial offer should contain the offeror’s best terms from a price and technical standpoint.
However, the Government reserves the right to conduct discussions if later determined by the Contracting Officer to be necessary. The Government may reject any or all offers if such action is in the public interest and waive informalities and minor irregularities in offers received.
19. As part of its proposal, the offeror must provide the estimated total cost (if any) incurred to comply with the enterprise Contractor Manpower Reporting Application (eCMRA) requirement. Offeror will determine to price or not separately price the CMRA requirement. CMR CLIN(s) is the CLIN(s) under which the Contractor shall bill for all costs associated with the CMRA requirement.
20. Postaward Conference: In the event the Contracting Officer decides to conduct a Postaward Conference in accordance with DFARS 242.5, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed.
21. ABILITYONE DESIGNATED ITEMS: In accordance with 52.208-9, contractors are referred to the web site of the Committee for Purchase from People Who Are Blind or Severely Disabled, the independent federal agency that administers the AbilityOne (formerly Javits-Wagner-O'Day or JWOD) Program for the lists of designated products and services http://abilityone.gov/procurement_list/product_buy.html.
22. Offeror representations and certifications requirement: Prospective contractors who have not completed electronic annual representations and certifications at http://www.sam.gov/ in conjunction with required registration in the System for Award Management (SAM) database, shall complete and submit FAR 52.212-3 Alternative 1 Offeror Representations and Certifications - Commercial Items and DFARS Representations and Certifications in SAM to be eligible to receive an award for this solicitation.
23. In accordance with FAR 52.223-2, Affirmative Procurement of Bio-based Products under Services and Construction Contracts, contractors are required to submit annual bio-based reports to the reporting module in the System for Award Management (SAM) at https://www.sam.gov.
24. If an offer is based on a teaming/partnering relationship or a joint venture, the offeror shall provide, with the proposal, all required solicitation information for all parties including a copy of the teaming/partnering or joint venture agreement. The agreement shall include information, which identifies the responsibilities for each entity under this contract. The agreement shall demonstrate the relationship between firms and identify contractual relationships and authorities to bind each entity of the teaming/partnering or joint venture relationship.
25. The “Equal Employment Opportunity Is The Law” notice (poster) referenced in FAR Clause 52.222- 26(b)(3), is located at http://www.dol.gov/ofccp/regs/compliance/posters/pdf/eeopost.pdf .
26. In accordance with FAR Clause 52.222-41(g), the contractor must notify each service employee working on this contract of the minimum wage and fringe benefits required to be paid pursuant to this contract, or shall post a copy of the wage determination and Department of Labor Form WH-1313 in a prominent place at the worksite. The applicable wage determination is incorporated into the contract. The WH-1313 poster is located at http://www.dol.gov/whd/regs/compliance/posters/sca.htm.
27. Alternate disputes resolution: In furtherance of Federal policy and the Administrative Dispute Resolution
Act of 1990 (ADR Act), Public Law 101-552 and FAR Clause 52.233-1, Subparagraph (d) (2) (1) (B) (2), the Contracting Officer will try to resolve all post award acquisition issues in controversy by mutual agreement of both parties. Interested parties are encouraged to use alternative dispute resolution procedures to the maximum extent practicable, in accordance with the authority and requirements of the ADR Act.
28. Contract performance:
Purpose. IAW with FAR Subpart 42.1500 contractor past performance information (PPI) is relevant information for future source selection purposes regarding a contractor’s actions under previously awarded contracts. It includes, for example, the contractor's record of conforming to contract requirements and to standards of good workmanship; the contractor's record of forecasting and controlling costs; the contractor's adherence to contract schedules, including the administrative aspects of performance; the contractor's history of reasonable and cooperative behavior and commitment to customer satisfaction; and generally, the contractor's business-like concern for the interest of the customer. Contractor past performance information is one of the tools that support Army efforts to acquire best value and is used to evaluate performance risk in source selection. The feedback provided by the government to the contractor in collecting PPI, and the knowledge that PPI will be used in future source selection decisions, should result in improved performance and a greater contractor focus on customer satisfaction.
