Bid_Abstract.pdf
PDF 265 KB Posted
- Attached to
- Aurora and Harris Harbor Maintenance, Juneau, AK
- Solicitation number
- W911KB19B0002
About this file
Bid Abstarct
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W911KB19B0002-0011_AMENDMENT.pdf | ||
| Amendment_0010.pdf | ||
| Specs-JNU004-AM_9.pdf | ||
| SF30.pdf | ||
| W911KB19B0002_Amend_08.pdf | ||
| B.01.03_AMENDMENT_07.pdf | ||
| Amendment_06.pdf | ||
| W911KB19B0002-0005.pdf | ||
| 19B0002-0004.pdf | ||
| 19B0002-0002_AMEND.pdf | ||
| W911KB19B0002_Amendment__1.pdf | ||
| W911KB19B0002_Print.pdf | ||
| Dwgs-JNU004-IFB_Half_Size_(11x17).pdf | ||
| W911KB19B0002_att.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For Official Use Only
2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES
27-Jun-2019 5-Sep-2019 1 of 3
DATE SIGNED
ITEM NO.
EST.
QUANTITY UNIT
UNIT
PRICE
ESTIMATED
AMOUNT
UNIT
PRICE
AMOUNT
UNIT
PRICE
AMOUNT
2019 Mobilization and Demobilization, complete.
1 JOB $1,331,800.00 $1,331,800.00 $249,000.00 $249,000.00 $1,018,706.00 $1,018,706.00
Remove and Replace Aurora Harbor Wave Barrier, complete
1 JOB $2,543,520.00 $2,543,520.00 $1,750,000.00 $1,750,000.00 $2,865,000.00 $2,865,000.00
0003 Repair Harris Harbor Breakwater, complete 1 JOB $46,570.00 $46,570.00 $30,000.00 $30,000.00 $50,000.00 $50,000.00
2020 Mobilization and Demobilization, complete
1 JOB $1,522,300.00 $1,522,300.00 $125,000.00 $125,000.00 $935,000.00 $935,000.00
0005AA First 14,800 cubic yards 14,800 CY $37.10 $549,080.00 $25.00 $370,000.00 $35.00 $518,000.00 0005AB All over 14,800 cubic yards 6,500 CY $33.70 $219,050.00 $25.00 $162,500.00 $35.00 $227,500.00
Topographic/Hydrographic Surveys for Harris Harbor Dredging, complete
2 EA $85,720.00 $171,440.00 $30,000.00 $60,000.00 $42,000.00 $84,000.00
Hydrographic Surveys for Disposal Area, complete
2 EA $6,940.00 $13,880.00 $15,000.00 $30,000.00 $19,000.00 $38,000.00
Total of Base Items 0001-0007 $6,397,640.00 $2,776,500.00 $5,736,206.00
0008AA First 7,100 cubic yards 7,100 CY $41.70 $296,070.00 $35.00 $248,500.00 $35.00 $248,500.00 0008AB All over 7,100 cubic yards 2,500 CY $34.10 $85,250.00 $35.00 $87,500.00 $35.00 $87,500.00
Topographic/Hydrographic Surveys for Aurora Harbor Dredging, complete
2 EA $6,940.00 $13,880.00 $6,000.00 $12,000.00 $26,000.00 $52,000.00
Total of Option Items 0008-0009 $395,200.00 $348,000.00 $388,000.00
Total of Base and Option Items 0001- 0009 $6,792,840.00 $3,124,500.00 $6,124,206.00
Harris Harbor Maintenance Dredging and Dredged Material Disposal, complete
Aurora Harbor Maintenance Dredging and Dredged Material Disposal, complete
7. NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)
Western Marine Construction
A. OFFEROR
Duwamish-Pacific Joint Venture
A. OFFEROR
Yes-20%
Christine Dale, Contracting Officer
C. AMENDEMENTS ACKNOWLEDGED
No. 01 Aurora and Harris Harbor Maintenance, Juneau, Alaska
SIGNATURE
9. OFFERS
W911KB-19-B-0002
ABSTRACT OF OFFERS - CONSTRUCTION
4. ISSUING OFFICE
5. PROJECT TITLE
1. SOLICITATION NUMBER
U.S. Army Engineer District, Alaska PO Box 6898
JBER, AK 99506-6898
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
8. GOVERNMENT ESTIMATE
(Check A, B, C and complete D, E, and F)
No. 02
B. BID SECURTIY (TYPE AND AMOUNT)B. BID SECURTIY (TYPE AND AMOUNT)
Yes-20%
6. NUMBER OF AMENDMENTS ISSUED
To be Determined Yes Yes
C. AMENDEMENTS ACKNOWLEDGED
| 2019-09-23T18:23:30-0800 | |
| Christine A. Dale |