W911KB19B0002_Amendment__1.pdf
PDF 391 KB Posted
- Attached to
- Aurora and Harris Harbor Maintenance, Juneau, AK
- Solicitation number
- W911KB19B0002
About this file
Pre-Proposal Conference Minutes
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Abstract.pdf | ||
| W911KB19B0002-0011_AMENDMENT.pdf | ||
| Amendment_0010.pdf | ||
| Specs-JNU004-AM_9.pdf | ||
| SF30.pdf | ||
| W911KB19B0002_Amend_08.pdf | ||
| B.01.03_AMENDMENT_07.pdf | ||
| Amendment_06.pdf | ||
| W911KB19B0002-0005.pdf | ||
| 19B0002-0004.pdf | ||
| 19B0002-0002_AMEND.pdf | ||
| W911KB19B0002_Print.pdf | ||
| Dwgs-JNU004-IFB_Half_Size_(11x17).pdf | ||
| W911KB19B0002_att.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JNU004
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
PROJECT TITLE/LOCATION: Aurora and Harris Harbor Maintenance, Juneau, Alaska
BIDS DUE DATE remains 6 August 2019, 2:00 PM Alaska Time.
Bids shall be submitted in accordance w ith Section 00 21 00, Paragraph 7, Bid Submission Instructions This Amendment provides changes to the solicitation as indicated on page 2 of this document.
YOU ARE REQUIRED TO ACKNOWLEDGE RECEIPT OF THIS AMENDMENT ON THE REVERSE SIDE OF THE STANDARD FORM 1442.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 18-Jul-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911KB19B0002
X 9B. DATED (SEE ITEM 11)
27-Jun-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
18-Jul-2019
CODE
U.S. ARMY ENGINEER DISTRICT, AK
CEPOA-CT (W911KB)
PO BOX 6898
JBER AK 99506-0898
W911KB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911KB19B0002
SUMMARY OF CHANGES
AMENDMENT #0001
• The following drawings are substituted for the superseded drawings:
NONE
• The following revised documents are substituted for the superseded documents. The identifier “AM#1” appears before and after new and/or revised material and replacement pages are provided, except as noted:
SECTION 35 20 23 Page 5 para 3.1.1 General is replaced.
• The following documents/drawings are deleted:
• The following documents are added:
• The following revisions are incorporated:
• Other:
Pre-Proposal Conference Minutes are attached
AM#1 AURORA AND HARRIS HARBOR MAINTENANCE JNU004
JUNEAU, ALASKA
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.1 DREDGING AND EXCAVATION
3.1.1 General
The Contractor shall mobilize and use dredging equipment capable of excavating, removing, and hauling soil as necessary to achieve the required depths specified and shown. The Contractor is responsible for ensuring that no material or effluent is leaked from equipment transporting material to the disposal site by ensuring that equipment typical of that used for this type of work is in good repair and operating properly. The Contractor shall inspect the equipment daily.
The Contractor shall notify the local officials a minimum of 21 calendar days in advance of AM#1... the start of the pre-dredge survey for the harbor under consideration ...AM#1 to allow adequate time for the removal of vessels from the dredge area. All dredging and excavation shall be performed to the depths and grades shown on the drawings, and within the areas shown. The Contractor shall be responsible for selection and provision of the appropriate equipment and dredging methods commensurate with the subsurface conditions presented in this contract.
Side slopes shall be dredged or excavated to the limits and grades shown on the drawings. If any side slope sloughing or erosion occurs in the completed dredge slope, the Contractor shall cease dredging operations in that location immediately and contact the Contracting Officer's Representative.
Caution shall be used and care taken not to damage the float system or piles within the entrance channel and mooring area limits. The Contractor shall inspect the float system and piles daily to ensure that no damage has occurred. The Contractor's daily Quality Control report shall document the results of the damage inspection. The Contractor shall repair at his own expense any damages to the harbor float system or the piles caused by dredging and/or disposal operations. Tieing off or anchoring barges and equipment to the existing breakwater armor rock, docks, floats, or other adjacent harbor infrastructure will not be permitted.