Contractor Performance Assessment Reports System (CPARS): CPARS shall be prepared IAW AFARS Subpart 42 upon physical completion of the contract. If the period of performance will exceed 18 months, an “interim” assessment report shall be prepared at the completion of 12 months performance and annually thereafter until the contract is physically complete. An out-of-cycle or “addendum” report may be prepared if there is a need to record an extraordinary event prior to the next regularly scheduled evaluation or if it is necessary to report a meaningful occurrence during the period between physical completion of the contract and contract closeout. Additionally, addendum reports may be prepared to record contractor’s performance relative to contract closeout and other administrative requirements (e.g.
final indirect cost proposals, technical data, etc.).
Completion Due Date. The government will complete the CPARS within 60 days after the end of the assessment rating period (if applicable).
Evaluators. The Contracting Officer and the Contracting Officer’s Representative will jointly complete the performance assessment.
Contracts Performance Elements. The contractor’s performance shall be assessed in accordance with elements and rating system set forth in AFARS Subpart 42.
Contractor Review. The Contracting Officer will furnish a copy of the CPARS to the contractor requesting that the contractor submit comments, rebutting statements, and/or additional information to the Contracting Officer within 30 calendar days of receipt. Failure to respond within the designated timeframe will be taken as agreement with the assessment.
Contract Concurrence. Where a contractor concurs with, or takes no exception to a CPARS, such report shall be considered final and releasable for use in source selection and other deliberative purposes.
Contractor Rebuttal. Where a contractor takes exception to a performance report, the Contracting Officer will review the contractor’s rebuttal or comments and make appropriate changes. If the Contracting Officer makes changes, the changed rating will be reflected in the narrative. The Contracting Officer will make all reasonable efforts to reconcile the report and the contractor’s comments. However, it is not necessary that they reach agreement on the report where such is clearly impracticable. The contractor’s rebuttal or comments shall be made part of the CPARS.
Resolving Disagreements between the Government and the Contractor. In the event disagreements between the parties regarding the CPARS occur, the Contracting Officer will review the rebuttal and make appropriate changes. If no agreement is reached, the CPARS is forwarded to the Reviewing Official (Director of Contracting) along with the Contracting Officer’s Findings and Recommendation and supporting documentation. The decision of the Reviewing Official is final. Copies of the CPARS and the contractor’s response and review comments, if any, shall be retained as part of the evaluation.
Release of Contractor Performance Evaluation Information. The evaluation will not be released to other than government personnel and the contractor whose performance is evaluated. The performance evaluation information will be input into the applicable module within Contractor Performance Assessment Reporting System (CPARS) database (or Government system in use at time of the evaluation).
Source Selection Information. Departments and agencies will electronically access the CPARS information to support future award decisions.
29. Required insurance:
In accordance with FAR clause 52.228-5 entitled, “Insurance--Work on a Government Installation” the following minimum amounts of insurance are required.
Workmen’s Compensation As required by state laws
Employer’s Liability Insurance $100,000 per accident General Liability Insurance - Bodily Injury Liability $500,000 per occurrence
Auto Liability Insurance $200,000 per person
Bodily Injury $500,000 per occurrence
Property Damage $20,000 per occurrence
Within ten (10) calendar days after contract award, the Contractor shall certify to the Contracting Officer, in writing, that the required insurance has been obtained.
30. Legal compliance: The Contractor shall comply with all Federal, State, and Local Laws, codes and regulations applicable to his performance under this contract, and shall be solely responsible for all costs associated with said compliance.
31. In accordance with FAR 52.222-42, In compliance with the Service Contract Labor Standards statute and the regulations of the Secretary of Labor (29 CFR part 4), this clause identifies the classes of service employees expected to be employed under the contract states the wages and fringe benefits payable to each if they were employed by the contracting agency subject to the provisions of 5 U.S.C. 5341 or 5 332.
This Statement is for Information Only. It is not a Wage Determination.
