7PW032_SOW.pdf
PDF 477 KB Posted
- Solicitation number
- W911PT-19-R-0014
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W911PT-19-R-0014_0003.pdf | ||
| Combined_Specifications.pdf | ||
| W911PT-19-R-0014_0002.pdf | ||
| W911PT-19-R-0014_0001.pdf | ||
| Photos_of_Manholes_&_Rubber_Boots.pdf | ||
| SITE_VISIT_INFORMATION.pdf | ||
| Drawings.pdf | ||
| NY2WageDetermination.pdf | ||
| W911PT-19-R-0014.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
FOR
Replace 15kV Electrical Cables 1B1 – 1A5
AT
Watervliet Arsenal
Building 135, 136, 125
Project #: 7PW032
Installation Management, Public Works Division
Facilities Engineering (TAWV-IMP-F)
Revision 1
PART 1 GENERAL
1.01 Overview.
A. As part of the Watervliet Arsenal electrical infrastructure maintenance program, the below 15kV underground cables have been identified for replacement as part of a fault repair and other routine phased maintenance.
1. Loop 1 South, Both Parallel Feeders, 1B1 to 1A5 South, approx. distance 3000 ft.
1.02 Scope.
A. This Statement of Work (SOW) defines the effort required for removing and replacement of Loop 1
South, 15kV cable(s) routed underground in parallel pairs per phase through duct bank(s) in the roadways between Building 135, 136 and 125. The cables in scope are connecting substation 1B1, 1B2, 1B3, 1B4, 1B5 and 1A5 sectionalizing switches.
1.03 Existing Conditions.
A. The majority of existing cable on site is Paper Insulated Lead Covered (PILC), 3-conductor cable, 500MCM, routed through underground electrical duct banks & manholes outdoors or through electrical trenches, metal conduit or tray indoors.
B. Work in scope covers 13.2kV Loop 1 parallel feeder cables through 13x outdoor manholes (18-20 &
22-32) covering a distance of approximately 3000 Linear Feet.
C. The concrete encased duct banks leading from manhole to manhole contain either 4 or 5 inch diameter conduits which may be of “Orangeburg”, rigid steel or PVC type construction. Conduits are typically enclosed within #3 & #4 rebar for duct bank reinforcement.
D. Duct banks in scope are mostly beneath roadways which are paved. Roadways consist of approximately 6 inches of asphalt over concrete. Concrete may be up to 8 inches thick (no rebar).
Earth beneath concrete is likely to contain shale. Other utilities and clay drains may also be routed beneath the same roadways. Contractor shall provide a cost per square foot for concrete and/or shale removal under Option 1.
E. Manholes are typically 6-10’ deep. The manholes are frequently half-full or more with accumulated ground water, which will require de-watering each day before entering.
F. Known faulted cable(s) run between substations 1B3 & 1B4 (through MH-23, 25, 26).
G. Manufacturing operations take priority. Any required utility shutdowns may need to be scheduled around operations (i.e. at night or on weekends). Contractor will need to utilize personnel qualified for “hot-work” on 13.2kV cable systems & provide all necessary safety equipment. Any Substation outages require 60-Day prior notice to WVA tenants and should be included in Contractor’s Master
Plan. Execution plan to be reviewed and approved with Government prior to beginning work.
1.04 Contractor Qualifications.
A. Splicing and terminations of cable equal to or greater than 600 volts shall only be performed by a qualified medium voltage technician possessing a “National Cable Splicing Certification Board
(NCSCB) medium voltage personnel certification”. The Contractor shall submit copies of NCSCB certification(s) for Government review and approval prior to splicing or terminating any cable equal to, or greater than 600 volts.
B. Workers who install, splice, terminate or test the cables shall have not fewer than five years of experience working with cables equivalent to those being supplied. Submit a list of workers who will splice and terminate the service entrance cables with documented relevant experience.
C. Installing contractor to use mechanically powered, cable reel rotating equipment, designed for the purpose of installing MV cables through underground conduit and manholes. Also to be utilized;
truck mounted, hydraulically powered equipment designed such that boom reaches into manhole for cable pulling operations.
D. This equipment is required because it efficiently, safely, handles MV cable work in underground applications with reduced chance of damage to newly installed cable. Submit description of such equipment to be utilized for Government review and approval.
1.05 Hours of Operation.
A. Normal duty hours are 7:00 AM through 4:00 PM, Monday through Thursday, and 7:00 AM through
3:00 PM on select Fridays (the arsenal is closed every-other Friday). Federal holidays are non-work days. If a federal holiday falls on a Saturday or Sunday, the preceding Friday or following Monday is a work holiday.
1.06 General Requirements.
A. The contractor shall perform all work in strict conformance with Watervliet Arsenal Instructions for Contractors (WAIC). The contractor shall read and understand this document prior to submitting a proposal. The WAIC is publically available at:
http://www.wva.army.mil/Documents/Contracting/WAIC.pdf
B. The contractor shall supply all tools, materials, supplies, equipment, labor, temporary utilities and supervision necessary for the complete execution of the requirements within the contract documents and requirements of this SOW.
C. The contractor shall, prior to submitting a proposal, review (i) all contract documents, and (ii) the project work site, and shall provide written notice to Contracting Specialist detailing any discrepancies that are found between the contract documents and the project work site.
D. The contractor shall notify the Contracting Specialist a minimum of two (2) business days before the contractor starts work. The contractor shall notify the COR a minimum of seven (7) business days before the shut-down of a utility or building service.
