AMENDMENT 0011
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Abstract.pdf | ||
| Amendment_0010.pdf | ||
| Specs-JNU004-AM_9.pdf | ||
| SF30.pdf | ||
| W911KB19B0002_Amend_08.pdf | ||
| B.01.03_AMENDMENT_07.pdf | ||
| Amendment_06.pdf | ||
| W911KB19B0002-0005.pdf | ||
| 19B0002-0004.pdf | ||
| 19B0002-0002_AMEND.pdf | ||
| W911KB19B0002_Amendment__1.pdf | ||
| W911KB19B0002_Print.pdf | ||
| Dwgs-JNU004-IFB_Half_Size_(11x17).pdf | ||
| W911KB19B0002_att.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W911KB19B0002
JNU004
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
PROJECT TITLE/LOCATION: Aurora and Harris Harbor Maintencance, Juneau AK
See summary of changes on page 2
ProjNet Bidder Inquiry Report is attached.
No other changes YOU ARE REQUIERED TO ACKNOWLEDGE RECEIPT OF THIS AMENDMENT ON THE REVERSE SIDE OF THE STANDARD FORM 1442
1. CONTRACT ID CODE PAGE OF PAGES
1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 03-Sep-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911KB19B0002
X 9B. DATED (SEE ITEM 11)
27-Jun-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
03-Sep-2019
CODE
U.S. ARMY ENGINEER DISTRICT, AK
CEPOA-CT (W911KB)
PO BOX 6898
JBER AK 99506-0898
W911KB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911KB19B0002
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 MODIFICATION CONTINUATION
PAGE
The following have been added by full text:
SUMMARY OF
CHANGES
AMENDMENT #0011
The following drawings are substituted for the superseded drawings:
NONE
The following revised documents are substituted for the superseded documents. The identifier “AM#11” appears before and after new and/or revised material and replacement pages are provided, except as noted:
NONE
The following documents/drawings are deleted:
NONE
The following documents are added:
NONE
• The following revisions are incorporated:
NONE
Other:
ProjNet Bidder Inquiry Report has been provided, see attachment.
UNCLASSIFIED\\FOR OFFICIAL USE ONLY
Bid Inquiry Contractor Report All Inquiries
Project: Aurora and Harris Harbor Maintenance Review: Aurora & Harris Bidder Inquiry (00001) (sorted by CommentID ) Displaying 11 inquiries.
Id Discipline Sheet Detail Spec
8087086 Civil 35 20 23 Dredging
Comment Classification: UNCLASSIFIED (U)
3.1.1 says in part, "Tieing off or anchoring barges and equipment to armor rock, docks, floats, or other adjacent harbor infrastructure will not be permitted. Will it be allowable to vibe in spuds to help moor the barges during dredging operations (depending on methods, there can be a large force exerted by mechanical dredging on the vessel) and/or high wind events?
On: Jul 10 2019.
Government Response. . Spuds may be vibed in to moor barges during dredging and will be subject to the same environmental mitigation measures as the dredging. On: Jul 18 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8087089 Civil C103, C101
Comment Classification: UNCLASSIFIED (U)
Please confirm the entire area will be cleared of vessels so the pre-survey, dredging, post-survey can be continuous, only one pre-survey and one post-survey, assuming depth has been obtained.
On: Jul 10 2019.
Government Response. . Please see amendment number 1, revised Section 35 20 23 paragraph 3.1.1 General. On: Jul 18 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8087097 Civil 35 20 23 3.1.3
Comment Classification: UNCLASSIFIED (U)
Please confirm the Corps will accept a reasonable amount of high spots under floats and near piles as it is understood there are limitations to dredging to depth near these items without high risk of damage or high cost of extreme measures.
On: Jul 10 2019.
Government Response. . In accordance with the contract, dredging shall be performed as close as practicable to the floats and piles without causing damage. Any remaining high spots under the floats or near piles will be subject to Contracting Officer approval. On: Jul 18 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8087098 Civil C101 and C103
Comment Classification: UNCLASSIFIED (U)
Please confirm silt curtain will not be required for any of the construction or dredging required by this project.
On: Jul 10 2019.
Government Response. . A silt curtain is not required for this project. On: Jul 18 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8087116 Civil Exhibit X-831
Comment Classification: UNCLASSIFIED (U)
W911KB19B0002-0011ProjNet: Logged In User
9/3/2019https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll...
It appears the H Pile will be driven through "quarry run rock". Can you find out if there was a maximum size spec to this material, or are there photos? If these are more than 3 or 4 inch material, it could be difficult to drive to the required tolerance for the wall. If the original contractor drove pile and backfilled with 4' rock, it could be a huge effort to excavate and drive the new pile.
On: Jul 10 2019.
Government Response. . The contract documents include the best available information on this material {see "EXISTING MAIN (ROCK) BREAKWATER WITH STEEL AND TIMBER WAVE BARRIER NOTES" on sheet C-301}. On: Jul 18 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8107581 Materials 061334
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Questions and associated documents attached.
Thank-you.
Mikr
(Attachment: Specifications_at_061334.pdf) On: Jul 24 2019.
Government Response. . The questions regarding specification 06 13 34 are acknowledged. See Amendment #2 for changes to the specification. On: Jul 25 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8109494 Structural 2.1.2
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Timber preservative treatment specs listed in 2.1.2 are not consistent with current wood preservative specifications.
Can you confirm the spec is correct?
On: Jul 25 2019.
Government Response. . Section 06 13 34-2.1.2 has been revised by Amendment 0002. On: Jul 25
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8109516 Contracting Box 13 06 Aug 2019
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
There have been difficulties sourcing some of the breakwater materials. For this reason we respectfully request a bid extension of up to 2 weeks to ensure proper compliance and competitive pricing.
On: Jul 25 2019.
Government Response. . The Government has no current plan to postpone the bid opening date. On:
Jul 29 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8109774 Structural s-501
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
During removal of the existing and installation of the new wood and steel breakwater; are there any phasing restrictions or expectations where only a portion of the wall can be removed before being replaced? or can the entire wall be removed, rock removed, new wall put in and rock put back in place without any phasing?
On: Jul 25 2019.
Government Response. . The Contract Documents do not impose any phasing requirements on the demolition and reconstruction of the Aurora Harbor wave barrier and associated rock breakwater work. On:
Jul 29 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8127552 Materials 061334 Amendment #2
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Amendment #2 addressed several issues related to the lumber and treating. It deleted the terms "surfaced dry" from the referenced specification. The previous request was relative to the term "dry" and the moisture content of the lumber prior to treating. By removing the term "surfaced" is it your intent to require rough lumber or is "surfaced" (S4S S-GRN) material desired. Is either rough or surfaced allowed?
On: Aug 06 2019.
Government Response. . Rough lumber is not allowed. On: Aug 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8128478 Contracting 1 1 1
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Under this contract will the contractor be allowed to invoice, and be paid for, materials on hand stored in Seattle area in advance of being delivered to site?
On: Aug 06 2019.
Government Response. . No, the provision for payment of materials stored off-site is not included in this contract. On: Aug 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
Report Complete
UNCLASSIFIED\\FOR OFFICIAL USE ONLY
Patent 11/892,984 ProjNet property of ERDC since 2004.
File details come from the government source that posted it.