Solicitation - W911S025BA001 ADJ. FINAL.pdf
PDF 2 MB Posted
- Attached to
- GRADING, DRAINAGE AND PAVEMENT CONSTRUCTION, MAINTENANCE, AND REPAIRS POSTWIDE FORT NOVOSEL, ALABAMA
- Solicitation number
- W911S025BA0001
About this file
This is a Sealed Bid (IFB) solicitation document W911S025BA001 issued by the Department of the Army Mission and Installation Contracting Command at Fort Eustis for paving services at Fort Novosel, Alabama. The solicitation is for an Indefinite Delivery/Indefinite Quantity contract for asphalt paving, construction of horizontal structures, earth works, and storm drainage structures, with a guaranteed minimum of $2,000 and maximum value of $29.5 million over five years if all options are exercised.
The contract includes a base year and four one-year options, with work to be performed from April 1, 2025 through March 31, 2026 for the base period. Bids are due March 10, 2025 at 10:00 AM EST at 705 Washington Blvd STE 126, Fort Eustis. A bid guarantee of 20% of the estimated annual maximum contract value ($5.7M) is required. The NAICS code is 237310 with a size standard of $45M. Pricing will be based on coefficients applied to a Unit Price Book for standard hours, non-standard hours, and non-pre-priced work. The contractor must provide all labor, materials, equipment, supervision, transportation and incidentals except for Government-furnished items.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF 1409 Novosel Paving.pdf | ||
| SF_1409 Novosel Bid Recording.pdf | ||
| Solicitation Amendment - W911S025BA0010001.pdf | ||
| Paving Solicitation QuestionsAnswers.xlsx | XLSX spreadsheet | |
| Ft Novosel Paving PERFORMANCE WORK STATEMENT 03042025.docx | DOCX document | |
| BidSchedule Novosel Paving.xlsx | XLSX spreadsheet | |
| Paving Solicitation QuestionsAnswers (1).xlsx | XLSX spreadsheet | |
| Bid Schedule 1.xlsx | XLSX spreadsheet | |
| Performance Work Statment.docx | DOCX document | |
| SpecBookComplete ALDOT Specs 2022.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION
15A. NAME AND
ADDRESS
OF OFFEROR
SOLICITATION, OFFER, AND AWARD 1. This Contract is a Rated Order under the Defense Priorities and Allocations System (DPAS) - Code of Federal Regulations - at 15 CFR 700.
RATING PAGE OF PAGES
2. CONTRACT NUMBER 3. SOLICITATION NUMBER 4. TYPE OF SOLICITATION 5. DATE ISSUED 6. REQUISITION/PURCHASE NUMBER
CODE7. ISSUED BY 8. ADDRESS OFFER TO (If other than item 7)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
9. Sealed offers in original and copies for furnishings the supplies or services in the Schedule will be received at the place specified in item 8, or if hand carried, in the depository located in until local time
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision Number 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.
10. FOR
INFORMATION
CALL:
A. NAME B. TELEPHONE (NO COLLECT CALLS)
AREA CODE NUMBER EXTENSION
C. EMAIL ADDRESS
11. TABLE OF CONTENTS
(X) DESCRIPTION PAGE(S) (X) SECTION PAGE(S)DESCRIPTION
A B C D E F G H
I
J
K
L
M EVALUATION FACTORS FOR AWARD
INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
REPRESENTATIONS, CERTIFICATIONS AND OTHER
STATEMENTS OF OFFERORS
PART IV - REPRESENTATIONS AND INSTRUCTIONS
LIST OF ATTACHMENTS
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
CONTRACT CLAUSESSOLICITATION/CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/COSTS
DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
PACKAGING AND MARKING
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
CONTRACT ADMINISTRATION DATA
SPECIAL CONTRACT REQUIREMENTS
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
OFFER (Must be fully completed by offeror)
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause Number 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the SOLICITATION for offerors and related documents numbered and dated):
10 CALENDAR DAYS (%) 20 CALENDAR DAYS (%) 30 CALENDAR DAYS (%) CALENDAR DAYS (%)
DATEAMENDMENT NUMBERAMENDMENT NUMBER DATE
CODE FACILITY 16. NAME AND THE TITLE OF PERSON AUTHORIZED TO SIGN OFFER
(Type or print)
15B. TELEPHONE NUMBER
AREA CODE NUMBER EXTENSION
15C. CHECK IF REMITTANCE ADDRESS IS
DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
17. SIGNATURE 18. OFFER DATE
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL OPEN COMPETITION UNDER THE
UNITED STATES CODE AT:
10 U.S.C. 3204(a) ( )41 U.S.C. 3304(a)
24. ADMINISTERED BY (If other than Item 7)
26. NAME OF CONTRACTING OFFICER (Type or print)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is unusable
23. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
25. PAYMENT WILL BE MADE BY
27. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
28. AWARD DATE
CODE
ITEM
STANDARD FORM 33 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.214 (c)
SEALED BID (IFB) INVITATION FOR BID
NEGOTIATED (RFP) REQUEST FOR
PROPOSAL
(Hour) (Date)
PART I - THE SCHEDULE PART II - CONTRACT CLAUSES
Created On:
06 Feb 2025, 18:39 PM Central Standard Time
Section A - Solicitation/Contract Form
Ft. Novosel Paving
a. Title: Fort Novosel, AL Paving Contract.