E. The contactor shall clean all work areas, at the end of each work day, to remove all tools, equipment, debris, materials, and all waste from the work site.
1.07 Safety Requirements.
A. General.
1. The contractor shall be responsible for complying with all DOD, Army, Federal, and State health and safety requirements which are applicable to this project, and shall use all means and http://www.wva.army.mil/Documents/Contracting/WAIC.pdf precautions available to ensure the safety of the occupants and protection to the existing buildings and structures.
B. Hazardous Materials.
1. The contractor shall inspect the project work site prior to starting work, and shall request a copy of the asbestos inspection records to verify the location and description of known asbestos-containing materials. The contractor shall sign the “Asbestos Notification
Acknowledgement Record” and submit this form to the Project COR prior to starting project work.
2. If any asbestos-containing materials or other environmental hazards (ex. Oil filled cable or
PCB materials) are unexpectedly discovered or encountered in the work area during construction, work will immediately be stopped & the Project COR will be immediately notified. Work will not continue until the COR can make an abatement determination & notifies the contractor in writing that work can be resumed.
C. Lockout/Tagout Procedures.
1. The contractor is required to provide the proper control of hazardous energy (lockout/tagout) per OSHA 29 CFR 1910.147.
2. The Contractor shall sign and submit a “Lockout/Tagout (LOTO) Notification
Acknowledgement Record” prior to working on or de-energizing any electrical equipment.
D. Contractor Safety Plan.
1. The contractor shall submit a safety plan which is specific to the work activity being performed under the scope of this project for Government review and approval.
1.08 Period of Performance.
A. The contractor shall be required to (i) commence work under this contract within 7 calendar days after the date the contractor receives notice to proceed, (ii) prosecute the work diligently, and (iii) complete the entire work ready for use not later than [120] calendar days after notice to proceed was given. The time stated for completion shall include any required fill & resurfacing of excavated duct banks and final cleanup of the premises.
1.09 Project Schedule.
A. The contractor shall create a project schedule and submit for Government review and approval. The project schedule shall detail the phases of work and the overall timeline for the execution of the work.
The contractor shall include delivery dates, appropriate milestones, and shall clearly detail any requirements for work performed outside of regular hours of operation.
B. The project schedule shall also include target dates for any document deliverables (catalog sheets, test reports, O&M manuals, customer drawings, etc).
C. A preliminary schedule shall be included with Contractor’s initial bid.
1.10 Permits.
A. The Contractor shall obtain the following WVA Permits from the Contracting Officer’s
Representative (COR), IAW the Watervliet Arsenal Information for Contractors (WAIC). The Project
COR will provide the Permit forms and the direction necessary to complete each Permit.
1. Utility Clearance (Dig) Permit
2. Hot Work (Flame) Permit
3. Confined Space Entry Permit
B. The clearance of buried utilities will be performed by the Government in advance of the Contractor performing subsurface work, unless otherwise explicitly stated. The Contractor shall obtain a copy of the completed Utility Clearance Permit (WVA Form 420-2-E) from the COR prior to performing subsurface work.
C. Contractor is responsible to verify existing utility locations as indicated on contract drawings, within area of work.
D. Obtain permit for welding, burning, use of flame, or entry into confined space from WVA Fire
Department by calling (518)266-5990 each day the permit is to be used.
1.11 Contractor’s Equipment.
A. The contractor shall create and affix a label to all large equipment, dumpsters, and other mobilized property, which is weather-resistant (laminated, or within a see-thru label hanger), securely affixed to the equipment or visible through a window, and which clearly displays the General Contractor’s:
1. Company name
2. POC name (first, last)
3. POC phone number
4. Project Number (see title page of SOW)
B. The contractor shall place any waste dumpsters in a manner that does not interfere with thru-traffic.
Place waste dumpsters with a minimum of 33’ clearance from any building. The final location shall be coordinated with, and approved by the COR before any dumpsters are mobilized.
1.12 Project Drawings.
A. The Contractor shall complete the Items of Work in accordance with the following associated Project
Drawing(s), attached to this SOW.
1. SK-1-DJF-20181206-R1: Site Plan
2. SK-2-DJF-20181206-R1: Manhole Plan
3. SK-3-DJF-20181206-R1: General All buried Infrastructure
4. SK-E1 through E5: Duct bank Detail (Typical)
B. The Project Drawings do not indicate each component, device, fastener, fixture, or similar incidental item necessary for the performance of the work. The Contractor shall provide, furnish, and install all necessary and appropriate components, devices, fasteners, fixtures, or similar incidental items as necessary and required to provide complete, operable, and functional system to suit the intended purpose.
C. Project Drawings are illustrative in nature. . Dimensions listed in this document or on any included drawings are approximate point- to- point distances with no allowance for cable terminations, splicing, or racking of cable at perimeter of manholes. The contractor is required to review the project site, and obtain and/or verify all measurements and project data/information required to perform this project work. In addition, the contractor is required to review all contract documents, and provide written notice to Contracting Officer of any discrepancies that are found.
1.13 Project Specifications.
A. The Contractor shall complete the Items of Work in accordance with the following associated Project
Specification(s), attached to this SOW.
