FTG192, Switchgear Facility, Ft Greely, AK Federal contract opportunity
Solicitation number
W911KB-17-R-0019
Issued by
Department of the Army Corps of Engineers Engineering District Alaska

About this file

W911KB-17-R-0019--Amendment 0004--FTG192

View the file

Other files for this federal contract opportunity

Other files attached to FTG192, Switchgear Facility, Ft Greely, AK, newest first.
File Type Posted
Amendment_03.pdf PDF
17R0019-Amendment_0002-FTG192_Final.pdf PDF
AM_01.pdf PDF
A.03.06_Redacted_JandA_Brand_Name-_FTG192.pdf PDF
A.07.23_W911KB-17-R-0019_to_post.pdf PDF
FTG192_Presolicitation_Notice.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

PROJECT TITLE/LOCATION: FTG192, IDT Switchgear Facility, Fort Greely, ALASKA a.This amendment provides changes to the solicitation as indicated on the continuation pages of this document.

b.PROPOSAL DUE DATE REMAINS 13 April 2017 at 1400 hours ALASKA TIME. Proposals shall be submitted in accordance with Section 00 21 00, paragraph 1.8, Proposal Submittals.

c.YOU ARE REQUIRED TO ACKNOWLEDGE RECEIPT OF THIS AMENDMENT ON THE REVERSE SIDE OF THE STANDARD FORM 1442.

1. CONTRACT ID CODE PAGE OF PAGES

1 100

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-Apr-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911KB-17-R-0019

X 9B. DATED (SEE ITEM 11)

02-Feb-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Apr-2017

CODE

U.S. ARMY ENGINEER DISTRICT, AK

CEPOA-CT (W911KB)

PO BOX 6898

JBER AK 99506-0898

W911KB 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

a. The following drawings are substituted for the superseded documents/sections:

C-W00100, C-W00500, C-W00501, E-W28634, F-W28110, F-W28120, G-W00051

b. The following revised documents/sections are substituted for the superseded documents/sections.

The identifier “AM 04” appears before and after new and/or revised materials, except as noted below.

SECTION 00 21 00 – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFEROR

Table of Contents

Para. 1.15

SECTION 00 73 46 – WAGE DETERMINATIONS SCHEDULES

Replaced with AK170001 dated 04/07/2017

SECTION 01 11 00 – SUMMARY OF WORK

Para. 1.2.1 (a)

SECTION 01 19 30.00 29 – SPECIAL ITEMS

Para. 1.7.2.1 Para. 1.8.9 Para. 1.11.1

SECTION 01 91 00 – COMMISSIONING

Para. 1.5 (a)(8) Para. 1.5 (b)

SECTION 08 34 49.00 20 – HEMP SHIELDED DOOR AND HATCH

Para. 2.6.2 Para. 2.6.4

SECTION 13 27 54 – HIGH ALTITUDE ELECTROMAGNETIC PULSE (HEMP)

PROTECTION SUBSYSTEMS

Para. 2.4.2 – 2.4.3 Para. 3.12

Para. 3.12.4 Para. 3.14 – 3.14.2

SECTION 13 34 24.00 50 – INTEGRATED EQUIPMENT ENCLOSURES

Para. 1.6.1.1 Para. 1.6.1.2 (a)

SECTION 13 48 00.00 10 – SEISMIC PROTECTION FOR MECHANICAL EQUIPMENT

Para. 1.2.2

SECTION 26 33 53.00 20 – UNINTERRUPTIBLE POWER SUPPLY (UPS)

Para. 2.1 Para. 2.2.1 – 2.2.2 Para. 2.2.5 – 2.2.6 Para. 2.3.1 Para. 2.4.6 Para. 2.5.1.1 – 2.5.1.2 Para. 2.5.2 – 2.5.3 Para. 2.11

SECTION 26 41 00 – LIGHTNING PROTECTION SYSTEM

Para. 3.1.2

SECTION 27 10 00 – BUILDING TELECOMMUNICATIONS CABLING SYSTEM

Para. 2.4.1 (c)

SECTION 28 31 64.00 10 – FIRE DETECTION AND ALARM SYSTEM, ADDRESSABLE

Para. 2.11

SECTION 33 71 02 – UNDERGROUND ELECTRICAL DISTRIBUTION

Para. 1.1 Para 1.5 Para 2.1.5 Para. 2.1.6.1 Attachment A

c. The following documents/sections replace the documents/sections from Amendment 03. The only changes to the documents are the identifier “AM 03” markings. “AM 03” appear before and after new and/or revised materials, except as noted below.