b. The Government intends to award one Indefinite Delivery/Indefinite Quantity paving contract.
c. The guaranteed minimum amount is $2,000.
d. The total value of the contract will not exceed $29,500,000 for all five years should the Government exercise all four option periods.
e. This acquisition is full and open competition.
f. Offers are due 10 March 2025 10:00am EST
NOTES:
Block 11: The contract establishes period(s) of ordering whereas the individual task orders establish specific completion dates for those job orders.
Block 12: The required bonding amount must represent the annual maximum contract
W911S025BA001
Section B - Supplies or Services & Prices or Costs
Additional Information/Notes
Item Supplies/Service Estimated Quantity
Unit Unit Price Amount
Estimated Value of the Contract for the Base Year. (NOTE: The Contractor shall provide all labor, materials, and equipment and perform all work in accordance with the individual Task Orders, Scope of Work, and Drawings, if any).
Pricing for items to be utilized in ordering the work to be performed shall be annotated on Attachment 2 - Bid Schedule.
Product Service Code: Y1LB Pricing Arrangement: Firm Fixed Price
1 Job
Option Line Item
Estimated Value of the Contract for Option Year 1. (NOTE: The Contractor shall provide all labor, materials, and equipment and perform all work in accordance with the individual Task Orders, Scope of Work, and Drawings, if any).
Pricing for items to be utilized in ordering the work to be performed shall be annotated on Attachment 2 - Bid Schedule.
Product Service Code: Y1LB Pricing Arrangement: Firm Fixed Price
1 Job
Option Line Item
Estimated Value of the Contract for Option Year 2. (NOTE: The Contractor shall provide all labor, materials, and equipment and perform all work in accordance with the individual Task Orders, Scope of Work, and Drawings, if any).
Pricing for items to be utilized in ordering the work to be performed shall be annotated on Attachment 2 - Bid Schedule.
Product Service Code: Y1LB Pricing Arrangement: Firm Fixed Price
1 Job
Option Line Item
Estimated Value of the Contract for Option Year 3. (NOTE: The Contractor shall provide all labor, materials, and equipment and perform all work in accordance with the individual Task Orders, Scope of Work, and Drawings, if any).
Pricing for items to be utilized in ordering the work to be performed shall be annotated on Attachment 2 - Bid Schedule.
1 Job
Product Service Code: Y1LB Pricing Arrangement: Firm Fixed Price
Option Line Item
Estimated Value of the Contract for Option Year 4. (NOTE: The Contractor shall provide all labor, materials, and equipment and perform all work in accordance with the individual Task Orders, Scope of Work, and Drawings, if any).
Pricing for items to be utilized in ordering the work to be performed shall be annotated on Attachment 2 - Bid Schedule.
Product Service Code: Y1LB Pricing Arrangement: Firm Fixed Price
1 Job
Section C - Description/Specifications/Statement of Work
See attachment 1: Performance Work Statement (PWS)
Requirements This requirement is for a performance-based acquisition for asphalt paving, construction of horizontal structures, earth works, and storm drainage structures that are on or owned by Fort Novosel.
Section E - Inspection and Acceptance
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
52.246-12 Inspection of Construction. Aug 1996
Overall Contract Inspection/Acceptance Locations
Inspection and Acceptance Location
Both Destination Instructions: See Statement of Work (SOW) or Performance Work Statement (PWS) for Acceptance/inspection criteria.
DoDAAC: W31BMV CountryCode: USA
W6CE DIR PUBLIC WORKS
DEPARTMENT OF PUBLIC WORKS, BLDG 1100 DILLY BRANCH RD
FORT NOVOSEL, AL 36362-5116
UNITED STATES
Option Line Item
Inspection and Acceptance Location
Both Destination Instructions: See Statement of Work (SOW) or Performance Work Statement (PWS) for Acceptance/inspection criteria.