Employee Class Monetary Wage -- Fringe Benefits 23470 -- Laborer WG-2 -- Step 2
W911SA20Q3084
PWS
PERFORMANCE WORK STATEMENT (PWS)
Directorate of Public Works (DPW)
Installation Furniture Movement Fort McCoy, WI
PART 1
GENERAL INFORMATION
1.1. General. This is a Firm Fixed Price (FFP), Indefinite Delivery, Indefinite Quantity (IDIQ) contract non-personnel services contract to provide for furniture movement services. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.
1.2. Scope of Work. Services include furniture movement services to support Fort McCoy, WI. Services may include movement and relocation, installation, assembly, disassembly, packing, palletizing, shrink wrapping, banding, unpacking, transporting, accountability, adjustments and repairs to designated furniture, property book items, office panel systems, shelving units, bulletin boards, white boards, mop closet hangers, coat racks and other miscellaneous items, and disposal of items as determined by the Government. When deemed necessary, the Government will provide furniture, office panel systems, and shelving unit space drawing plans for the Contractor to follow. The Contractor shall not move personal property. The Contractor shall perform to the standards in this contract. The Contractor shall review space plans accompanying any Task Order.
1.2.1. The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform furniture movement services defined in this PWS except for those items specified as government furnished property and services in Part 3 of this PWS.
1.3. Place of Performance: The work performed under this contract will be performed at various buildings on Fort McCoy, WI.
1.4. Period of Performance. The period of performance shall be for one (1) Base Year of 12 months and four (4) 12 month option years.
1.5. Hours of Operation: The Contractor is responsible for conducting business, between 0700 and 1630 hours Monday through Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. For other than firm fixed price contracts, the Contractor will not be reimbursed when the government facility is closed for the above reasons.
The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all Tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
1.6. Federal Government Holidays.
New Year’s Day 1st day of January Martin Luther King Jr.'s Birthday 3rd Monday of January Presidents Day 3rd Monday of February Memorial Day Last Monday of May Independence Day 4th day of July Labor Day 1st Monday of September Columbus Day 2nd Monday of October Veterans Day 11th day of November Thanksgiving Day 4th Thursday of November Christmas Day 25th day of December
1.7 Ordering: Services will be ordered by issuance of a Task Order, awarded by the Contracting Office or by the Ordering Officer. The Task Order (TO) will specify which services are required and the building numbers where the performance of services will be located.
1.7.1 Task Order (TO) Period of Performance (POP): Each Task Order issued under this contract shall have a scheduled TO POP date. Each Task Order shall be completed within the scheduled TO POP date.
1.8. Ordering Officer Information. There will be a designated Ordering Official under this contract, authorized to make purchases up to their designated authority of $25,000, per single known requirement, against this IDIQ contract. Orders under this threshold will not be issued on an individual Delivery Order FORM 1449, however, all requirements of the contract award, and all policies and procedures will be applicable to orders by the designated official. Prices and Salient Features for the project will still require agreement/approval by the ordering official.
The ordering officials will administer and be the main POC for all orders placed under their authority.
The following describes the procedures to be used for ordering items under this contract by using the Federal Government-wide purchase card. This option to order by use of the Government-wide purchase card is strictly an alternative method of ordering by the Government and may be used in place of ordering by other order forms that comply with FAR 12.204. The Government reserves the right to unilaterally terminate the use of the credit card at any time.
All ordering officers may use the Government-wide purchase card, commonly referred to as the Government "credit card," as an alternative method of ordering and paying for purchases made under this contract. Purchase card orders are subject to all terms and conditions of this contract, unless otherwise stated in this provision or another provision or clause in this contract. The purchase card is specifically designed for use by the Federal Government. The purchase card is like a typical commercial credit card. However, the authorization limitations of the purchase card are more specific, i.e., only for a particular contract, monthly limitations, certain categories of products or services, etc. The purchase card will be exclusively used for official Government purchases in accordance with the prices, terms, and conditions of this contract. The purchase card order limitation shall be $25,000. With respect to ordering authority, only designated Ordering Officers may use the purchase card as a means of purchasing items on this contract.