1. 26 05 05 - General Provisions for Electrical Systems
2. 26 05 13 - Medium Voltage Cables
3. 26 05 26 - Grounding and Bonding of Electrical Systems
4. 26 05 53 - Identification for Electrical Systems
5. 33 70 02 - Underground Electric Duct Banks
6. 32 12 00 - Paving
7. 03 01 00 – Concrete (Pads, Slabs, Small Jobs)
8. UFC 3-550-01 - Exterior Electrical Power Distribution
9. UFGS 26 05 19.10 – Insulated Wire and Cable
10. UFGS 33 71 02 - Underground Electrical Distribution
1.14 Applicable Codes & References.
A. The following references accompany this Statement of Work and are a part thereof.
1. Watervliet Arsenal Instructions for Contractors (WAIC).
2. NFPA 70 – National Electric Code (NEC)
3. IEEE C2- National Electrical Safety Code
4. ACI 318- Building Code Requirements for Reinforced Concrete
5. AMC Environmental Requirements Supplement
1.15 Submittals.
A. The contractor shall e-mail all submittals to the Contracting Specialist for review and approval. All submittals require government approval unless otherwise explicitly stated.
B. Approved submittals shall only allow the contractor to proceed with the installation and shall not be construed to mean that the contractor has satisfied all requirements of these specifications.
Government approvals shall be obtained, where required, prior to any materials being purchased and/or installed. Proceeding without approvals will be at the Contractor’s own risk – subsequent changes required from approved drawings will then be at the Contractor’s expense.
C. Where a variation/deviation from the Contract Documents exists, the submittal shall include a cover letter providing a list of each variation that the submittal may have from the requirements of the contract documents. In addition the Contractor shall provide specific notation on each shop drawing, sample, catalog cut, data sheet, installation manual, etc. submitted for review and approval, of each such variation.
D. The contractor shall reference APPENDIX A “Consolidated List of Submittals” for complete list of required submittals.
PART 2 PRODUCTS
2.01 General.
A. Unless otherwise stated, all materials for this project shall be new. All products shall not contain any asbestos, mercury, chromium, lead, Class I Freon, and Polychlorinated Biphenyls (PCB), and shall state such on the manufacturer’s original packaging.
B. All work shall be in strict accordance with product manufacturer’s instructions and specifications, including but not limited to manufacturer guidance for storage, staging, application, installation, and disposal of the product.
C. All construction materials shall meet the applicable requirements of the DoD Green Procurement
Program, specifically recycled content products, environmentally preferable products and services, bio-based products, energy-and water-efficient products, alternate fuel vehicles and alternative fuels, products using renewable energy, and alternatives to hazardous or toxic chemicals as found at
<http://www.acq.osd.mil/dpap/cpic/cp/docs/USA001967-08-DPAP.pdf>.
2.02 Products and Materials.
A. Cable:
1. 15kV, MV-105, 500MCM, 1/C, Shielded, Copper, 133% EPR Insulation (AC Power Cable)
B. Conduit:
1. 5” Schedule 80 PVC Pipe, Type E
2. Schedule 80 PVC Couplings and Fittings
C. Concrete:
1. 4000 PSI, Maximum Aggregate Size of ½”
D. Reinforcement:
1. #4 (1/2”) Epoxy Coated Bars, Grade 60 Steel
2. #3 (3/8”) Epoxy Coated Ties, Grade 60 Steel
E. Spacers:
1. Carlon Snap-N-Stac Combo Duct Spacers or pre-approved equivalent
PART 3 ITEMS OF WORK
3.01 General.
A. The Contractor shall complete the Items of Work in accordance with the Project Drawings, attached to this SOW as Appendix [C&D]. The Project Drawings and Specifications do not indicate each component, item, fastener, or similar incidental item necessary for the performance of the Work. The
Contractor shall provide, furnish, and install all necessary and appropriate component, item, fastener, or similar incidental items as necessary and required to provide a complete cable and terminal replacement in the indicated areas. The following Items of Work further clarify and constrain the project execution. Option 1 items are applicable to replacement of unserviceable conduit runs.
3.02 Cable Replacement
A. Contractor shall secure / cordon off work areas, prepare manholes, and identify cables.
1. Pump any ground water that has accumulated within manholes before accessing and working within each manhole. It is assumed and expected that each manhole will have some accumulation of ground water. Manholes shall remain dry during work within them.
2. Suspected hazardous substances must be contained & may not be pumped into local storm drains. COR shall be immediately notified if any sheen or visible oils are discovered in manholes in order to make an assessment prior to continuing work.
3. Government personnel will perform switching operations to ensure that power is taken out of each working manhole. This includes de-energizing and energizing. The Contractor shall not perform switching operations.
4. Identify, verify, and label each cable to be replaced under this scope of work prior to commencing pulling or removing of any cable.
5. Confirm electrical phasing at Substations 1B1, 1B2, 1B3, 1B4, 1B5 & 1A5, and notify the
Project COR that phasing is as expected, or that discrepancies have been found. The use of a
15KV phase meter to check energized lines is required.
6. Inspect duct banks and conduits intended for cable replacement. Identify conduit runs which are still serviceable versus those needing replacement to the COR. The COR shall make final determination on which conduits and/or duct banks shall be replaced. Refer to sections 3.03 &
3.04 for requirements covering duct bank replacement. See attached drawings (SK-1, SK-2, SK-3) for reference. Once non-disclosure agreement is in place, manhole photos can also be provided for review.
B. Contractor shall remove cable and shovel clean manholes and ducts.
1. Identify, verify, and label each cable to be replaced under this scope of work.
2. Pull a minimum 5/16” dia. twisted polypropylene pull rope during cable removal with a minimum of 48” slack at either end.