SECTION 01 45 04.00 29 – CONTRACTOR QUALITY CONTROL

Para 1.2.6 (b)

SECTION 13 27 54 – HIGH ALTITUDE ELECTROMAGNETIC PULSE (HEMP)

PROTECTION SUBSYSTEMS

Para. 2.11.1 Para 3.4.2 Para 3.9 Para. 3.10.1

SECTION 13 34 24.00 50 – INTEGRATED EQUIPMENT ENCLOSURES

Para. 1.6.4.1

NOTE: Revisions within the following documents do not contain the above referenced identifiers:

NONE

d. The following sections are deleted:

e. The following documents are added:

Bidder Inquiry Report

f. The following revisions are incorporated:

g. Other:

(End of Summary of Changes)

ALL OTHER TERMS AND CONDITIONS SHALL REMAIN THE SAME.

Section 00 21 00 - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

INSTRUCTIONS TO OFFERORS

SECTION 00 21 00

INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFEROR

1.0 GENERAL INFORMATION

1.1 GENERAL DESCRIPTION OF WORK

1.2 CONTRACT COST MAGNITUDE FOR CONSTRUCTION COSTS

1.3 GOVERNMENT SECURITY REQUIREMENTS

1.4 OFFEROR'S QUESTIONS AND COMMENTS

1.5 SMALL BUSINESS SIZE STANDARD/NAICS CODE

1.6 PROPOSAL EXPENSES AND PRE-CONTRACT COSTS

1.7 ACCURACY IN PROPOSALS

1.8 PROPOSAL SUBMITTAL

1.9 PROPOSAL FORMAT

1.10 JOINT VENTURE AND LLC PROPOSAL REQUIREMENTS

1.11 BUY AMERICAN ACT ADVISORY NOTICE 1.12

BOND AMOUNT REQUIRED

1.13 SURETY REQUIREMENTS

1.14 PRE-AWARD SURVEYS

1.15

1.16 DEVIATIONS FROM THE RFP

Offer Guarantee: The requirements for an Offer Guarantee as required in FAR Clause 52.228-1 Bid Guarantee (Sep 1996) are hereby waived. However, the offeror must submit a letter from their bonding company indicating the offeror’s ability to obtain performance and payment bonds in the amount of the proposal price.

1.13 SURETY REQUIREMENTS

a. Corporate Sureties - Corporate sureties for performance and payment bonds must appear on the list contained in the Department of the Treasury Circular 570, "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and Acceptable Reinsuring Companies". Other requirements for corporate sureties are contained in FAR 28.202-1.

b. Individual Sureties - If individual sureties are used for bond obligations, they must meet the requirements under

FAR 28.203.

1.14 PRE-AWARD SURVEYS

The Government reserves the right to conduct a pre-award survey of any firm under consideration to confirm any part of the information furnished by the Offeror, or to require other evidence of managerial, financial, technical, and other capabilities, the positive establishment of which is determined by the Government to be necessary for the successful performance of the contract.

1.15 PERFORMANCE OF WORK BY CONTRACTOR

Your attention is invited to Section 00 72 00, FAR 52.219-14 entitled “Limitations on Subcontracting.” Submit with the proposal, a description of the work that the contractor intends to perform with his own organization (e.g.

earthwork, paving, brickwork, roofing, etc.), the percentage of total work and the estimated cost thereof.

1.16 DEVIATIONS FROM THE RFP

The minimum requirements of the RFP shall be met and proposals shall not include any deviations or exceptions.

The contractor proposal shall include the following: Include BAA waiver requests and rationale.

52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)

Any contract awarded as a result of this solicitation will be N/A DX rated order; C2 DO rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation.