DoDAAC: W31BMV CountryCode: USA
W6CE DIR PUBLIC WORKS
DEPARTMENT OF PUBLIC WORKS, BLDG 1100 DILLY BRANCH RD
FORT NOVOSEL, AL 36362-5116
UNITED STATES
Option Line Item
Inspection and Acceptance Location
Both Destination Instructions: See Statement of Work (SOW) or Performance Work Statement (PWS) for Acceptance/inspection criteria.
DoDAAC: W31BMV CountryCode: USA
W6CE DIR PUBLIC WORKS
DEPARTMENT OF PUBLIC WORKS, BLDG 1100 DILLY BRANCH RD
FORT NOVOSEL, AL 36362-5116
UNITED STATES
Option Line Item
Inspection and Acceptance Location
Both Destination Instructions: See Statement of Work (SOW) or Performance Work Statement (PWS) for Acceptance/inspection criteria.
DoDAAC: W31BMV CountryCode: USA
W6CE DIR PUBLIC WORKS
DEPARTMENT OF PUBLIC WORKS, BLDG 1100 DILLY BRANCH RD
FORT NOVOSEL, AL 36362-5116
UNITED STATES
Option Line Item
Inspection and Acceptance Location
Both Destination Instructions: See Statement of Work (SOW) or Performance Work Statement (PWS) for Acceptance/inspection criteria.
DoDAAC: W31BMV CountryCode: USA
W6CE DIR PUBLIC WORKS
DEPARTMENT OF PUBLIC WORKS, BLDG 1100 DILLY BRANCH RD
FORT NOVOSEL, AL 36362-5116
UNITED STATES
Section F - Deliveries or Performance
From 01 Apr 2025 to 31 Mar 2026
Party to Pay Transportation Cost: Contractor
Point Type: Destination
Line Item Delivery Schedule Estimated Quantity
Address and POC
Period of Performance From 01 Apr 2025 To 31 Mar 2026
1 Job
Option Line Item
Period of Performance From 01 Apr 2026 To 31 Mar 2027
1 Job
Option Line Item
Period of Performance From 01 Apr 2027 To 31 Mar 2028
1 Job
Option Line Item
Period of Performance From 01 Apr 2028 To 31 Mar 2029
1 Job
Option Line Item
Period of Performance From 01 Apr 2029 To 31 Mar 2030
1 Job
Section G - Contract Administration Data
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
252.201-7000 Contracting Officer's Representative. Dec 1991 252.232-7003 Electronic Submission of Payment Requests and Receiving Reports. Dec 2018 252.236-7000 Modification Proposals--Price Breakdown. Dec 1991
Section I - Contract Clauses
52.219-14 Limitation on subcontracting. (Sept 2021)(DEVIATION 2021 O0008)
52.219-16 Liquidated Damages - Subcontracting Plan (Sept 2021)
FAR Clauses Incorporated by Full Text
52.217-8 Option to Extend Services.
Option to Extend Services (Nov 1999)
The Government require continued performance of any services within the limits and at the rates specified in the contract. These rates be may may adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The provision be exercised more than option may once, but the total extension of performance hereunder not exceed 6 months. The exercise the by written notice shall Contracting Officer may option to the Contractor within . 30 days
(End of clause)
52.217-9 Option to Extend the Term of the Contract
Option to Extend the Term of the Contract (Mar 2000)
(a) The Government extend the term of this contract by written notice to the Contractor within ; provided that the Government gives the may 30 days Contractor a preliminary written notice of its intent to extend at least 30 days before the contract expires. The preliminary notice does not commit the Government to an extension.
(b) If the Government exercises this , the extended contract be considered to include this clause. option shall option
(c) The total duration of this contract, including the exercise of any under this clause, not exceed 78 months. options shall
(End of clause)
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
52.202-1 Definitions. Jun 2020 52.203-3 Gratuities. Apr 1984 52.203-5 Covenant Against Contingent Fees. May 2014 52.203-6 Restrictions on Subcontractor Sales to the Government. Jun 2020 52.203-7 Anti-Kickback Procedures. Jun 2020 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. May 2014 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. May 2014 52.203-12 Limitation on Payments to Influence Certain Federal Transactions. Jun 2020
52.203-13 Contractor Code of Business Ethics and Conduct. Nov 2021 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. Jun 2020 52.204-13 System for Award Management Maintenance. Oct 2018 52.204-19 Incorporation by Reference of Representations and Certifications. Dec 2014
52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities.