Credit limits for the purchase card for ordering officers is $25,000. These credit limits for the purchase card are the responsibility of the credit card holder and the approving office.
The contractor shall accept payment via credit card for projects authorized by the ordering officers and that have followed the required policies and procedures within this solicitation and resultant contract.
***Invoices for orders placed by the ordering officer will be submitted directly to the ordering officer. However, use of WAWF to create and accept receiving reports is mandatory when the GPC is used as a method of payment against a contract. In order to ensure proper routing of contract transactions paid with the GPC, use the code "CRCARD" in the Pay Official/DoDAAC field. The contractor is required to generate a receiving report in WAWF, and the Government acceptor is required to accept the receiving report in WAWF. The Cardholder is required to verify that acceptance has occurred in WAWF prior to submitting the invoice to the Certifying Official for certification.
1.9. Key Personnel. The following personnel are considered key personnel by the Government: Project Manager.
The Contractor shall provide a project manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the Contractor when the manager is absent shall be designated via email to the COR NLT fifteen (15) business days after contract award and immediately after any changes. The project manager or alternate shall have full authority to act for the Contractor on all contract matters relating to daily operations of this contract. The project manager or alternate shall be available on Fort McCoy, WI during the performance of each Task Order.
1.9.1. Supervision of Contractor Employees: The Government will not exercise any supervision or control over Contractor or Sub-Contractor employees while performing work under the contract. Such employees shall be accountable solely to the Contractor, not the Government. The Contractor, in turn, shall be accountable to the Government for Contractor or Sub-Contractor employees.
1.10. Identification (ID) of Contractor Employees. The Contractor shall provide each employee, to include subcontractor employees, an ID Badge, which includes at a minimum, the company Name, employee Name and a color photo of the employee. ID Badges for Key Personnel shall also indicate their job title. ID Badges shall be worn at all times during which the employee is performing work under this contract. Each Contractor employee shall wear the ID Badge in a conspicuous place on the front of exterior clothing and above the waist except when safety or health reasons prohibit. The Contractor shall be responsible for collection of ID Badges upon completion of the contract or termination of an employee. An ID Badge list shall be submitted by email to the COR NLT five
(5) task order performance start date and updated NLT five (5) days prior to new employees commencing performance under this contract when personnel changes occur. All contract personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.
1.11. Background Checks. Access and General Protection/Security Policy and Procedures: All contractor employees to include subcontractor employees, must pass a background check prior to commencing performance under this contract. The contractor and all associated subcontractors' employees shall provide all information required for background checks (See Below) to meet installation access requirements to be accomplished by Director of Emergency Services (DES) or Security Office. Contractor workforce must comply with all Federal Acquisition Regulation (FAR) clause 52.204-9, personal identity verification requirements as directed by DOD, Head Quarters Department of Army (HQDA) and/or local policy. The contractor workforce shall also comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive (DIR) 2014-05/Army Regulation (AR) 190-13, applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes. The Government may require monthly participation in the Installation Random Antiterrorism Program.
1.11.1. The contractor shall provide all information required for background checks on Fort McCoy forms 451 and 452 (See Attachments Section 7) for all employees. Contractors shall complete and submit FM forms 451 and 452 to the COR no later than seven (7) calendar days prior to the required entry date requirement for each employee.
Contractor personnel performing work under this contract shall submit to a National Crime Information Center Interstate Identification Index (NCIC-III) Criminal History Check before access will be granted to Fort McCoy.
Once the individual has cleared the criminal history they will be issued an Installation Access Card (IAC). An unfavorable NCIC-III Criminal History Check will result in the contractor being denied access to the installation and a waiver request must be approved prior to gaining access. For waiver approval process coordinate with the installation physical security office. For more information please contact the Installation Physical Security Section at 608-388-8445/2010/4694 or 3794.