(End of provision)

52.215-1 INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2004)

(a) Definitions. As used in this provision--

“Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer's discretion, result in the offeror being allowed to revise its proposal.

General Decision Number: AK170001 04/07/2017 AK1

Superseded General Decision Number: AK20160001

State: Alaska

Construction Types: Building and Heavy

Counties: Alaska Statewide.

BUILDING AND HEAVY CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories)

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017.

The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/06/2017 1 01/20/2017 2 01/27/2017 3 02/17/2017 4 03/17/2017 5 03/31/2017 6 04/07/2017

ASBE0097-001 01/01/2017

Rates Fringes

Asbestos Workers/Insulator (includes application of all insulating materials protective coverings, coatings and finishings to all types of mechanical systems).........................$ 38.68 20.07

HAZARDOUS MATERIAL HANDLER

(includes preparation, wetting, stripping, removal scrapping, vacuming, bagging, and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems).........$ 37.38 19.55

* BOIL0502-002 08/01/2016

Rates Fringes

BOILERMAKER......................$ 44.26 28.41

BRAK0001-002 07/01/2016

Rates Fringes

Bricklayer, Blocklayer, Stonemason, Marble Mason, Tile Setter, Terrazzo Worker.....$ 40.81 19.15 Tile & Terrazzo Finisher.........$ 34.79 19.15

CARP1501-001 09/01/2014

Rates Fringes

MILLWRIGHT.......................$ 35.74 21.29

CARP2520-003 09/01/2014

Rates Fringes

Diver Stand-by....................$ 41.65 23.34 Tender......................$ 40.65 23.34 Working.....................$ 81.45 23.34 Piledriver Carpenter...................$ 37.34 23.34 Piledriver; Skiff Operator and Rigger..................$ 37.34 23.34 Sheet Stabber...............$ 36.59 22.59 Welder......................$ 42.90 23.34

DEPTH PAY PREMIUM FOR DIVERS BELOW WATER SURFACE:

50-100 feet $1.00 per foot 101 feet and deeper $2.00 per foot

ENCLOSURE PAY PREMIUM WITH NO VERTICAL ASCENT:

5-50 FEET $1.00 PER FOOT/DAY

51-100 FEET $2.00 PER FOOT/DAY

101 FEET AND ABOVE $3.00 PER FOOT/DAY

SATURATION DIVING:

The standby rate applies until saturation starts. The saturation diving rate applies when divers are under pressure continuously until work task and decompression are complete. the diver rate shall be paid for all saturation hours.

WORK IN COMBINATION OF CLASSIFICATIONS:

Employees working in any combination of classifications within the diving crew (except dive supervisor) in a shift are paid in the classification with the highest rate for that shift.

CARP4059-001 09/01/2014

Rates Fringes

CARPENTER

Carpenter...................$ 37.34 23.34 Lather/Drywall Applicator...$ 36.59 22.59

* ELEC1547-004 04/01/2017

Rates Fringes

CABLE SPLICER....................$ 39.82 3%+25.44

ELECTRICIAN......................$ 39.49 3%+25.69

* ELEC1547-005 04/01/2017

Line Construction

Rates Fringes

CABLE SPLICER....................$ 52.57 3%+30.81

Linemen (Including Equipment Operators, Technician)...........$ 50.52 3%+30.81 Powderman........................$ 48.52 3%+30.81

TREE TRIMMER.....................$ 35.84 3%+22.56

ELEV0019-002 01/01/2017

Rates Fringes

ELEVATOR MECHANIC................$ 53.76 31.585+a+b

FOOTNOTE: a. Employer contributes 8% of the basic hourly rate for over 5 year's service and 6% of the basic hourly rate for 6 months to 5 years' of service as vacation paid credit. b. Eight paid holidays:

New Year's Day; Memorial Day; Independence Day;

Labor Day; Veteran's Day; Thanksgiving Day; Friday after Thanksgiving, and Christmas Day

