APPENDIX A
Bid Schedule
The following pricing shall be included in your proposal for base year plus four (4) option years.
i. Fire Alarm Inspections Post Wide DLA CLIN 0001 Base $_________________ CLIN 0002 $_________________ CLIN 0009 Option 1 $_________________ CLIN 0010 $_________________ CLIN 0017 Option 2 $_________________ CLIN 0018 $_________________ CLIN 0025 Option 3 $_________________ CLIN 0026 $_________________ CLIN 0033 Option 4 $_________________ CLIN 0034 $__________________
ii. Sprinkler & Pump Inspections Post Wide DLA CLIN 0003 Base $__________________ CLIN 0004 $_________________ CLIN 0011 Option 1 $__________________ CLIN 0012 $_________________ CLIN 0019 Option 2 $__________________ CLIN 0020 $_________________ CLIN 0027 Option 3 $__________________ CLIN 0028 $_________________ CLIN 0035 Option 4 $__________________ CLIN 0036 $_________________
iii. Remediation/Maintenance of Fire Alarms, Sprinklers and Pumps:
The contractor shall provide with proposal an hourly rate solely for evaluation purposes.
CLIN 0005 Base Labor Rate Per Hour $__________ NTE $50,000.00 total for post wide and DLA.
CLIN 0013 Option 1 Labor Rate Per Hour $__________ NTE $50,000.00 total for post wide and DLA.
CLIN 0021 Option 2 Labor Rate Per Hour $__________ NTE $50,000.00 total for post wide and DLA.
CLIN 0029 Option 3 Labor Rate Per Hour $__________ NTE $50,000.00 total for post wide and DLA.
CLIN 0037 Option 4 Labor Rate Per Hour $__________ NTE $50,000.00 total for post wide and DLA.
iv. Emergency Repairs/Work on Fire Alarms, Sprinklers and Pumps:
The contractor shall provide with proposal an hourly rate solely for evaluation purposes.
CLIN 0006 Base Labor Rate Per Hour $__________ NTE $50,000.00 total for post wide and DLA.
CLIN 0014 Option 1 Labor Rate Per Hour $__________ NTE $50,000.00 total for post wide and DLA.
CLIN 0022 Option 2 Labor Rate Per Hour $__________ NTE $50,000.00 total for post wide and DLA.
CLIN 0030 Option 3 Labor Rate Per Hour $__________ NTE $50,000.00 total for post wide and DLA.
CLIN 0038 Option 4 Labor Rate Per Hour $__________ NTE $50,000.00 total for post wide and DLA.
v. Spare Parts:
Spare parts shall be provided to the Government for actual cost. Receipts shall be requested.
Not to Exceed (NTE) CLIN 0007 Base NTE $50,000.00 total for post wide and DLA.
CLIN 0015 Option 1 NTE $50,000.00 total for post wide and DLA.
CLIN 0023 Option 2 NTE $50,000.00 total for post wide and DLA.
CLIN 0031 Option 3 NTE $50,000.00 total for post wide and DLA.
CLIN 0039 Option 4 NTE $50,000.00 total for post wide and DLA.
APPENDIX A
Bid Schedule
The following pricing shall be included in your proposal for base year plus four (4) option years.
vi. Service Contract Reporting:
CLIN 0008 Base $__________________ CLIN 0016 Option 1 $__________________ CLIN 0024 Option 2 $__________________ CLIN 0032 Option 3 $__________________ CLIN 0040 Option 4 $__________________
PROJECT’S GRAND TOTAL $_______________________.
END OF APENDIX A