W911SA-17-B-2003_Amendment_0001.docx
DOCX document 43 KB Posted
- Attached to
- Job Order Contract (JOC), ID, MT, UT, WA, OR, CO
- Solicitation number
- W911SA-17-B-2003
About this file
Amendment 0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W911SA-17-B-2003_TE-2_NORTHWEST_JOC_Coefficient_Spreadsheet_10.16.17.xlsx | XLSX spreadsheet | |
| W911SA-17-B-2003_TE-5_Wage_Rate_Requirement_10.16.17.docx | DOCX document | |
| W911SA-17-B-2003_Amendment_0002.docx | DOCX document | |
| W911SA-17-B-2003_Pre-Bid_Conference_Slides_(u).pptx | PPTX presentation | |
| W911SA-17-B-2003_Pre-Bid_Conference_Sign-In_Sheet.pdf | ||
| W911SA-17-B-2003_TE-1_Statement_of_Work.doc | DOC document | |
| W911SA-17-B-2003_TE-2_NORTHWEST_JOC_Coefficient_Spreadsheet_(u1).xlsx | XLSX spreadsheet | |
| W911SA-17-B-2003_Solicitation.docx | DOCX document | |
| W911SA-17-B-2003_Appendix_A_-_Pre_Bid_Conference_Reg.docx | DOCX document | |
| W911SA-17-B-2003_TE-5_Wage_Rate_Requirement.docx | DOCX document | |
| W911SA-17-B-2003_TE-4_Unified_Facilities_Criteria_(UFC_4-171-05).pdf | ||
| W911SA-17-B-2003_TE-3_ATOPSEC_CoverSheet.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W911SA-17-B-2003
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 17-Oct-2017 02:00 PM to 24-Oct-2017 02:00 PM.
SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS
The following have been added by full text:
QUESTIONS AND ANSWERS
Q1. What size are the maximum Task Orders?
A1. Refer to FAR 52.216-19
Q2. What size are the average Task Orders?
A2. It is difficult to determine averages on task orders because work can be different for each facility depending on the needs of that facility and any emergencies that arise.
Q3. What is the majority of the work?
A3. The work varies depending on the need of the facility.
Q4. How many projects/workload can the contractor be given at one time?
A4. The contractor can be given whatever is within the limitation of FAR 52.216-19 as far as amount. However, it also varies depending on availability of funds
Q5. What are the range/type of task orders for this IDIQ?
A5. A task order/type can range from painting, repairing lights to HVAC changeovers, replacing elevators and anything in-between depending on the need of the facility/location.
Q6. Can the contractor deny task orders if they have too much work on hand?
A6. No, unless it falls outside the limitations of FAR Clause 52.216-19.
Q7. Are the 4 year renewal options by mutual consent?
A7. No, please refer to FAR Clause 52.217.9.
Q8. After reading the solicitation, I did not see that this 8a set-aside will be set-aside for a certain region. Can you please confirm that this contract is open to all 8a certified companies?
A8. This is open to all 8(a) companies. However, the company will still have to be validated/approved by the SBA.
Q9. Can you please let me know the previous incumbent contractor and the coefficient for the previous contract?
A9. The previous incumbent contractor is Allcon, LLC and the coefficients for the previous contract are as follows: Base Year .83; Option Period One .83; Option Period Two .83; Six Month Extension .41 and Total Evaluated Price (TEP) 2.90.