Dec 2023
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
Nov 2021
52.204-27 Prohibition on a ByteDance Covered Application. Jun 2023
52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment.
Nov 2021
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters. Oct 2018 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations. Nov 2015 52.210-1 Market Research. Nov 2021 52.214-26 Audit and Records-Sealed Bidding. Jun 2020
52.214-27 Price Reduction for Defective Certified Cost or Pricing Data-Modifications-Sealed Bidding.
Jun 2020
52.214-28 Subcontractor Certified Cost or Pricing Data-Modifications-Sealed Bidding. Jun 2020 52.219-8 Utilization of Small Business Concerns. Feb 2024 52.222-3 Convict Labor. Jun 2003 52.222-6 Construction Wage Rate Requirements. Aug 2018 52.222-7 Withholding of Funds. May 2014 52.222-8 Payrolls and Basic Records. Jul 2021 52.222-9 Apprentices and Trainees. Jul 2005 52.222-10 Compliance with Copeland Act Requirements. Feb 1988 52.222-11 Subcontracts (Labor Standards). May 2014 52.222-12 Contract Termination-Debarment. May 2014 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. May 2014 52.222-14 Disputes Concerning Labor Standards. Feb 1988 52.222-15 Certification of Eligibility. May 2014 52.222-21 Prohibition of Segregated Facilities. Apr 2015 52.222-26 Equal Opportunity. Sep 2016 52.222-27 Affirmative Action Compliance Requirements for Construction. Apr 2015
52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately Specified Method).
Aug 2018
52.222-35 Equal Opportunity for Veterans. Jun 2020 52.222-36 Equal Opportunity for Workers with Disabilities. Jun 2020 52.222-37 Employment Reports on Veterans. Jun 2020 52.222-50 Combating Trafficking in Persons. Nov 2021 52.222-54 Employment Eligibility Verification. May 2022 52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026. Jan 2022 52.223-5 Pollution Prevention and Right-to-Know Information. May 2024 52.225-13 Restrictions on Certain Foreign Purchases. Feb 2021 52.229-3 Federal, State, and Local Taxes. Feb 2013 52.232-17 Interest. May 2014 52.232-33 Payment by Electronic Funds Transfer-System for Award Management. Oct 2018 52.232-39 Unenforceability of Unauthorized Obligations. Jun 2013 52.232-40 Providing Accelerated Payments to Small Business Subcontractors. Mar 2023 52.233-1 Disputes. May 2014 52.233-1 Disputes. (Alternate I) May 2014 Alternate I Dec 1991 52.233-3 Protest after Award. Aug 1996 52.233-4 Applicable Law for Breach of Contract Claim. Oct 2004 52.236-2 Differing Site Conditions. Apr 1984 52.236-3 Site Investigation and Conditions Affecting the Work. Apr 1984 52.236-5 Material and Workmanship. Apr 1984 52.236-6 Superintendence by the Contractor. Apr 1984 52.236-7 Permits and Responsibilities. Nov 1991 52.236-8 Other Contracts. Apr 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. Apr 1984 52.236-10 Operations and Storage Areas. Apr 1984 52.236-11 Use and Possession Prior to Completion. Apr 1984 52.236-12 Cleaning Up. Apr 1984 52.236-13 Accident Prevention. Nov 1991 52.236-15 Schedules for Construction Contracts. Apr 1984 52.236-21 Specifications and Drawings for Construction. Feb 1997 52.242-13 Bankruptcy. Jul 1995 52.242-14 Suspension of Work. Apr 1984 52.243-4 Changes. Jun 2007 52.249-2 Termination for Convenience of the Government (Fixed-Price). Apr 2012 52.249-10 Default (Fixed-Price Construction). Apr 1984
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
252.203-7000 Requirements Relating to Compensation of Former DoD Officials. Sep 2011 252.203-7001 Prohibition on Persons Convicted of Fraud or Other Defense-Contract-Related Felonies. Jan 2023 252.203-7002 Requirement to Inform Employees of Whistleblower Rights. Dec 2022 252.203-7003 Agency Office of the Inspector General. Aug 2019 252.203-7004 Display of Hotline Posters. Jan 2023 252.204-7003 Control of Government Personnel Work Product. Apr 1992 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. May 2024 252.205-7000 Provision of Information to Cooperative Agreement Holders. Oct 2024
252.209-7004 Subcontracting with Firms that are Owned or Controlled by the Government of a Country that is a State Sponsor of Terrorism.