Information required for Criminal History Check:
• Full Name, Including middle name(s)
• Sex
• Date of Birth
• Driver’s License information
• Issuing State
• Beginning and End date
• Access Hours
• Work location
• Company Name
• Position (i.e. Construction) For more information please contact the Installation Physical Security Section at 608-388-8445/2010/4694 or 3794.
1.12 Contractor Personnel Conduct: Contractor personnel’s conduct shall not reflect discredit upon the Government. The Contractor shall ensure that personnel present a professional appearance. The Contractor’s employees shall observe and comply with all local policies and procedures concerning fire, safety, environmental protection, sanitation, security, and possession of firearms or other lethal or illegal weapons or substance. The Contractor is responsible for ensuring that any Contractor employees providing services under this contract conduct themselves and perform services in a professional, safe, and responsible manner. The Contractor shall remove from the job site any employee for reasons of misconduct or security. In accordance with DOD Directive 5500.7-R, “Joint Ethics Regulation”, Contractor employees must avoid improper influence in the execution of their duties under the contract. Particular attention should be paid to acceptance of gifts/ gratuities, and on non-disclosure of sensitive or classified information. The Contractor shall ensure employee conduct complies with 41 U.S. C 423 relative to release of acquisition related information or actions or discussions which may prejudice future competitions. The Contractor shall ensure no Contractor employees conduct political related activities or events on the Installation Facilities. The Contractor shall comply with all DOD and local requirements that establish uniform policies governing smoking in and around Government-owned buildings and vehicles. The Contractor shall comply with Federal drug-free workplace and requirements IAW FAR 52.223-6 and 252.223-7004. Government rules, regulations, laws, directives, and requirements which are issued during the contract term relating to law and order, Installation administration, and security on the Installation shall be applicable to all Contractor employees or representatives who enter the Installation. Violation of such rules, regulations, laws, directives, or requirements shall be grounds for removal (permanently or temporarily as the Government determines) from the work site.
Removal of employees does not relieve the Contractor from the responsibility for the work defined in this PWS.
•Removal by Garrison Commander. The Garrison Commander may, at his/her discretion, bar an individual from the Installation under the authority of 18 USC 1382 (1972), AR 210-10 (Administration), and the National Industrial Security Program Operating Manual (NISPOM) for conduct determined contrary to good order, discipline, or Installation security.
•Removal by Contracting Officer (KO). The Contracting Officer may require the Contractor to remove any employee, working under this contract, for reason of misconduct or security. Contractor employees shall be subject to dismissal from the premises upon determination by the Contracting Officer that such action is necessary in the interest of the Government.
•Removal by Installation Police. Contractor employees may be denied entry to the Installation by Military Police if it is determined that such entry may be contrary to good order, discipline, or the security of the Installation. Military Police may remove any Contractor employee from the Installation for reason of misconduct or security.1.6.18 Government and Personal Property. The Contractor shall be responsible for safeguarding US Government (USG) and personal property. The Contractor shall conduct work so that Government property, personnel and work areas shall be protected at all times from inconvenience, damage or injury. In the event of loss or damage of any nature, caused by Contractor operations or employees, due to improper protection, precaution or safety measures, such damages shall be repaired or such property shall be replaced by the Contractor at his expense. In the event the Contractor does not satisfactorily repair or replace such damages, the Government reserves the right to make necessary correction and the Contractor shall reimburse the Government for all labor and materials costs associated with repairs or replacement.
1.13 Installation Access and Control:
1.13.1 Restrictions: The Contractor shall not employ any person who is determined by the Installation Commander to be a potential threat to the health, safety, security, general well-being or operational mission of the Installation or its population, to include personnel who are, or become, barred or restricted from the Installation. The Government reserves the right to require removal of any Contractor personnel from the job site who endanger persons or property, or whose continued employment is inconsistent with the interest of military security. The Government also reserves the right to require the Contractor to remove from the job site, any employee found to be under the influence of alcohol, drugs or any other incapacitating agent or any employee involved in the theft of Government property. The removal from the job site of such personnel shall not relieve the Contractor of the requirement to provide personnel to perform services
1.13.2 Restricted Areas: During the course of the contract, certain areas/sites may become restricted or closed to contractor personnel. The Contractor shall comply with all rules, regulations and entry requirements to include signing in or obtaining an entry badge and/or waiting for an escort. Photography is prohibited without the written permission from the Government.