Inspect the work, keep records of work performed, and ensure that gages, targets, ranges, and other markers are in place and usable for the intended purpose. Furnish, at the request of the Contracting Officer, boats, boatmen, laborers, and materials necessary for inspecting, and surveying the work. When requested, provide transportation for the Contracting Officer and other Government personnel to and from the disposal area and between the dredging plant and adjacent points on shore.
3.1.2 Equipment and Operation Limits
The Contractor shall restrict the placement of dredging and excavating equipment to only that actually required to accomplish the work as specified and within the limits as defined on the drawings. The Contractor is required to have on-site equipment that is capable of dredging to the required dredge depth.
Section 35 20 23 Page 5
W911KB19B0002
JNU004
Aurora & Harris Harbor Maintenance Juneau, Alaska
Pre-Bid Teleconference 10-Jul-2019 1:00pm Alaska Time
Dial-In Number 1-877-336-1839 Access and Security Code 9400133
Topics for Part IV. TECHNICAL SPEC SECTIONS AND DRAWINGS
a. General Overview
i. Location: Aurora and Harris Harbors are located adjacent to one another in Juneau, Alaska just north of the Douglas Bridge.
ii. Project Description: Aurora Harbor and Harris Harbor are small boat harbors serving the City and Borough of Juneau. Aurora Harbor was constructed in the early 1960’s and is a 19 acre basin with an authorized depth of -12 feet MLLW in the northern half and -14 feet MLLW in the southern half. The harbor is protected by a 670 foot jetty to the north and a detached breakwater with a wood and steel wave barrier to the west. This project will dredge approximately 6 acres of the -12 feet MLLW portion of the harbor and replace the wood and steel wave barrier with similar construction. The estimated dredge quantity to required depth is 7,100 cubic yards. (Note: Aurora Harbor dredging is an option item.)
Harris Harbor was constructed in 1939 and is an 11.5 acre basin with an authorized depth of -12 feet MLLW. The harbor is protected by a 1540 foot breakwater north of the entrance channel and a 430 foot breakwater to the south of the entrance channel. This project will dredge approximately 6 acres in the southern half of the harbor and will dress up the north breakwater by adding riprap to fill visible voids. The estimated dredge quantity for required depth is 14,800 cubic yards.
Both Aurora and Harris Harbors provide moorage for recreational and commercial fishing vessels. The Contractor will be required to provide access through the project site at all times for boats entering or leaving the harbor.
iii. Schedule: The harbors are very active in the summer months so most of the work under this contract is scheduled for the winter months over the course of two years (see FAR 52.211-10). The contract bid schedule includes items for mobilization and demobilization in both 2019 and 2020.
The Aurora Harbor wave barrier replacement and Harris Harbor breakwater rock work is to be performed between October 15, 2019 and June 30, 2020.
Harris Harbor dredging is required to be completed between October 15, 2020 and February 15, 2021. There is a tanner crab fishery that opens in the latter part of February and no dredging is allowed during that fishery.
Aurora Harbor dredging, if the option is exercised, will be required to be completed between October 15, 2020 and December 31, 2020.
b. Aurora Wave Barrier
i. The existing wave barrier is approximately 1,500 feet long and will be demolished and replaced with a new wave barrier of similar construction.
ii. Environmental mitigation measures during pile activities (Section 01 57 20.01 29- 1.9.1):
All pile removal and pile driving must be performed “in the dry” meaning the water surface elevation must be below the ground/rock surface at the pile location.
A dedicated protected species observer must be on site during pile extraction and driving and shall have no other duties.
All sightings of marine mammals shall be documented on the form in the contract.