May 2019
252.219-7003 Small Business Subcontracting Plan (DoD Contracts). Dec 2019 252.222-7006 Restrictions on the Use of Mandatory Arbitration Agreements. Jan 2023 252.223-7006 Prohibition on Storage, Treatment, and Disposal of Toxic or Hazardous Materials. Sep 2014 252.225-7048 Export-Controlled Items. Jun 2013 252.232-7010 Levies on Contract Payments. Dec 2006 252.236-7005 Airfield Safety Precautions. Dec 1991 252.243-7001 Pricing of Contract Modifications. Dec 1991 252.243-7002 Requests for Equitable Adjustment. Dec 2022 252.244-7000 Subcontracts for Commercial Products or Commercial Services. Nov 2023 252.246-7004 Safety of Facilities, Infrastructure, and Equipment for Military Operations. Oct 2010
FAR Clauses Incorporated by Full Text
52.211-10 Commencement, Prosecution, and Completion of Work. (Apr 1984)
As prescribed in 11.404(b), insert the following clause in solicitations and contracts when a fixed-price construction contract is contemplated. The clause may be changed to accommodate the issuance of orders under indefinite-delivery contracts for construction.
Commencement, Prosecution, and Completion of Work (Apr 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 10 calendar days.
* The time stated for completion shall include final cleanup of the premises.
* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.
(End of clause)
52.211-12 Liquidated Damages-Construction. (Sep 2000)
As prescribed in 11.503(b), insert the following clause in solicitations and contracts:
Liquidated Damages-Construction (Sept 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of 1% for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
52.219-28 Post-Award Small Business Program Rerepresentation. (Feb 2024)
As prescribed in 19.309(c)(1), insert the following clause:
Post-Award Small Business Program Rerepresentation (Feb 2024)
(a) Definitions. As used in this clause-
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern-
(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (d) of this clause.
(2) Affiliates, as used in this definition, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.
(b) If the Contractor represented that it was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (f) of this clause or, if applicable, paragraph (h) of this clause, upon occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts-
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) If the Contractor represented that it was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (f) of this clause or, if applicable, paragraph (h) of this clause, when the Contracting Officer explicitly requires it for an order issued under a multiple-award contract.
(d) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code(s) assigned to this contract. The small business size standard corresponding to this NAICS code(s) can be found at https://www.sba.gov/document/support--table-size-standards.
(e) The small business size standard for a Contractor providing an end item that it does not manufacture, process, or produce itself, for a contract other than a construction or service contract, is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition-
(1) Was set aside for small business and has a value above the simplified acquisition threshold;
(2) Used the HUBZone price evaluation preference regardless of dollar value, unless the Contractor waived the price evaluation preference; or
(3) Was an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(f) Except as provided in paragraph (h) of this clause, the Contractor shall make the representation(s) required by paragraph (b) and (c) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause, or with its offer for an order (see paragraph (c) of this clause), that the data have been validated or updated, and provide the date of the validation or update.
(g) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (f) or (h) of this clause.
(h) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
(1) The Contractor represents that it [ ] is, [ ] is not a small business concern under ____NAICS Code assigned to ____contract number.
(2) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that it [ ] is, [ ] is not, a small disadvantaged business concern as defined in 13 CFR 124.1001.
(3) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that it [ ] is, [ ] is not a women-owned small business concern.
(4) Women-owned small business (WOSB) joint venture eligible under the WOSB Program. The Contractor represents that it [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [The Contractor shall enter the name and unique entity identifier of each party to the joint venture: ____.]
(5) Economically disadvantaged women-owned small business (EDWOSB) joint venture. The Contractor represents that it [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [The Contractor shall enter the name and unique entity identifier of each party to the joint venture: ____ .]
(6) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause. ] The Contractor represents that it [ ] is, [ ] is not a veteran-owned small business concern.
(7) [Complete only if the Contractor represented itself as a veteran-owned small business concern in paragraph (h)(6) of this clause.] The Contractor represents that it [ ] is, [ ] is not a service-disabled veteran-owned small business concern.
(8) Service-disabled veteran-owned small business (SDVOSB) joint venture eligible under the SDVOSB Program. The Contractor represents that it [ ] is, [ ] is not an SDVOSB joint venture eligible under the SDVOSB Program that complies with the requirements of 13 CFR 128.402. [The Contractor shall enter the name and unique entity identifier of each party to the joint venture: ____.]