3. Clean the ducts JUST PRIOR to pulling new cable. In past cable replacements, “OrangeBurge” has degraded after cleaning duct and prevented an otherwise serviceable conduit from use, or required extra splices. Clean by pulling in a mandrel, brush, and trailing burlap. The Project
COR will verify that ducts have been sufficiently cleaned, defined by no excessive debris remaining in the ducts, prior to installation of new cable.
4. Remove abandoned PILC in manholes if necessary. Pull in minimum 5/16 ” dia. poly pull rope allowing 48” slack at each end. Tie Off ends to MH racks.
5. Inspect all cable racks in work scope. Confirm with COR cable racks that are to be re-used in each manhole. Re-install detached cable racks if still serviceable. Replace racks if non-serviceable. Racks shall be spaced approximately 3 to 4.5ft apart horizontally. There shall be at least two racks on each wall. Utilize drop-in anchor kits; 316 stainless steel, ½” -13 thread.
6. Inspect all pulling irons, bare copper neutrals, grounding terminations, and ground rods in each manhole. Clean & repair serviceable items. Replace non-serviceable items. COR shall be notified when complete & will inspect prior to pulling ‘new’ cable in each manhole.
C. Contractor shall install new cable.
1. Factory Testing: Prior to installation, Contractor shall provide COR with results of factory testing for each reel of cable in accordance with specification 26 05 13 & 26 05 19.10.
2. Lead covered cable shall not be used.
3. Cables installed underground shall be listed for use in wet locations & shall comply with NEC
310.10.C. THWN or XHHW insulation shall not be used underground.
4. Furnish and install “Okoguard-Okoseal Okonite” Type MV-105 15kV Shielded Power Cable
(see Specification 26 05 13) or pre-approved equal, using techniques as described by the manufacturer of the cable, ensuring that the maximum pulling tension and sidewall pressure is not exceeded. Install new 4/0 bare annealed, stranded, copper grounding conductor with MV cable runs and connect to existing grounding system with Cad Weld, (refer to section 3.04.E for grounding conductors in new duct bank). Install grounding bushings on MV rigid conduit as required.
a. Contractor shall provide one continuous run of cable between Sub to Sub terminations.
Ensure that manufacturer’s recommend pulling tension and side wall pressure are not exceeded. If local conditions prevent a continuous run, the COR shall be immediately notified. Splices shall not be applied without pre-approval by COR (prior to pulling cable) and shall only be located in manholes.
b. Furnish and install 600A @15kV dead break connectors if splicing is necessary, and mount each dead break connector within manhole as high as possible without causing accessibility, maintenance or other interference issues due to installation location.
Install cable rack(s) as required to adequately support cable and splices. Use glass reinforced polymer components from UnderGround Devices or pre-approved equal. It is requested that contractor provide separate pricing breakout for components/labor to provide this option.
c. The contractor shall “High-Pot” each splice. Cable not spliced by the end of the workday shall be fitted with Raychem #ESC-6/A or equivalent heat shrink end sealing cap to ensure no water infiltration.
d. Terminate new 15kV cables with appropriate Raychem Heat Shrink termination kits.
e. High-Pot entire length of cable upon completion of last splice / termination. The installation shall hold 45kV without breakdown. Govt. Rep to witness test of each conductor and contractor to provide written results of same.
f. Field Tests: The Contractor shall perform additional Visual, Mechanical and Electrical field acceptance checks and tests as specified in UFGS 33 71 02 for MV cables.
g. Conduit Sealing: When installation and testing is complete, cable conduits or raceways which enter from an underground system shall be sealed with an approved sealing compound on the end within a building or electrical enclosure. Compound will be suitable for protecting energized live parts and preventing the ingress of rodents, insects, moisture or gases.
5. Complete cable installations and then wrap all exposed cable (newly installed) in manholes with an approved fire-retardant arc-proofing tape. Secure arc proofing tape with woven Hi-
Temp glass reinforced cloth tape.
6. Re-attach terminations to switchgear after verifying correct phasing.
7. Provide and attach two engraved tags per new cable in each manhole that was accessed.
Manhole tags shall be located at or near both the entry & exit conduit for each cable. Tags shall be placed in an area that is easily readable and as high as is practical within the manhole.
8. One tag per cable shall also be provided at all termination points. Color tape each phase at termination points.
9. At a minimum, each engraved tag provided shall include the following information:
a. Manufacturer
b. Cable size
c. Voltage
d. Cable Route (From-To locations)
e. Loop number
f. Circuit number
g. Phase number
h. Date installed
i. Existing tags, if nomenclature is appropriate, may be used as sample to make new ones.
j. Detailed quantity / nomenclature to be approved by Project COR prior to installation.
10. Also provide and attach engraved tags to existing cables in accessed manholes and termination points.
11. Shovel clean each manhole after completion of work, removing mud, muck, and any other debris and obtain Project COR inspection / approval to close up before completing work in each manhole. Govt Rep will want to photo completed installations in MH and Switch Gear before final closing / re-energization.
12. Install new manganese, sacrificial “Turtle” cathodic protection in each manhole to replace existing spent one.
D. Contractor shall arrange to have MV cable installations acceptance tested by 3rd party per specification 26 05 13 & UFGS 33 71 02. Acceptance Test Report(s) shall be provided to COR for each cable. Notice for testing shall be given in advance to allow project COR and Government
Personnel to witness test.
E. Contractor shall properly dispose of the removed cable.
1. The ends of removed PILC cable shall be sealed to prevent leakage of oil on pavement, and any associated Pot Heads sealed to prevent leakage. Processing of cable will be done on double layer of 6 mil polyethylene sheeting. The contractor shall cut lead cable into 3’ lengths and stack into metal drums ½ full and secure covers.