ENGI0302-002 01/01/2017

Rates Fringes

POWER EQUIPMENT OPERATOR

GROUP 1.....................$ 40.28 22.65

GROUP 1A....................$ 42.04 22.65

GROUP 2.....................$ 39.51 22.65

GROUP 3.....................$ 38.79 22.65

GROUP 4.....................$ 32.58 22.65

TUNNEL WORK

GROUP 1....................$ 44.31 22.65

GROUP 1A...................$ 46.24 22.65

GROUP 2....................$ 43.46 22.65

GROUP 3....................$ 42.67 22.65

GROUP 4....................$ 35.84 22.65

POWER EQUIPMENT OPERATOR CLASSIFICATIONS

GROUP 1: Asphalt Roller: Breakdown, Intermediate, and Finish; Back Filler; Barrier Machine (Zipper); Beltcrete with power pack and similar conveyors; Bending Machine;

Boat Coxwains; Bulldozers; Cableways, Highlines and Cablecars; Cleaning Machine; Coating Machine; Concrete Hydro Blaster; Cranes-45 tons and under or 150 foot boom and under (including jib and attachments): (a) Hydralifts or Transporters, all track or truck type,(b) Derricks;

Crushers; Deck Winches-Double Drum; Ditching or Trenching Machine (16 inch or over); Drilling Machines, core, cable, rotary and exploration; Finishing Machine Operator, Concrete Paving, Laser Screed, Sidewalk, Curb and Gutter Machine; Helicopters; Hover Craft, Flex Craft, Loadmaster, Air Cushion, All Terrain Vehicle, Rollagon, Bargecable, Nodwell, and Snow Cat; Hydro Ax: Feller Buncher and similar; Loaders (2 1/2 yards through 5 yards, including all attachments): Forklifts with telescopic boom and swing attachment, Overhead and front end, 2 1/2 yards through 5 yards, Loaders with forks or pipe clamps; Loaders, elevating belt type, Euclid and similar types; Mechanics, Bodyman; Micro Tunneling Machine; Mixers: Mobile type w/hoist combination; Motor Patrol Grader; Mucking Machines:

Mole, Tunnel Drill, Horizontal/Directional Drill Operator, and/or Shield; Operator on Dredges; Piledriver Engineers, L. B. Foster, Puller or similar Paving Breaker; Power Plant, Turbine Operator, 200 k.w. and over (power plants or combination of power units over 300 k.w.); Scrapers-through 40 yards; Service Oiler/Service Engineer; Sidebooms-under 45 tons; Shot Blast Machine; Shovels, Backhoes, Excavators with all attachments, and Gradealls (3 yards and under), Spreaders, Blaw Knox, Cedarapids, Barber Greene, Slurry Machine; Sub-grader (Gurries, Reclaimer, and similar types); Tack tractor; Truck mounted Concrete Pumps, Conveyor, Creter; Water Kote Machine; Unlicensed off road hauler

GROUP 1A: Camera/Tool/Video Operator (Slipline), Cranes-over 45 tons or 150 foot (including jib and attachments): (a) Clamshells and Draglines (over 3 yards),

(b) Tower cranes; Licensed Water/Waste Water Treatment Operator; Loaders over 5 yds.; Certified Welder, Electrical Mechanic, Camp Maintenance Engineer, Mechanic (over 10,000 hours); Motor Patrol Grader, Dozer, Grade Tractor, Roto-mill/Profiler (finish: when finishing to final grade and/or to hubs, or for asphalt); Power Plants: 1000 k.w.

and over; Quad; Screed; Shovels, Backhoes, Excavators with all attachments (over 3 yards), Sidebooms over 45 tons;

Slip Form Paver, C.M.I. and similar types; Scrapers over 40 yards;

GROUP 2: Boiler-fireman; Cement Hog and Concrete Pump

Operator; Conveyors (except as listed in group 1); Hoist on steel erection; Towermobiles and Air Tuggers;

Horizontal/Directional Drill Locator;Licensed Grade Technician; Loaders, (i.e., Elevating Grader and Material Transfer Vehicle); Locomotives: rod and geared engines;

Mixers; Screening, Washing Plant; Sideboom (cradling rock drill regardless of size); Skidder; Trencing Machine under 16 inches; Waste/ Waste Water Treatment Operator.