(9) [ Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause. ] The Contractor represents that-
(i) It [ ] is, [ ] is not a HUBZone small business concern listed, on the date of this representation, on the List of Qualified HUBZone Small Business Concerns maintained by the Small Business Administration, and no material changes in ownership and control, principal office, or HUBZone employee percentage have occurred since it was certified in accordance with 13 CFR part 126; and
(ii) It [ ] is, [ ] is not a HUBZone joint venture that complies with the requirements of 13 CFR part 126, and the representation in paragraph (h)(8)(i) of this clause is accurate for each HUBZone small business concern participating in the HUBZone joint venture. [The Contractor shall enter the names of each of the HUBZone small business concerns participating in the HUBZone joint venture:____.] Each HUBZone small business concern participating in the HUBZone joint venture shall submit a separate signed copy of the HUBZone representation.
[____Contractor to sign and date and insert authorized signer's name and title.]
(End of clause)
52.219-28 Post-Award Small Business Program Rerepresentation. (Alternate I) (Feb 2024) Alternate I (Mar 2020)
Alternate I (Mar 2020). As prescribed in 19.309 (c)(2), substitute the following paragraph (h)(1) for paragraph (h)(1) of the basic clause:
(h)(1) The Contractor represents its small business size status for each one of the NAICS codes assigned to this contract.
NAICS Code Small business concern (yes/no)
237310 NO
52.222-40 Notification of Employee Rights Under the National Labor Relations Act. (Dec 2010)
As prescribed in 22.1605 , insert the following clause:
Notification of Employee Rights Under the National Labor Relations Act (Dec 2010)
(a) During the term of this contract, the Contractor shall post an employee notice, of such size and in such form, and containing such content as prescribed by the Secretary of Labor, in conspicuous places in and about its plants and offices where employees covered by the National Labor Relations Act engage in activities relating to the performance of the contract, including all places where notices to employees are customarily posted both physically and electronically, in the languages employees speak, in accordance with 29 CFR471.2 (d) and (f).
(1) Physical posting of the employee notice shall be in conspicuous places in and about the Contractor's plants and offices so that the notice is prominent and readily seen by employees who are covered by the National Labor Relations Act and engage in activities related to the performance of the contract.
(2) If the Contractor customarily posts notices to employees electronically, then the Contractor shall also post the required notice electronically by displaying prominently, on any website that is maintained by the Contractor and is customarily used for notices to employees about terms and conditions of employment, a link to the Department of Labor's website that contains the full text of the poster. The link to the Department's website, as referenced in (b)(3) of this section, must read, "Important Notice about Employee Rights to Organize and Bargain Collectively with Their Employers."
(b) This required employee notice, printed by the Department of Labor, may be-
(1) Obtained from the Division of Interpretations and Standards, Office of Labor-Management Standards, U.S. Department of Labor, 200 Constitution Avenue, NW., Room N-5609, Washington, DC 20210, (202) 693-0123, or from any field office of the Office of Labor-Management Standards or Office of Federal Contract Compliance Programs;
(2) Provided by the Federal contracting agency if requested;
(3) Downloaded from the Office of Labor-Management Standards Web site at http://www.dol.gov/olms/regs/compliance/EO13496.htm; or
(4) Reproduced and used as exact duplicate copies of the Department of Labor's official poster.
(c) The required text of the employee notice referred to in this clause is located at Appendix A, Subpart A, 29 CFR Part 471.
(d) The Contractor shall comply with all provisions of the employee notice and related rules, regulations, and orders of the Secretary of Labor.
(e) In the event that the Contractor does not comply with the requirements set forth in paragraphs (a) through (d) of this clause, this contract may be terminated or suspended in whole or in part, and the Contractor may be suspended or debarred in accordance with 29 CFR 471.14 and subpart 9.4.
Such other sanctions or remedies may be imposed as are provided by 29 CFR part 471, which implements Executive Order 13496 or as otherwise provided by law.
(f) Subcontracts.
(1) The Contractor shall include the substance of this clause, including this paragraph (f), in every subcontract that exceeds $10,000 and will be performed wholly or partially in the United States, unless exempted by the rules, regulations, or orders of the Secretary of Labor issued pursuant to section 3 of Executive Order 13496 of January 30, 2009, so that such provisions will be binding upon each subcontractor.
(2) The Contractor shall not procure supplies or services in a way designed to avoid the applicability of Executive Order 13496 or this clause.
(3) The Contractor shall take such action with respect to any such subcontract as may be directed by the Secretary of Labor as a means of enforcing such provisions, including the imposition of sanctions for noncompliance.
(4) However, if the Contractor becomes involved in litigation with a subcontractor, or is threatened with such involvement, as a result of such direction, the Contractor may request the United States, through the Secretary of Labor, to enter into such litigation to protect the interests of the United States.
