W911SA-17-B-2004_Solicitation_Amendment_0001.docx

DOCX document 29 KB Posted

Attached to
REPLACE FLOORING AT B370 AND B520 AT CAMP PARKS, CA Federal contract opportunity
Solicitation number
W911SA-17-B-2004
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort McCoy

About this file

Solicitation Amendment 0001

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911SA-17-B-2004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00700 - CONTRACT CLAUSES

The following have been deleted:

52.211-12
LIQUIDATED DAMAGES--CONSTRUCTION
SEP 2005

SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS

The following have been added by full text:

QUESTIONS AND ANSWERS

Q1. Can the Site Superintendent act also as the QCM and the SSHO (1 person wearing all three hats)?

A1. Yes, as long all the training requirements are met.

Q2.Are there any hazardous materials within the carpet and base adhesives or work areas?

A2. No, this building are fairly new, bldg. 520 built 2003, and 370 built 1992

Q3.Due to the occupied areas, will any phasing be required? If so,please provide an anticipated phasing plan.

A3. Depending on the time of year, bldg. 370 will have training, but contractor will be notify ahead of time to work a schedule. Bldg. 520 there is not schedule as this building is always occupy, we just have to work around them, firemen are aware of the project.

Q4.The SOW requires the contractor to move existing office furniture. Does this include computers, copiers, printers, or any personal items?

A4. Yes, but if fire department are willing to help with electronics and computers. Bldg. 370 there is one printer that we can ask our maintenance contract to move if required.

Q5.Are there areas within the facilities where the existing office furniture can be temporarily placed during construction? Or will the contractor be required to provide temporary storage containers?

A5. At bldg 520 we have the tv room that is large enough to hold up to two offices. Bldg. 370 no need for temporary holding furniture.

Q6.There is a built-in cabinet/armoire within the bedrooms of Bldg.520. The cabinet is wrapped with 6" cove base. Is this base to be removed and 4" cove base installed in its place?

A6. No, contractor shall install new 6" cove base.

Q7. The existing Cove base is 4". When the existing carpet is removed and the 1/*" Vinyl tile is installed the new base will set lower than the original. The outcome of that will be a horizontal line that was previously covered by the original base. If it is not painted or painted and not matched to existing paint the walls will look terrible. Would the Government desire the Contractor to Install 4 1/ " Base if available?

A7. Yes, no more than 4 1/2"-5" the existing carpet seems not to have padding so it should only be a small difference. Also, bldg. 520 wall lockers and cabinets have 8" cove base that will required to install.

Q8. In building 370 we are to install floor covering in the Elevator. Does the Government desire Coin flooring made of sheet vinyl or rubber as per the conversation at the site visit.

A8.We prefer Coin Flooring, it last longer and is more rigid for heavy rolling carts.