2. The drums, liners, and absorbent will be provided by the Government. The Government will dispose of lead cable filled drums.
3. Government reserves option to negotiate with contractor to dispose of scrap PILC cable. If contractor arranges for scrap dealers dumpster to be used to remove scrap PILC, dumpster to be lined with 6 mil poly before filling with PILC. Dumpster to be adequately covered so no rainwater accumulates in dumpster. Have set up approved by COR. Remove dumpster when full.
4. Where cable “Potheads” are removed, “Potheads” & cable to be wrapped with poly and taped to prevent leakage. Deliver to B-145 storage area as directed by COR.
F. Contractor shall turn over all excess new material to Government. Deliver material to Building 120 loading dock or other on site location directed by COR. Government shall reserve option to claim any original material/equipment before disposal by contractor. Contractor will deliver salvaged material to on site location specified by COR.
G. Cleanup. The Contractor shall cleanup project area at the end of each work day, and at the end of project work. At the end of the project, contractor shall clean up and remove all debris, materials, tools and equipment generated or used on the project. COR to shall be notified when complete and inspect for compliance prior to close-out of project. Contractor will redress any items deemed non-compliant by the COR.
3.03 Excavation. (Option 1)
A. Contractor shall provide a cost per linear foot for replacing Duct Bank under Option 1. Contractor shall consider all elements of the specified Existing Conditions (Section 1.03), Excavation (Section
3.03), and New Duct Bank (Section 3.04) in generating Contractor’s estimate.
B. Existing underground utilities shown on the contract drawings have been determined by standard surveying methods and available records. Neither the exact location nor the information of these existing utilities is guaranteed to be complete or correct.
C. All work shall be accomplished in a way that minimizes impact on vehicle traffic.
D. The contractor shall maintain a safety perimeter around the construction zone at all times. Contractor is responsible for maintaining site barricades and work site security.
E. The government will provide pavement markings for any underground utilities. No cutting or digging shall occur prior to completion of the Dig Permit.
F. The contractor shall use reasonable care to avoid damaging underground utilities. Contractor shall plan the excavation so as to avoid damage or to minimize interference with the underground utilities in or near the work area.
G. The contractor shall comply with all applicable federal and state safety regulations.
H. The contractor shall protect and preserve the staking, marking, or other designation of underground utilities until no longer required for proper and safe excavation.
I. The contractor shall notify the Project COR directly if an underground utility is not found where one has been marked or if an unmarked underground utility is found. Following this notification, the contractor may continue work if the excavation can be performed without damaging the utility.
J. The contractor shall have an observer to assist the equipment operator when operating excavation equipment around known underground utilities.
K. The contractor shall support and protect exposed underground utilities from damage.
L. The contractor shall notify the Project COR immediately after discovering or causing damage to underground utilities. All breaks, leaks, nicks, dents, gouges, grooves, or other damage shall be reported and repaired.
M. Excavated material may be reused for final backfill; however, any remnants of shale, brick or pavement shall be removed and discarded.
N. The contractor shall protect all utilities from damage when backfilling an excavation. Trash, debris, or other material that could damage or interfere with the accuracy of future locating shall not be buried in the excavation.
O. The contractor shall remove all excess clean soil from the Arsenal at the end of the project. Any environmentally contaminated/hazardous soil/materials will be placed on two (2) layers of six (6) mil polyethylene, covered with one (1) layer of six (6) polyethylene, batted down and labeled by the contractor. The Arsenal will test and dispose of environmentally contaminated/hazardous soil/materials.
3.04 New Duct Bank. (Option 1)
A. Contractor shall provide a cost per linear foot for replacing Duct Bank under Option 1. Contractor shall consider all elements of the specified Existing Conditions (Section 1.03), Excavation (Section
3.03), and New Duct Bank (Section 3.04) in generating Contractor’s estimate.
B. Contractor will coordinate with COR to inspect cable routes & conduits intended for cable replacement. Contractor shall recommend to COR which conduits are serviceable – COR will make final determination if a conduit shall be used. If sufficient numbers of conduits are not serviceable for new cable run(s), a new duct bank shall be provided.
C. For duct banks requiring replacement as approved by the COR, the contractor shall remove and replace existing duct bank in accordance with Specification 33 70 02 – Underground Electric Duct
Banks (attached). See attachments SK-E1 through E5 for additional duct bank requirements & typical configurations.
D. The contractor shall saw cut along the path of the existing duct bank. Duct bank routing shown on the attached site plan drawing (SK-1) is approximate. Contractor shall redirect duct bank as required to complete the run.
E. The entire run from manhole to manhole shall be excavated, graded, and prepped prior to installing new duct. Bottom of trench shall achieve 85% to 95% of maximum dry density prior to concrete placement.
F. The contractor shall construct new duct bank with the number and size of ducts as shown on the attached detail drawing (SK-E1 through E5). Contractor shall run conduit in straight lines except where a change in direction is necessary.
G. Where new duct bank is installed, Contractor shall provide new station grounding conductor (4/0 bare annealed, stranded, copper) imbedded in concrete along with new conduit run(s) per attached detail drawing (SK-E1 through SK-E5). Imbedded ground conductor shall be terminated at existing grounding locations on each end. Grounding terminations shall conform to requirements of specification 26 05 26. This supersedes ground conductor routing cited in clause 3.02.C.3 of this specification.