(End of clause)
52.232-5 Payments under Fixed-Price Construction Contracts. (May 2014)
As prescribed in 32.111(a)(5), insert the following clause:
Payments under Fixed-Price Construction Contracts (May 2014)
(a) Payment of price. The Government shall pay the Contractor the contract price as provided in this contract.
(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.
(1) The Contractor's request for progress payments shall include the following substantiation:
(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.
(ii) A listing of the amount included for work performed by each subcontractor under the contract.
(iii) A listing of the total amount of each subcontract under the contract.
(iv) A listing of the amounts previously paid to each such subcontractor under the contract.
(v) Additional supporting data in a form and detail required by the Contracting Officer.
(2) In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if-
(i) Consideration is specifically authorized by this contract; and
(ii) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.
(c) Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)
I hereby certify, to the best of my knowledge and belief, that-
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor's performance.
____ (Name)
____ (Title)
____ (Date)
(d) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-
(1) Notify the Contracting Officer of such performance deficiency; and
(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8 thday after the date of receipt of the unearned amount until-
(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or
(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.
(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.
(f) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-
(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or
(2) Waiving the right of the Government to require the fulfillment of all of the terms of the contract.
(g) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.
(h) Final payment. The Government shall pay the amount due the Contractor under this contract after-
(1) Completion and acceptance of all work;
(2) Presentation of a properly executed voucher; and
(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 (31 U.S.C.3727 and 41 U.S.C.6305).
(i) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.
(j) Interest computation on unearned amounts. In accordance with 31 U.S.C.3903(c)(1), the amount payable under paragraph (d)(2) of this clause shall be-
(1) Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior to the date the Contractor receives the unearned amount; and
(2) Deducted from the next available payment to the Contractor.
(End of clause)
52.232-27 Prompt Payment for Construction Contracts. (Jan 2017)
As prescribed in 32.908(b), insert the following clause:
Prompt Payment for Construction Contracts (Jan 2017)
Notwithstanding any other payment terms in this contract, the Government will make invoice payments under the terms and conditions specified in this clause. The Government considers payment as being made on the day a check is dated or the date of an electronic funds transfer. Definitions of pertinent terms are set forth in sections 2.101, 32.001, and 32.902 of the Federal Acquisition Regulation. All days referred to in this clause are calendar days, unless otherwise specified. (However, see paragraph (a)(3) concerning payments due on Saturdays, Sundays, and legal holidays.)
(a) Invoice payments-
(1) Types of invoice payments. For purposes of this clause, there are several types of invoice payments that may occur under this contract, as follows:
(i) Progress payments, if provided for elsewhere in this contract, based on Contracting Officer approval of the estimated amount and value of work or services performed, including payments for reaching milestones in any project.
(A) The due date for making such payments is 14 days after the designated billing office receives a proper payment request. If the designated billing office fails to annotate the payment request with the actual date of receipt at the time of receipt, the payment due date is the 14 thday after the date of the Contractor's payment request, provided the designated billing office receives a proper payment request and there is no disagreement over quantity, quality, or Contractor compliance with contract requirements.
(B) The due date for payment of any amounts retained by the Contracting Officer in accordance with the clause at 52.232-5, Payments Under Fixed- Price Construction Contracts, is as specified in the contract or, if not specified, 30 days after approval by the Contracting Officer for release to the Contractor.
(ii) Final payments based on completion and acceptance of all work and presentation of release of all claims against the Government arising by virtue of the contract, and payments for partial deliveries that have been accepted by the Government (e.g., each separate building, public work, or other division of the contract for which the price is stated separately in the contract).
(A) The due date for making such payments is the later of the following two events:
(1) The 30 thday after the designated billing office receives a proper invoice from the Contractor.
(2) The 30 thday after Government acceptance of the work or services completed by the Contractor. For a final invoice when the payment amount is subject to contract settlement actions (e.g., release of claims), acceptance is deemed to occur on the effective date of the contract settlement.
(B) If the designated billing office fails to annotate the invoice with the date of actual receipt at the time of receipt, the invoice payment due date is the 30 thday after the date of the Contractor's invoice, provided the designated billing office receives a proper invoice and there is no disagreement over quantity, quality, or Contractor compliance with contract requirements.
(2) Contractor's invoice. The Contractor shall prepare and submit invoices to the designated billing office specified in the contract. A proper invoice must include the items listed in paragraphs (a)(2)(i) through (a)(2)(xi) of this clause. If the invoice does not comply with these requirements, the designated billing office must return it within 7 days after receipt, with the reasons why it is not a proper invoice. When computing any interest penalty owed the Contractor, the Government will take into account if the Government notifies the Contractor of an improper invoice in an untimely manner.