1.13.3 Installation / Gate Closure: Unscheduled gate closures may occur at any time and personnel entering or exiting the Installation may experience a delay. Privately owned vehicles are subject to search upon entry, exit, and at any time while on the Installation. Refusal to comply with a request to search a vehicle could result in access to the Installation being denied. Delays in entering or leaving the Installation due to gate closures or vehicle searches shall not be compensated for in any form by the Government.
1.13.4 Search and Seizure: Contractor personnel and property shall be subject to search and seizure upon entering the confines of Fort McCoy, Wisconsin and upon leaving the confines of Fort McCoy, Wisconsin in accordance with AR 190-22 (Search, Seizure, and Disposition of Property).
1.13.5 Controlled Substances: Contractor personnel shall not perform PWS work while in possession of, or while under the influence of, alcohol or any controlled substance.
1.13.6 Weapons: Contractor personnel shall comply with all Fort McCoy regulations governing possession and transport of privately owned weapons on the Installation, including all forms of firearms, tasers, bow and arrow, switchblade or automatic blade knives, knives with blades in excess of three inches, ammunition and pyrotechnics, fireworks, bludgeons, brass knuckles, shooting pens or similar devices IAW Fort McCoy Regulation 190-12.
1.13.7 Government Issued Identification Media: The Contractor shall ensure Government issued pass and identification items required for contract performance are obtained for employees and non-government owned vehicles prior to the employee performing work under the contract. Final payment under the contract will not be made until all Government issued identification media, including Common Access Cards are returned to the Government.
1.14 Physical Security: The Contractor shall be responsible for safeguarding all government equipment, information and property provided for Contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured. The Contractor shall, at the conclusion of each workday or departure from each worksite/facility, sign a Activity Security Checklist (see section 7 attachments) to validate the secure status of each facility. The Contractor shall provide the Activity Security Checklists via email to the COR upon request.
1.15. Key Control: The Government will provide keys for the Contractor to gain access to facilities where work issued on Task Order(s) is to be performed during normal working hours. The Contractor shall maintain control of government keys at all times. Key control applies to both physical keys and electronic key access. Security and storage of electronic key codes shall comply with AR 380-5. The Contractor shall establish and implement methods of making sure all keys issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. NOTE: All references to keys include key cards. No keys/key cards issued to the Contractor by the Government shall be duplicated. The Contractor shall develop procedures covering key control. Such procedures shall include turn-in of any issued keys/key cards by personnel who no longer require access to locked areas. The Contractor shall immediately report any occurrences of lost or duplicate keys/key cards to the COR. The Contractor shall be responsible for security of the area in which work is being performed and prior to completion.
The Contractor shall maintain accountability and control of any keys provided, and shall return them to the COR daily and upon completion of work.
1.15.1 Missing/Lost Keys: Lost keys shall be reported to the COR immediately. The Contractor is responsible for filing a Police Report with the Fort McCoy Department of Emergency Services (DES) and notifying the COR NLT 24 hours after the discovery of the lost key or keys. In the event keys/key cards are lost or duplicated, the Government will replace the affected lock or locks or perform re-keying. The total cost of re-keying or replacement of the lock or locks shall be deducted from the payment due to the Contractor. The Contractor shall comply with Security of Unclassified Army Property (Sensitive and Non-sensitive) AR 190-51 and Property Accountability Policies AR 735-5 chapter 14-23.
1.15.2 Authorized Access: The Contractor shall prohibit the use of Government issued keys/key cards by any persons other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas In Accordance With (IAW) this contract, or personnel authorized entrance by the KO or COR.