H. Any Contractor installed duct banks shall include 25% spare conduits (minimum of two) in each duct bank. Spare conduits shall include pull rope with label indicating “From-To” manhole locations, and be suitably sealed to prevent ingress of vermin, water and debris.
I. The contractor shall provide concrete for encasement of underground duct with 4,000 psi minimum 28 day compressive strength. Concrete shall be allowed to cure a minimum of seven (7) days prior to backfill.
1. Concrete encasement surrounding the bank must be rectangular in cross-section and must provide at least three (3) inches of concrete cover for ducts.
2. Contractor shall separate conduits by a minimum concrete thickness of three (3) inches.
3. Prior to pouring concrete, contractor shall anchor duct bank assembly to prevent the assembly from floating during concrete pouring. Anchoring must be done by driving reinforcing rods adjacent to the duct spacer assembly and attaching rods to the spacer assembly.
4. Concrete shall not be placed when the temperature drops below 40° F unless approval is given in writing. Provisions must be made to protect the concrete from freezing during the entire curing period.
5. Placement temperature of concrete shall not exceed 85° F (unless an approved retarder is used). Provisions shall be made to maintain the temperature below this specified level.
6. Concrete shall be protected against loss of moisture and rapid temperature change for at least 7 days after placement. Fresh concrete shall be protected from rain and flowing water until hard.
All equipment required for protection must be on hand prior to placing the concrete.
7. Concrete shall be properly cured in accordance with ACI 308.1. Contractor shall use an appropriate curing method which satisfies the physical project conditions and exposure temperature. All concrete work shall be in accordance with the established procedures as set forth by the American Concrete Institute (ACI).
J. The contractor shall furnish and install continuous steel reinforcing along the entire concrete pour.
Reinforcing steel includes top and bottom longitudinal steel as well as transverse ties.
K. Conduits shall be kept clean of concrete, dirt, or foreign substances during all phases of construction.
L. Duct bank envelope connecting to existing underground structures shall be flared to have enlarged cross-section at the manhole entrance to provide additional shear strength.
1. Perimeter of the duct bank opening in the underground structure shall be flared toward the inside or keyed to provide a positive interlock between the duct and the wall of the structure.
M. Where duct lines are removed from existing underground structures, contractor shall close the openings to waterproof the structure. Contractor shall chip out wall opening to provide a key for the new section of wall.
N. The contractor shall seal all electrical penetrations for radon mitigation, maintaining integrity of the vapor barrier, and to prevent infiltration of air, insects, and vermin.
O. When installation is complete, contractor shall restore paved surface back to original elevation and condition any surfaces disturbed during installation of duct bank.
1. Where trenches, pits, or other excavations are made in existing roadways and other areas of pavement, contractor shall restore surface treatment or pavement to the same thickness and in the same kind as previously existed, except as otherwise specified.
2. Contractor shall follow WVA Specification 32 12 00 and Specification 03 01 00 for restoring paving and concrete.
PART 4 CLOSE OUT REQUIREMENTS
4.01 Cleanup of Work Site.
A. The contactor shall clean all work areas and remove all tools, equipment, debris, materials, and all waste from the premises.
B. The contractor shall remove all debris from any remote holding locations, to include any excavation and concrete equipment chute cleanout debris.
C. The contractor shall remove their equipment from Watervliet Arsenal premises within five (5) working days after completion of project work.
4.02 Final Repairs and Restoration to Work Site.
A. The contractor is responsible to restore any surfaces affected by construction to their original condition. This shall include repair of any building surfaces, walkways, road surfaces, equipment or miscellaneous items which were damaged during the execution of this SOW. Items that cannot be repaired to restore original function or aesthetics shall be replaced in kind by the Contractor at no additional charge to the Government.
B. Grass, trees, and other vegetation affected by project work shall be restored to same or better condition as existed prior to the start of project work. The Contractor shall prepare the affected areas to eliminate uneven areas and low spots. Remove foreign materials, weeds, and damaged soil. The
Contractor shall scratch the area to a depth of three (3) inches where topsoil is to be placed. Spread topsoil to a uniform, compacted depth of less than five (5) inches over areas to be reseeded. Rake until smooth. The Contractor shall seed, fertilize, and water the area to establish grass.
4.03 As-Built Drawings.
A. The Contactor shall provide professional ‘As-Built’ drawings detailing updated cable layout & installation information for the area of construction. Update shall include ‘new’ products and materials provided in Contractor’s scope, as well as existing products materials left in place in order to provide a complete picture of what is routed through each manhole upon project completion.
