SEE SCHEDULE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this Amendment is:
1 To add the location for the cutting system draw ing's for buliding 5 and building 456 as Attachment 11 and 12 respectively.
2. To answ er vendor questions about the solicitation.
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Apr-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911KF18Q0030
X 9B. DATED (SEE ITEM 11)
26-Mar-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Apr-2018
CODE
ARMY CONTRACTING COMMAND - WARREN (ANAD)
HEATHER GLOVER
7 FRANKFORD AVENUE
ANNISTON AL 36201
W911KF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911KF18Q0030
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
ANSWERS TO QUETIONS
Question: 5 Apr 2018: I’m working on completing this solicitation and had a question about Item 0003 page 24. This is a little different than the last solicitation I completed for ANAD. Is this the same as the previous request for “install & training” cost? Or is it asking for electrical and rigging subcontract cost as well?
Answer: The contract Manpower reporting is a report that is submitted that reports the direct labor hours (including Subcontractors); (6) direct labor dollars paid this reporting period (including Subcontractors); the report is completed once a year and submitted on the following websites: https://cmra.army.mil/.
Question: 10 Apr 2018. Section 4.0 testing. The section implies testing at origin prior to acceptance- is this correct? Will these tests be performed again at destination after installation?
Answer: Testing will be performed at destination after installation only.
Question: 11 Apr 2018. On page 7 of attachment 1 (statement of work) section 5.2 installation- It states we are to supply a floor plan drawing- It says drawing PMD 0330 and PMD 03329 are attached. I do find them nor do I find them on FBO.
Answer: Amendment W911KF 18-Q-0039-P0001 provides drawing PMD 0330 and PMD 03329.
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
TABLE OF CONTENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 STATEMENT OF
WORK
26-MAR-2018
Attachment 10 DD Form 1664 Data Item Description
26-MAR-2018
Attachment 2 Evidence of Authority To Sign Offers
26-MAR-2018
Attachment 3 EPA Guideline Items 26-MAR-2018
W911KF18Q0030
Attachment 4 Contractor Request for Waiver Non-EPA Items
26-MAR-2018
Attachment 5 Contractor Affirmative Procurement Report
26-MAR-2018
Attachment 6 Past Performance Questionnaire
26-MAR-2018
Attachment 7 Request for Technical Literature
26-MAR-2018
Attachment 8 Wage Determination 26-MAR-2018 Attachment 9 DDForm 1423 Contract
Data Requirement List to:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 STATEMENT OF
WORK
26-MAR-2018
Attachment 10 DD Form 1664 Data Item Description
26-MAR-2018
Attachment 11 PMD-03329 Proposed Location BLDG 456
12-APR-2018
Attachment 12 PMD-03330 Proposed Location BLDG 5
12-APR-2018
Attachment 2 Evidence of Authority To Sign Offers
26-MAR-2018
Attachment 3 EPA Guideline Items 26-MAR-2018 Attachment 4 Contractor Request for
Waiver Non-EPA Items
26-MAR-2018
Attachment 5 Contractor Affirmative Procurement Report
26-MAR-2018
Attachment 6 Past Performance Questionnaire
26-MAR-2018
Attachment 7 Request for Technical Literature
26-MAR-2018
Attachment 8 Wage Determination 26-MAR-2018 Attachment 9 DDForm 1423 Contract
Data Requirement List