ID Ta Mo

Task Name Duration Actual Start Actual Finish % Complete

Start Finish Predecessors Successors Status

1 FTG251 - Maintenance Support Facility (DBB)(P2 501568) 1699 days? Tue 7/31/18 NA 35% Tue 7/31/18 Mon 2/3/25 Late

2 FUNDING 858 days? Wed 10/20/21 NA 86% Wed 10/20/21 Mon 2/3/25 On Schedule

11 PROGRAMMING 1402 days? Tue 7/31/18 NA 2% Tue 7/31/18 Wed 12/13/23 Late

38 PLANNING & DESIGN 1553 days Tue 7/31/18 NA 39% Tue 7/31/18 Thu 7/11/24 Late

39 Survey (CEPOA) 137 days Thu 3/17/22 NA 78% Thu 3/17/22 Fri 9/23/22 Late

44 Geotechnical (Geotek Alaska, Inc.) 1118 days Tue 7/31/18 NA 54% Tue 7/31/18 Thu 11/10/22 Late

54 A-E TO Procurement 381 days Thu 3/17/22 Thu 8/31/23 100% Thu 3/17/22 Thu 8/31/23 Complete

68 AE Design 407 days Wed 12/21/22 NA 10% Wed 12/21/22 Thu 7/11/24 Late

69 Design Charrette Prep 25 days Wed 12/21/22 Tue 1/24/23 100% Wed 12/21/22 Tue 1/24/23 67 70 Complete

70 Design Charrette (Fort Greely, AK) 3 days Tue 1/24/23 Thu 1/26/23 100% Tue 1/24/23 Thu 1/26/23 69,7 71,76 Complete

71 Design Charrette Prepare Draft Report 18 days Fri 1/27/23 Tue 2/21/23 100% Fri 1/27/23 Tue 2/21/23 70 74,73,72 Complete

72 Design Charrette Submit Draft Report 1 day Wed 2/22/23 Wed 2/22/23 100% Wed 2/22/23 Wed 2/22/23 71 73 Complete

73 Design Charrette Gov't Review 10 days Thu 2/23/23 Wed 3/8/23 100% Thu 2/23/23 Wed 3/8/23 71,72 74 Complete

74 Design Charrette Prepare Final Report 9 days NA NA 0% Thu 3/9/23 Tue 3/21/23 71,73 77,75 Future Task

75 Design Charrette Submit Final Report 1 day NA NA 0% Wed 3/22/23 Wed 3/22/23 74 77 Future Task

76 15% OTS AE Prepares Design 41 days NA NA 0% Fri 1/27/23 Fri 3/24/23 70 77 Late

77 35% AE Prepares Design 58 days NA NA 0% Mon 3/27/23 Wed 6/14/23 74,75,76 78 Future Task

78 35% Design Submission (ML110) 0 days NA NA 0% Wed 6/14/23 Wed 6/14/23 77 79SF+5 days,81,80 Future Task

79 35% Cost Estimate Submission 0 days NA NA 0% Wed 6/21/23 Wed 6/21/23 78SF+5 days 82,26 Future Task

80 35% Design Gov't Review Period 12 days NA NA 0% Thu 6/15/23 Fri 6/30/23 78 81 Future Task

81 35% AE Annotated Comments 5 days NA NA 0% Mon 7/3/23 Fri 7/7/23 78,80 82 Future Task

82 35% Design Review Meeting (Fort Greely, AK) 5 days NA NA 0% Mon 7/10/23 Fri 7/14/23 81,79 96,85,83SS+20 days Future Task

83 Value Engineering Study (JBER, AK) (ML285/ML290) 4 days NA NA 0% Mon 8/7/23 Thu 8/10/23 82SS+20 days 96SS Future Task

84 DCA Assessment 107 days NA NA 0% Mon 7/17/23 Tue 12/12/23 Future Task

96 65% AE Prepares Design 75 days NA NA 0% Mon 8/7/23 Fri 11/17/23 82,43,53,83SS 98FS+5 days,97 Future Task

97 65% Design Submission 0 days NA NA 0% Fri 11/17/23 Fri 11/17/23 96 99 Future Task

98 65% Cost Estimate Submission 0 days NA NA 0% Fri 11/24/23 Fri 11/24/23 96FS+5 days 99FF Future Task

99 65% Design/BCOE Review 10 days NA NA 0% Mon 11/20/23 Fri 12/1/23 97,98FF 100 Future Task

100 65% AE Annotated Comments 5 days NA NA 0% Mon 12/4/23 Fri 12/8/23 99 101 Future Task

101 65% Design Review Conference 5 days NA NA 0% Mon 12/11/23 Fri 12/15/23 100 102 Future Task

102 95% AE Prepares Design 100 days NA NA 0% Mon 12/18/23 Fri 5/3/24 101 103 Future Task

103 95% Design Submission 0 days NA NA 0% Fri 5/3/24 Fri 5/3/24 102 104FS+5 days,105 Future Task

104 95% Cost Estimate Submission 0 days NA NA 0% Fri 5/10/24 Fri 5/10/24 103FS+5 days 105FF Future Task

105 95% Design Review Period 10 days NA NA 0% Mon 5/6/24 Fri 5/17/24 103,104FF 106 Future Task

106 95% AE Annotated Comments 5 days NA NA 0% Mon 5/20/24 Fri 5/24/24 105 107 Future Task

107 95% Design Review Conference 5 days NA NA 0% Mon 5/27/24 Fri 5/31/24 106 108 Future Task

108 100% AE Annotated Comments 20 days NA NA 0% Mon 6/3/24 Fri 6/28/24 107 109 Future Task

109 100% Design Submission (IDaC Production Point) 0 days NA NA 0% Fri 6/28/24 Fri 6/28/24 108 110,111 Future Task

110 BCOE Review and Back Check 9 days NA NA 0% Mon 7/1/24 Thu 7/11/24 109 111 Future Task

111 RTA Design Submittal 0 days NA NA 0% Thu 7/11/24 Thu 7/11/24 109,110 Future Task