B. The government shall provide base CAD file to be used for Contractor’s update.
C. Revised drawing information shall include but not be limited to the following;
1. Duct Bank Locations & lengths
2. Manhole locations
3. Section switch locations
4. Substation locations
5. Loop designations
6. Duct Run Quantity/Diameter
7. No. of ducts used
8. No. of spare ducts
9. No. of conductors in each conduit & conductor sizes
D. Drawings shall be provided in both CAD & PDF format.
PART 5 APPENDICES
5.01 Purpose.
A. Consolidated List of Submittals
B. Quality Assurance Surveillance Plan (QASP)
C. AMC Environmental Requirements Supplement
D. SK-1-DJF-20181206: Site Plan
E. SK-2-DJF-20181206: Manhole Plan
F. SK-3-DJF-20181206: General All Buried Infrastructure
G. SK-E1 through E5: Duct Bank Detail
H. 26 05 05 – General Provisions for Electrical Systems
I. 26 05 13 – Medium Voltage Cables
J. 26 05 26 – Grounding and Bonding of Electrical Systems
K. 33 70 02 – Underground Electric Duct Banks
L. UFGS 33 71 02 – Underground Electrical Distribution
M. UFGS 26 05 19.10 – Insulated Wire & Cable
N. UFC 3-550-01 – Exterior Electrical Power Distribution
APPENDIX A: Consolidated List of Submittals
Line Item Submitted Submittal Needed By Submittal Reviewed By (Office)
1 Safety Data Sheets for Hazardous Materials
(SDS)
NLT 7 Calendar
Days After Award
Safety Office
2 Signed Contractor Asbestos Notification Form NLT 7 Calendar
Days After Award
Environmental Office
3 Signed Lockout/Tagout (LOTO) Notification
Acknowledgement Record
NLT 7 Calendar
Days After Award
Safety Office
4 Project Schedule NLT 7 Calendar
Days After Award
COR
5 Contractor Safety Plan (1.05.A.) NLT 7 Calendar
Days After Award
Safety Office
6 PVC Pipe and Fittings Product Data NLT 7 Calendar
Days After Award
COR
7 Cable Product Data (Catalog Sheet)
Fire / Arc Retardant Tape Product Data
NLT 7 Calendar
Days After Award
COR
8 Conduit Spacer Product Data NLT 7 Calendar
Days After Award
COR
9 Concrete Mix Data NLT 7 Calendar
Days After Award
COR
10 Cable Nameplate (Tag) Drawing NLT 14 Calendar
Days After Award
COR
11 Cable Pulling Equipment Data NLT 14 Calendar
Days Prior to
Construction
COR
12 MV Technician NCSCB Certifications and
Equivalent Experience List (5yrs)
NLT 14 Calendar
Days Prior to
Construction
COR
13 Manufacturer’s Factory Test Reports(Each Reel) NLT 7 Calendar
Days Prior to
Construction
COR
14 3rd Party Cable Installation Acceptance Test
Reports (Each Cable)
NLT 7 Calendar
Days After Test
COR
15 As-Built Drawing(s) – CAD & PDF NLT 14 Calendar days After
Construction is
Completed
COR
16 Bills of Lading, Dump Slips for C&D Debris and
Recycled Materials
Before Closeout Environmental Office
APPENDIX B: Quality Assurance Surveillance Plan (QASP)
PURPOSE
This Quality Assurance Surveillance Plan (QASP) will be used as a guide to Government Quality Assurance
Personnel (QAP). It provides a systematic method to evaluate the services the contractor is required to furnish.
SURVEILLANCE PROCEDURES
Timeliness: Progress is maintained to assure compliance with completion time.
Quality: Conformance with statement of work and industry standards.
Tasks: Performed according to statement of work requirements.
Problem Resolution: Contractor submits deliverables in accordance with the contract and resolves any deficiencies identified by the government in the final submission. Following final submission, contractor resolves any additional deficiencies identified by the government and resubmits and or corrects within one week.
Delivery: Contractor submits each deliverable in accordance with the statement of work and terms of the contract.
PERFORMANCE AREAS
Management Responsiveness: Evaluate the adequacy of the contractor’s responsiveness and their ability to keep the government informed of work progress and provides for early problem identification and effective corrective action plans.
Schedule Control: Evaluate the contractor’s adherence to completion schedule.
Performance: The contractor will be evaluated as to the workmanship and adherence to the statement of work.
EVALUATION CRITERIA
(Outstanding). Indicates performance clearly exceeds contractual requirements. The area of evaluation contains few minor problems for which corrective actions appear highly effective.
(Satisfactory). Indicates performance clearly meets contractual requirements. The area of evaluation contains some minor problems for which the corrective actions appear satisfactory.
(Unsatisfactory). Indicates the contractor failed to satisfy contractual requirements and recovery is not likely in a timely manner. The area of evaluation contains serious problems for which the corrective actions were ineffective.
DOCUMENTATION
Documentation used to perform surveillance will consist of random government inspections and inspection records, as well as the evaluation of final work product delivery by the project COR/COTR.
RATING
Contractor will be given an overall rating of Outstanding, Satisfactory, or Unsatisfactory by the Government
Technical point of contact or Contracting Specialist Representative, if appointed, 3 using the above evaluation criteria.
APPENDIX C: AMC Environmental Requirements Suppliment
1. Compliance with Environmental Laws and Regulations: Contractor shall comply with all applicable federal, state, and local environmental laws, statutes, regulations, executive orders, permits, Army regulations (with supplements), as well as Major Subordinate Command (MSC) and installation regulation, policy, Host Tenant
Agreement, Interagency Service Support Agreement, or Status-of-Forces Agreement. Contractor shall immediately report any conflicts between applicable federal, state, local environmental laws, statutes, executive orders, and provisions of Army Regulation 200-1, and any specifications within this contract to the Contracting Officer
Representative (COR).
2. Compliance with Green Procurement Requirements: Contractor shall follow Federal EPA Comprehensive
Procurement guidelines (www.epa.gov/cpg) and Army Contracting Command Quick Guide
(https://acc.aep.army.mil/accapps/ACCMAP/Documents/Quick-Guide-for-Sustainable-Procurement.docx) for acquisition of building materials and products and select materials that have a long life cycle; the least toxic materials; recyclable materials; materials that are resource-efficient; materials with the maximum recycled content;
materials harvested on a sustained yield basis; and products causing the least pollution during their manufacture, use, and reuse.