GROUP 3: "A" Frame Trucks, Deck Winches: single power drum;

Bombardier (tack or tow rig); Boring Machine; Brooms-power;

Bump Cutter; Compressor; Farm tractor; Forklift, industrial type; Gin Truck or Winch Truck with poles when used for hoisting; Grade Checker and Stake Hopper; Hoist, Air Tuggers, Elevators; Loaders: (a) Elevating-Athey, Barber Green and similar types (b) Forklifts or Lumber Carrier (on construction job site) (c) Forklifts with Tower (d) Overhead and Front-end, under 2 1/2 yds. Locomotives:Dinkey (air, steam, gas and electric) Speeders; Mechanics (light duty); Oil, Blower Distribution; Post Hole Diggers, mechanical; Pot Fireman (power agitated); Power Plant, Turbine Operator, under 200 k.w.; Pumps-water; Roller-other than Plantmix; Saws, concrete; Skid Steer with all attachments; Straightening Machine; Tow Tractor

GROUP 4: Rig Oiler/Crane Assistant Engineer;Parts and Equipment Coordinator; Swamper (on trenching machines or shovel type equipment); Spotter; Steam Cleaner; Drill Helper.

FOOTNOTE: Groups 1-4 receive 10% premium while performing tunnel or underground work. Rig Oiler/Crane Assistant Engineer shall be required on cranes over 85 tons or over 100 feet of boom.

IRON0751-003 07/01/2015

Rates Fringes

Ironworkers:

BRIDGE, STRUCTURAL,

ORNAMENTAL, REINFORCING

MACHINERY MOVER, RIGGER,

SHEETER, STAGE RIGGER,

BENDER OPERATOR.............$ 36.25 28.05

FENCE, BARRIER INSTALLER....$ 32.75 28.05

GUARDRAIL INSTALLERS........$ 33.75 28.05

GUARDRAIL LAYOUT MAN........$ 33.49 28.05

HELICOPTER, TOWER...........$ 37.25 28.05

LABO0341-005 04/01/2016

Rates Fringes

Laborers: South of the 63rd Parallel & West of Longitude

138 Degrees

GROUP 1.....................$ 30.00 26.17

GROUP 2.....................$ 31.00 26.17

GROUP 3.....................$ 31.90 26.17

GROUP 3A....................$ 35.18 26.17

GROUP 3B....................$ 38.72 23.46

GROUP 4.....................$ 19.57 26.17

TUNNELS, SHAFTS, AND RAISES

GROUP 1....................$ 33.00 26.17

GROUP 2....................$ 34.10 26.17

GROUP 3....................$ 35.09 26.17

GROUP 3A...................$ 38.70 26.17

GROUP 3B...................$ 42.59 23.46

LABORERS CLASSIFICATIONS

GROUP 1: Asphalt Workers (shovelman, plant crew); Brush Cutters; Camp Maintenance Laborer; Carpenter Tenders; Choke Setters, Hook Tender, Rigger, Signalman; Concrete Laborer(curb and gutter, chute handler, grouting, curing, screeding); Crusher Plant Laborer; Demolition Laborer;

Ditch Diggers; Dump Man; Environmental Laborer (asbestos (limited to nonmechanical systems), hazardous and toxic waste, oil spill); Fence Installer; Fire Watch Laborer;

Flagman; Form Strippers; General Laborer; Guardrail Laborer, Bridge Rail Installers; Hydro-Seeder Nozzleman;

Laborers (building); Landscape or Planter; Laying of Decorative Block (retaining walls, flowered decorative block 4 feet and below); Material Handlers; Pneumatic or Power Tools; Portable or Chemical Toilet Serviceman; Pump Man or Mixer Man; Railroad Track Laborer; Sandblast, Pot Tender; Saw Tenders; Scaffold Building and Erecting; Slurry Work; Stake Hopper; Steam Point or Water Jet Operator;

Steam Cleaner Operator; Tank Cleaning; Utiliwalk, Utilidor Laborer and Conduit Installer; Watchman (construction projects); Window Cleaner