(i) Name and address of the Contractor.
(ii) Invoice date and invoice number. (The Contractor should date invoices as close as possible to the date of mailing or transmission.)
(iii) Contract number or other authorization for work or services performed (including order number and line item number).
(iv) Description of work or services performed.
(v) Delivery and payment terms (e.g., discount for prompt payment terms).
(vi) Name and address of Contractor official to whom payment is to be sent (must be the same as that in the contract or in a proper notice of assignment).
(vii) Name (where practicable), title, phone number, and mailing address of person to notify in the event of a defective invoice.
(viii) For payments described in paragraph (a)(1)(i) of this clause, substantiation of the amounts requested and certification in accordance with the requirements of the clause at 52.232-5, Payments Under Fixed-Price Construction Contracts.
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision (e.g., 52.232-38, Submission of Electronic Funds Transfer Information with Offer), contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer-System for Award Management, or 52.232- 34, Payment by Electronic Funds Transfer-Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(xi) Any other information or documentation required by the contract.
(3) Interest penalty. The designated payment office will pay an interest penalty automatically, without request from the Contractor, if payment is not made by the due date and the conditions listed in paragraphs (a)(3)(i) through (a)(3)(iii) of this clause are met, if applicable. However, when the due date falls on a Saturday, Sunday, or legal holiday, the designated payment office may make payment on the following working day without incurring a late payment interest penalty.
(i) The designated billing office received a proper invoice.
(ii) The Government processed a receiving report or other Government documentation authorizing payment and there was no disagreement over quantity, quality, Contractor compliance with any contract term or condition, or requested progress payment amount.
(iii) In the case of a final invoice for any balance of funds due the Contractor for work or services performed, the amount was not subject to further contract settlement actions between the Government and the Contractor.
(4) Computing penalty amount. The Government will compute the interest penalty in accordance with the Office of Management and Budget prompt payment regulations at 5 CFR Part 1315.
(i) For the sole purpose of computing an interest penalty that might be due the Contractor for payments described in paragraph (a)(1)(ii) of this clause, Government acceptance or approval is deemed to occur constructively on the 7th day after the Contractor has completed the work or services in accordance with the terms and conditions of the contract. If actual acceptance or approval occurs within the constructive acceptance or approval period, the Government will base the determination of an interest penalty on the actual date of acceptance or approval. Constructive acceptance or constructive approval requirements do not apply if there is a disagreement over quantity, quality, or Contractor compliance with a contract provision.
These requirements also do not compel Government officials to accept work or services, approve Contractor estimates, perform contract administration functions, or make payment prior to fulfilling their responsibilities.
(ii) The prompt payment regulations at 5 CFR1315.10(c) do not require the Government to pay interest penalties if payment delays are due to disagreement between the Government and the Contractor over the payment amount or other issues involving contract compliance, or on amounts temporarily withheld or retained in accordance with the terms of the contract. The Government and the Contractor shall resolve claims involving disputes, and any interest that may be payable in accordance with the clause at FAR 52.233-1, Disputes.
(5) Discounts for prompt payment. The designated payment office will pay an interest penalty automatically, without request from the Contractor, if the Government takes a discount for prompt payment improperly. The Government will calculate the interest penalty in accordance with the prompt payment regulations at 5 CFR Part 1315.
(6) Additional interest penalty.
(i) The designated payment office will pay a penalty amount, calculated in accordance with the prompt payment regulations at 5 CFR Part 1315 in addition to the interest penalty amount only if-
(A) The Government owes an interest penalty of $1 or more;
(B) The designated payment office does not pay the interest penalty within 10 days after the date the invoice amount is paid; and
(C) The Contractor makes a written demand to the designated payment office for additional penalty payment, in accordance with paragraph (a)(6)(ii) of this clause, postmarked not later than 40 days after the date the invoice amount is paid.
(ii)
(A) The Contractor shall support written demands for additional penalty payments with the following data. The Government will not request any additional data. The Contractor shall-
(1) Specifically assert that late payment interest is due under a specific invoice, and request payment of all overdue late payment interest penalty and such additional penalty as may be required;
(2) Attach a copy of the invoice on which the unpaid late payment interest was due; and
(3) State that payment of the principal has been received, including the date of receipt.
(B) If there is no postmark or the postmark is illegible-
(1) The designated payment office that receives the demand will annotate it with the date of receipt provided the demand is received on or before the 40 thday after payment was made; or
(2) If the designated payment office fails to make the required annotation, the Government will determine the demand's validity based on the date the Contractor has placed on the…
This is the start of the file's text. The full file is on GovTribe.