1.16 Government and Personal Property. The Contractor shall be responsible for safeguarding US Government (USG) and personal property. The Contractor shall conduct work so that Government property, personnel and work areas shall be protected at all times from inconvenience, damage or injury. In the event of loss or damage of any nature, caused by Contractor operations or employees, due to improper protection, precaution or safety measures, such damages shall be repaired or such property shall be replaced by the Contractor at his expense. In the event the Contractor does not satisfactorily repair or replace such damages, the Government reserves the right to make necessary corrections and the Contractor shall reimburse the Government for all labor and materials costs associated with repairs or replacement.
1.16.1 Mishaps. In the event of any mishap to property or person(s), the Contractor shall take reasonable and prudent action to establish control of the mishap scene, prevent further damage to persons or property and notify emergency services by calling 911. The Contractor shall remain on-scene until released by the Fort McCoy Police Department.
1.16.1.1 Mishap Reporting. The contractor shall provide a verbal and written report to the COR NLT (1) business day of occurrence. Initial notification shall be made by phone followed up by a written Damage or Discrepancy Reports via email NLT one (1) business day of occurrence. The Contractor shall bear all costs of repairing or replacing the damaged property or loss if the determination is made that the damage or loss was caused by the Contractor or the Contractor’s employees. The Contractor shall bear all costs of minor damages (to include nicks, dents, mars, and scratches) as identified in the Discrepancy Report and Joint Post inspection in accordance with the Performance Requirements Summary (PRS).
1.17. Anti-Terrorism (AT) Level I Awareness Training. All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, or controlled access areas shall complete AT Level I awareness training. AT Level I awareness training certification for all employees shall be submitted to the COR NLT 30 calendar days after notification of contract award, or within NLT 30 calendar days after new employees commence performance under this contract, and annually NLT 30 calendar days after the start of the option period.
The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR via email (or to the contracting officer, if a COR is not assigned) NLT 60 calendar days after completion of training by all employees and subcontractor personnel. The COR will provide a copy to the requiring activity Anti-Terrorism Office (ATO). AT Level I awareness training is available at https://jkodirect.jten.mil/Atlas2/page/login/Login.jsf. When available, classroom training may also be coordinated locally through the ATO. Contact the COR for availability of this local classroom training.
1.18. iWATCH Training. The contractor shall brief all contractor employees, including subcontractor employees, on the local iWATCH program. The training standards will be provided to the contractor by the COR who will obtain the locally developed training from the requiring activity ATO. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employee’s where/how to report suspicious activity. An iWATCH training certification for all employees shall be submitted to the COR NLT 30 calendar days after the contract start date, or NLT 30 calendar days after new employees commence performance under this contract and annually NLT 30 calendar days after the start of the option period. COR will provide a copy to the requiring activity ATO.
1.19. Operations Security (OPSEC) Awareness Training. Per AR 530-1 All contractor Employees, including subcontractor employees, requiring access to Army installations, facilities, or controlled access areas shall complete
OPSEC Level I training NLT 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever applies. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR (or to the contracting officer, if a COR is not assigned) within 60 calendar days after completion of training by all employees and subcontractor personnel.
Training is available at http://cdsetrain.dtic.mil/opsec. The COR will provide a copy to the requiring activity ATO.
1.20 Safety Plan: The Contractor is solely responsible for compliance with the Occupational Safety and Health Act (OSHA) (Public Law 91-596) and the resulting standards, OSHA Standard 29 CFR 1910, 1926, and the protection of their employees. The Contractor shall establish and maintain a Safety Plan that delineates the processes and procedures the Contractor shall use to prevent accidents and preserve the life and health of Contractor and Government personnel. The Contractor shall report Contractor employees’ accidents and injuries to the Contractor’s Project Management Staff, the Contracting Officer, the COR and the Fort McCoy Installation Safety Office (ISO) in accordance with Fort McCoy Reg 385-10 and 29 CFR 1910. The Contractor shall be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence, and shall take proper safety and health precautions to protect the work, the workers, the public, and the property of others.