3. Compliance with License and Certification Requirements: Contractor shall obtain all license and certification required by Federal, State, and Local environmental laws and regulations necessary to adhere to the specifications of this contract. The Contractor shall submit all plans, notifications, reports, submittal documents, and fees required by
Federal, State, and Local environmental laws and regulations to the appropriate Federal, State, and Local authority and/or agency as necessary to adhere to the specification of this contract. All required licenses and certifications required by Federal, State, and Local environmental laws and/or regulations shall be considered a contract deliverable upon award.
4. Notification of Federal and State Regulators: Contractor shall immediately notify the Designated Government
Representative (DGR) and COR of the arrival on site of any Federal, State, and/or DoD environmental regulator or enforcement agent and/or the receipt of any correspondence from a Federal or State environmental agency.
5. Inspections of Work Sites: Contractor shall submit to potential Federal, State, Army and installation work site environmental regulatory inspections and/or investigations into noncompliance, and fully cooperate with such inspections/investigations by providing the appropriate records and documentation. Environmental regulatory agencies are authorized by law to inspect any work site for environmental compliance with regulatory requirements.
If an inspection is conducted, it will not stop or disrupt ongoing contract activities. The inspection will only require the work site environmental officer, or supervisor/manager to answer questions and/or escort the inspector to specific work site areas with the potential to affect environmental quality.
6. Reporting Noncompliance: Contractor shall immediately report any nonconformance and/or noncompliance with applicable Federal, State or Local environmental laws, Army and installation environmental regulations or policies to the COR and DGR.
7. Verification of National Environmental Policy Act Documents: Contractor shall obtain from the COR or
DGR, a copy of AMC's National Environmental Policy Act Policy and 32 CFR 651 which addresses actions to be taken by contractor. These documents include but is not limited to the analysis-associated decision document of an
Environmental Impact Statement and Record of Decision; Environmental Assessment and Finding of No Significant
Impact or Notice to Proceed; or Record of Environmental Consideration on the proposed contract actions prior to commencement of such actions.
8. Conformance with Environmental Management System: Contractor shall take the necessary actions to identify, monitor, and control those contract operations and activities that pose risk of contamination, or can negatively impact the natural and/or human environment.
9. Assignment of Environmental Compliance Designee (ECD): Contractor shall appoint an ECD for all contract work periods exceeding 180 consecutive days. Contractor shall appoint a primary and alternate ECD for each production, shop or work area that uses and/or stores hazardous materials and/or generates hazardous wastes.
Contractor ECDs shall monitor implementation of all environmental regulatory requirements, report all environmental noncompliance to the work site supervisor, correct all environmental noncompliance, and verify implementation of directed actions to correct identified environmental noncompliance. Contractor shall have at least one ECD on duty at all times at each shop or work area. Contractor shall require all personnel designated as ECDs to complete the initial ECD training through the installation or Major Subordinate Command (MSC) environmental compliance point of contact within 15 days of the start of contract performance. Contractor personnel appointed as
ECDs may perform other duties provided they do not prevent the performance of ECD duties. Contractors may request a waiver of this requirement through the COR and DGR, if using and/or storing very small quantities of hazardous materials.
10. Competency Training for Contractor Personnel: Contractor shall not allow personnel to perform any activities and/or tasks on AMC installations without proper and adequate qualifications or job competency training.
In the event of any identified noncompliance, the Contractor shall, if requested, provide proof of contract personnel training or qualification (individual name, training/qualification type, training/qualification certificate, and date of training/qualification) to perform those contract activities associated with the identified noncompliance.
11. Generation of Solid Waste: Contractor shall remove from the installation and dispose of all solid waste generated, which cannot be recycled to an approved and permitted off-post disposal facility.
11.1. Contractor shall make every effort to divert construction, demolition debris, and all other solid waste to comply with the Army Integrated Solid Waste Management Policy.
11.2. The Contractor shall establish a program to promote cost-effective waste reduction in all operations and facilities covered by the contract. This includes collection, separation, and processing products or other materials recovered from solid waste streams for use in the form of raw materials.
11.3. The Contractor shall make maximum effort to reduce and prevent waste.
11. 4. The Contractor shall establish a program to promote cost-effective waste reduction in all operations and facilities covered by the contract. This includes collection, separation, and processing products or other materials recovered from solid waste streams for use in the form of raw materials.
11. 5. The Contractor shall make maximum effort to reduce and prevent waste.
13. Use of Hazardous Materials: Contractor shall assign all hazardous materials management responsibilities to the appointed ECD. Contractor shall contact the DGR or COR to obtain technical assistance from Environmental Office for assisting the ECD with achieving and maintaining compliance with hazardous material storage, issue, use, and disposal requirements. Contractor shall submit to the COR and/or DGR a hazardous material inventory. The hazardous material inventory will be submitted 30 days prior to commencement of work for contracts that exceed
180 consecutive days. The inventory list will contain the hazardous material type and maximum quantities of materials anticipated to be stored on-site. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. The Contractor shall maintain copies of Safety Data Sheets for all hazardous materials used and stored on-site during performance of the contract. Contractor shall not supply or deliver any hazardous materials or chemicals to an installation that are listed on EPA toxic chemical list without prior written approval from DGR and/or COR.
18. Prevention of Spills: Contractor shall adopt the installation's Spill Prevention Control and Countermeasures
Plan (SPCC) if transporting, processing, storing, or in any way managing hazardous waste, hazardous material, petroleum-oils-lubricants, or other restricted items.