There is a 150 meter exclusion zone around the pile work and work shall be shut down if a marine mammal enters, or appears likely to enter the exclusion zone. See Section 01 57 20.01 29 for details of the shutdown requirements.
iii. Section 31 62 16.17 addresses pile driving requirements. A pile driving plan is required prior to the start of any pile related work and shall address pile extraction as well as pile installation.
iv. Drawing G-002, general note 8 addresses incidental work associated with the wave barrier work.
v. Fabricate lumber and timber prior to preservative treatment, see Section 06 13 34, paragraph 2.1.2 Preservative Treatment. Field treat damaged areas and field drilled holes in accordance with paragraphs 2.1.3 Field Treatment and 3.2 FIELD TREATMENT of this section.
vi. New W8x67 piles are uncoated.
vii. Red-lines and as-built record drawings of the Aurora wave barrier shall be provided in accordance with Section 01 78 00.
c. Dredging (Section 35 20 23 and contract drawings)
i. Dredging will be performed in the southern half of Harris Harbor and the northern third of Aurora Harbor. Aurora Harbor dredging is a contract option which may be exercised at any time until July 1, 2020 (see contract clause 52.217-7).
ii. Required dredge depth in both harbors is -12 feet mean lower low water.
Hydrographic surveys were conducted in March 2019 and are included as exhibit drawings. Note that there are a few obstructions identified which must be removed if the obstruction is within the dredge limits.
iii. Dredging will be performed around the harbor floats. To facilitate the removal of vessels from the floats, the contractor shall provide a minimum 21 calendar day advance notice of the start of dredging operations. Dredging shall be performed as close to the floats as practicable to not cause damage to the floats or pilings.
iv. The dredge material disposal site is in Gastineau Channel just east-southeast of Douglas Harbor and approximately 900 feet down channel from a disposal site that was used for the placement of contaminated material from Douglas Harbor in 2015.
v. Section 35 20 23-3.2.3 identifies measures required for the controlled placement of dredge material from Harris and Aurora Harbors to keep material from drifting into the Douglas Harbor disposal site.
vi. Section 35 20 23.13 requires the use of Dredge Quality Management (DQM) instrumentation on the dump scow to monitor disposal location. The DQM instrumentation requires a current annual certification (Letter of National Dredging Quality Management Certification) from the DQM center located in Mobile, Alabama.
vii. Section 01 57 20.01 29-1.9.2 includes requirements for a marine mammal watch during dredging. The requirements differ for dredging with a crane-operated clamshell/bucket versus dredging with a barge-mounted excavator so please review carefully. Paragraph 1.9.3 includes a speed limit of 8 knots on transiting vessels.
d. Surveys (Section 31 09 13.00 29)
i. Pre-dredge and post-dredge hydrographic surveys by an independent certified hydrographic surveyor are required for both Harris and Aurora Harbors. The survey limits for each include the entire harbor rather than just the dredge limits.
Reference COORDINATE TABLE NOTE 2 on V-102 regarding the requirements related to the survey limits shown.
ii. Post-dredge surveys shall also include LiDAR surveys of the breakwaters of each harbor. See Section 31 09 13.00 29-2.1.C.4
iii. Pre-disposal and post-disposal surveys of the Gastineau Channel disposal area are required before any disposal occurs and after all dredge material disposal is complete.
e. Safety Requirements (Section 01 35 26)
i. Floating Plant: Requirements for Floating Service Load Chart and Naval Architectural Analysis are contained in this Section as well as EM 385-1-1. This documentation shall be provided for Government review and approval in the Accident Prevention Plan following contract award.
ii. Site Safety Health Officer (SSHO): Requirements and qualifications for this individual and approved alternates are contained in this Section as well as EM 385-1-1. The Contractor Quality Control System Manager cannot serve as the
SSHO.
iii. Navigation Safety Plan: Requirements for this plan are included in Section 01 19 40.00 29, Special Items. The Navigation Safety Plan shall be included as part of the Accident Prevention Plan.