Bldg 36 BEP Addendum 01 Summary of Changes.pdf
PDF 203 KB Posted
- Attached to
- Bldg 36 Renovation
- Solicitation number
- W911QY-24-R-0004
About this file
This addendum provides changes to construction documents for the DEVCOM SC Building 36 BEP Renovations project. The renovation work includes demolishing selected walls, furniture, plumbing fixtures, and ceiling components in rooms E166 and E167 to create space for the Bureau of Engraving and Printing. Mechanical, electrical, and security plans have been updated to reflect the removal of these items and realignment of diffusers and ceiling grid. Demolition of sinks, cubicles, work benches, and manufactured walls is specified. The Army Contracting Command at Aberdeen Proving Ground will award a contract for the labor, materials, and equipment to complete this renovation, as described in solicitation number W911QY-24-R-0004.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEVCOM SOLIDIERS CENTER
BUILIDNG 36 BEP RENOVATION
NATICK SOLDIERS CENTER
10 GENERAL GREENE AVENUE
NATICK MA 01760
Addendum 01 Summary of Changes
Line 3 Sheet No. Change
15 February 24
SKA‐100 Remove and dispose of all work benches and shelfing and all associated components in their entirety in room E166 and E167.
SKA‐100 Remove and dispose of all cubicles and all associated components in their entirety.
SKA‐100 Remove and dispose of existing sink and millwork and all associated components in their entirety.
SKA‐100 Remove and dispose of manufactured walls, doors and all associated components in their entirety.
SKA‐101 Demolition reflected ceiling plan has changed to show manufactured wall to be removed.
SKA‐101 Architectural plan changed to show room without walls, furniture and plumbing work.
SKA‐102 Reflective ceiling plan changed to show room without walls and to align new ceiling grid.
SKM‐100 Mechanical demolition plan changed to show room without walls.
SKM‐101 Mechanical plan changed to show new alignment of diffusers.
SKM‐101 Plumbing plan changed to show removal of sink from work and to cap existing lines in new location.