GROUP 2: Burning and Cutting Torch; Cement or Lime Dumper or Handler (sack or bulk); Choker Splicer; Chucktender (wagon, airtrack and hydraulic drills); Concrete Laborers (power buggy, concrete saws, pumpcrete nozzleman, vibratorman);

Culvert Pipe Laborer; Cured in place Pipelayer;

Environmental Laborer (marine work, oil spill skimmer operator, small boat operator); Foam Gun or Foam Machine Operator; Green Cutter (dam work); Gunnite Operator; Hod Carriers; Jackhammer or Pavement Breakers (more than 45 pounds);Laying of Decorative Block (retaining walls, flowered decorative block above 4 feet); Mason Tender and Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer and Cement Finisher Tenders; Power Saw Operator; Railroad Switch Layout Laborer; Sandblaster; Sewer Caulkers; Sewer Plant Maintenance Man; Thermal Plastic Applicator; Timber Faller, chain saw operator, filer; Timberman

GROUP 3: Alarm Installer; Bit Grinder; Guardrail Machine Operator; High Rigger and tree topper; High Scaler;

Multiplate; Slurry Seal Squeegee Man

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

GROUP 4: Final Building Cleanup

TUNNELS, SHAFTS, AND RAISES CLASSIFICATIONS

GROUP 1: Brakeman; Muckers; Nippers; Topman and Bull Gang;

Tunnel Track Laborer

GROUP 2: Burning and Cutting Torch; Concrete Laborers;

Jackhammers; Nozzleman, Pumpcrete or Shotcrete.

GROUP 3: Miner; Retimberman

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers.

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

Tunnel shaft and raise rates only apply to workers regularly employed inside a tunnel portal or shaft collar.

LABO0942-001 04/01/2016

Rates Fringes

Laborers: North of the 63rd Parallel & East of Longitude 138 Degrees

GROUP 1.....................$ 30.00 26.17

GROUP 2.....................$ 31.00 26.17

GROUP 3.....................$ 31.90 26.17

GROUP 3A....................$ 35.18 26.17

GROUP 3B....................$ 38.72 23.46

GROUP 4.....................$ 19.57 26.17

TUNNELS, SHAFTS, AND RAISES

GROUP 1....................$ 33.00 26.17

GROUP 2....................$ 34.10 26.17

GROUP 3....................$ 35.09 26.17

GROUP 3A...................$ 38.70 26.17

GROUP 3B...................$ 42.59 23.46

LABORERS CLASSIFICATIONS

GROUP 1: Asphalt Workers (shovelman, plant crew); Brush Cutters; Camp Maintenance Laborer; Carpenter Tenders; Choke Setters, Hook Tender, Rigger, Signalman; Concrete Laborer(curb and gutter, chute handler, grouting, curing, screeding); Crusher Plant Laborer; Demolition Laborer;

Ditch Diggers; Dump Man; Environmental Laborer (asbestos (limited to nonmechanical systems), hazardous and toxic waste, oil spill); Fence Installer; Fire Watch Laborer;

Flagman; Form Strippers; General Laborer; Guardrail Laborer, Bridge Rail Installers; Hydro-Seeder Nozzleman;

Laborers (building); Landscape or Planter; Laying of Decorative Block (retaining walls, flowered decorative block 4 feet and below); Material Handlers; Pneumatic or Power Tools; Portable or Chemical Toilet Serviceman; Pump Man or Mixer Man; Railroad Track Laborer; Sandblast, Pot Tender; Saw Tenders; Scaffold Building and Erecting; Slurry Work; Stake Hopper; Steam Point or Water Jet Operator;

Steam Cleaner Operator; Tank Cleaning; Utiliwalk, Utilidor Laborer and Conduit Installer; Watchman (construction projects); Window Cleaner

GROUP 2: Burning and Cutting Torch; Cement or Lime Dumper or Handler (sack or bulk); Choker Splicer; Chucktender (wagon, airtrack and hydraulic drills); Concrete Laborers (power buggy, concrete saws, pumpcrete nozzleman, vibratorman);

Culvert Pipe Laborer; Cured in place Pipelayer;

