This is a Questions and Answers document for federal contract solicitation W911RX-27-R-A001, issued by a federal agency for footwear fitting and retail services at Fort Riley.
The Q&A addresses key proposal requirements for offerors considering prime contractor arrangements with established local retail subcontractors. Offerors may use a performing retail partner that owns or leases the qualifying storefront and performs all required fitting, footwear selection, fulfillment, and exchanges, provided all proposals comply with Limitations on Subcontracting (FAR 52.219-14) and Sections L&M of the solicitation. Premises documentation need not be in the prime offeror's legal name; rather, the lease and binding agreement between both parties must accompany the proposal. Past-performance references attributed to the retail partner are permissible when clearly attributed to that partner's proposed work, subject to FAR 15.305(a)(2)(iii) compliance. Puncture resistance for safety boots is optional. The Fort Riley origin point for measuring the required 75-mile driving radius is Building 330. Offerors may reproduce the exact ten-CLIN bid schedule in Excel format for Volume III; no official editable workbook is provided. The RFP has not been amended, the question cutoff is November 30, 2026, and submission should be directed to the published contracting contacts. Exhibit A purchase request forms are not required for the solicitation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question 1: May Offeror serve as prime contractor using an established local retail subcontractor that owns or leases the qualifying storefront and performs all required fitting, footwear selection, fulfillment and exchanges?
Answer 1: All Proposals must comply with Limitations on Subcontracting (FAR 52.219-14) and Section L&M of the Solicitation W911RX-27-R-A001
Question 2: Would the retailer’s ownership or lease documentation, together with a signed subcontract or teaming commitment, satisfy this requirement, or must Offeror itself own or lease the premises?
Answer 2: All Proposals must comply with Limitations on Subcontracting (FAR 52.219-14) and Section L&M of the Solicitation W911RX-27-R-A001
Question 3: May the performing retail partner’s relevant past-performance references be submitted when clearly attributed to that partner and its proposed work?
Answer 3: All Proposals must comply with FAR 15.305(a)(2)(iii), and Section L&M of the Solicitation W911RX-27-R-A001
Question 4: Is the Exhibit A purchase request form available to Offerors?
Answer 4: Not required for solicitation.
Question 5: Is puncture resistance (PR) required or optional for the safety boots?
Answer 5: Optional.
Question 6: Q&A 2 A1/A2 refers retail-partner arrangements to FAR 52.219-14 and Sections L/M. Section M Element 1 requires ownership or a fully executed commercial lease. Must that premises documentation be in the prime offeror's legal name, or may a performing retail partner's ownership/lease plus binding commitment satisfy Element 1? If the latter is permitted, which specific documentation must accompany the proposal?
Answer 6: No, it doesn’t have to be in the prime offeror’s legal name. The documentation that must accompany the proposal is the lease and the agreement between the two parties.
Question 7: What Fort Riley origin point and route-measurement method should be used to document the 75-mile driving radius?
Answer 7: The Fort Riley origin point is from building 330.
Question 8: Is an official editable Excel bid schedule available for Volume III? The preserved RFP includes the schedule and requires both PDF and XLSX. If there is no agency workbook, may the offeror reproduce the exact ten-CLIN schedule in XLSX?
Please also identify the intended minimum/maximum IDIQ/order limits where those fields are blank in the RFP.
Answer 8: No, the schedule can be reproduced through Excel.
Question 9: Please identify any later amendment/clarification files and the applicable question cutoff, if any, and confirm the current electronic submission route remains to the published contracting contacts.
Answer 9: The RFP has not been amended, the cutoff is currently November 30, 2026, and the contacts remain the same.
File details come from the government source that posted it. Updated .