Environmental Laborer (marine work, oil spill skimmer operator, small boat operator); Foam Gun or Foam Machine Operator; Green Cutter (dam work); Gunnite Operator; Hod Carriers; Jackhammer or Pavement Breakers (more than 45 pounds);Laying of Decorative Block (retaining walls, flowered decorative block above 4 feet); Mason Tender and Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer and Cement Finisher Tenders; Power Saw Operator; Railroad Switch Layout Laborer; Sandblaster; Sewer Caulkers; Sewer Plant Maintenance Man; Thermal Plastic Applicator; Timber Faller, chain saw operator, filer; Timberman

GROUP 3: Alarm Installer; Bit Grinder; Guardrail Machine Operator; High Rigger and tree topper; High Scaler;

Multiplate; Slurry Seal Squeegee Man

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

GROUP 4: Final Building Cleanup

TUNNELS, SHAFTS, AND RAISES CLASSIFICATIONS

GROUP 1: Brakeman; Muckers; Nippers; Topman and Bull Gang;

Tunnel Track Laborer

GROUP 2: Burning and Cutting Torch; Concrete Laborers;

Jackhammers; Nozzleman, Pumpcrete or Shotcrete.

GROUP 3: Miner; Retimberman

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers.

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

Tunnel shaft and raise rates only apply to workers regularly employed inside a tunnel portal or shaft collar.

PAIN1959-001 09/01/2015

NORTH OF THE 63RD PARALLEL

Rates Fringes

PAINTER

BRUSH/ROLLER PAINT OR WALL

COVERER.....................$ 32.07 20.01

TAPING, TEXTURING,

STRUCTURAL PAINTING,

SANDBLASTING, POT TENDER,

FINISH METAL, SPRAY,

BUFFER OPERATOR, RADON

MITIGATION, LEAD BASED

PAINT ABATEMENT, HAZARDOUS

MATERIAL HANDLER............$ 32.59 20.01

PAIN1959-002 02/01/2016

SOUTH OF THE 63RD PARALLEL

Rates Fringes

PAINTER

Brush, Roller, Sign, Paper and Vinyl, Swing Stage, Hand Taper/Drywall, Structural Steel, and Commercial Spray............$ 30.31 19.76 Machine Taper/Drywall.......$ 31.56 19.76 Spray-Sand/Blast, Epoxy and Tar Applicator..........$ 31.66 19.76

PAIN1959-003 01/01/2017

NORTH OF THE 63RD PARALLEL

GLAZIER..........................$ 38.63 21.54

PAIN1959-004 07/01/2012

Rates Fringes

FLOOR LAYER: Carpet.............$ 30.09 13.02

PAIN1959-006 01/01/2017

SOUTH OF THE 63RD PARALLEL

Rates Fringes

GLAZIER..........................$ 38.63 20.82

PLAS0867-001 02/01/2016

Rates Fringes

PLASTERER

North of the 63rd parallel..$ 37.25 20.41 South of the 63rd parallel..$ 37.00 20.41

PLAS0867-004 02/01/2016

Rates Fringes

CEMENT MASON/CONCRETE FINISHER

North of the 63rd parallel..$ 37.25 20.41 South of the 63rd parallel..$ 37.00 20.41

* PLUM0262-002 01/01/2017

East of the 141st Meridian

Rates Fringes

Plumber; Steamfitter.............$ 38.02 26.72

PLUM0367-002 07/01/2016

South of the 63rd Parallel

Rates Fringes

Plumber; Steamfitter.............$ 39.85 22.85

PLUM0375-002 07/01/2016

North of the 63rd Parallel

Plumber; Steamfitter.............$ 40.81 24.25

PLUM0669-002 01/01/2015

Rates Fringes

SPRINKLER FITTER.................$ 43.75 22.57

ROOF0189-006 04/01/2016

Rates Fringes

ROOFER...........................$ 42.62 15.50

SHEE0023-003 07/01/2015

South of the 63rd Parallel

Rates Fringes

SHEET METAL WORKER...............$ 40.79 22.38

SHEE0023-004 07/01/2015

North of the 63rd Parallel

Rates Fringes

SHEET METAL WORKER...............$ 45.93 21.44

TEAM0959-003 09/01/2016

Rates Fringes

TRUCK DRIVER

GROUP 1.....................$ 39.59 21.17

GROUP 1A....................$ 40.86 21.17

GROUP 2.....................$ 38.33 21.17

GROUP 3.....................$ 37.51 21.17

GROUP 4.....................$ 36.93 21.17

GROUP 5.....................$ 36.17 21.17

GROUP 1: Semi with Double Box Mixer; Dump Trucks (including rockbuggy and trucks with pups) over 40 yards up to and including 60 yards; Deltas, Commanders, Rollogans and similar equipment when pulling sleds, trailers or similar equipment; Boat Coxswain; Lowboys including attached trailers and jeeps, up to and including 12 axles; Ready-mix over 12 yards up to and including 15 yards); Water Wagon (250 Bbls and above); Tireman, Heavy Duty/Fueler

GROUP 1A: Dump Trucks (including Rockbuggy and Trucks with pups) over 60 yards up to and including 100 yards; Jeeps (driver under load)

GROUP 2: Turn-O-Wagon or DW-10 not self-loading; All Deltas, Commanders, Rollogans, and similar equipment; Mechanics;

Dump Trucks (including Rockbuggy and Trucks with pups) over

20 yards up to and including 40 yards; Lowboys including attached trailers and jeeps up to and including 8 axles;

Super vac truck/cacasco truck/heat stress truck; Ready-mix over 7 yards up to and including 12 yards; Partsman;

Stringing Truck

GROUP 3: Dump Trucks (including Rockbuggy and Trucks with pups) over 10 yards up to and including 20 yards; batch trucks 8 yards and up; Oil distributor drivers; Oil Distributor Drivers; Trucks/Jeeps (push or pull); Traffic Control Technician

GROUP 4: Buggymobile; Semi or Truck and trailer; Dumpster;

Tireman (light duty); Dump Trucks (including Rockbuggy and Truck with pups) up to and including 10 yards; Track Truck Equipment; Grease Truck; Flat Beds, dual rear axle; Hyster Operators (handling bulk aggregate); Lumber Carrier; Water Wagon, semi; Water Truck, dual axle; Gin Pole Truck, Winch Truck, Wrecker, Truck Mounted "A" Frame manufactured rating over 5 tons; Bull Lifts and Fork Lifts with Power Boom and Swing attachments, over 5 tons; Front End Loader with Forks; Bus Operator over 30 passengers; All Terrain Vehicles; Boom Truck/Knuckle Truck over 5 tons; Foam Distributor Truck/dual axle; Hydro-seeders, dual axle;

Vacuum Trucks, Truck Vacuum Sweepers; Loadmaster (air and water); Air Cushion or similar type vehicle; Fire Truck/Ambulance Driver; Combination Truck-fuel and grease;

Compactor (when pulled by rubber tired equipment); Rigger (air/water/oilfield); Ready Mix, up to and including 7 yards;

GROUP 5: Gravel Spreader Box Operator on Truck; Flat Beds, single rear axle; Boom Truck/Knuckle Truck up to and including 5 tons; Pickups (Pilot Cars and all light duty vehicles); Water Wagon (Below 250 Bbls); Gin Pole Truck, Winch Truck, Wrecker, Truck Mounted "A" Frame, manufactured rating 5 tons and under; Bull Lifts and Fork Lifts (fork lifts with power broom and swing attachments up to and including 5 tons); Buffer Truck; Tack Truck; Farm type Rubber Tired Tractor (when material handling or pulling wagons on a construction project); Foam Distributor, single axle; Hydro-Seeders, single axle; Team Drivers (horses, mules and similar equipment); Fuel Handler (station/bulk attendant); Batch Truck, up to and including 7 yards;

Gear/Supply Truck; Bus Operator, Up to 30 Passengers;

Rigger/Swamper

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

FOR OFFICIAL USE ONLY

IDT Switchgear (AM#04) FTG192

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Utility Outage Requests

Utility Connection Requests

Excavation Permits

Welding Permits

Salvage Plan; G

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The Base Contract work includes:

a. Provide and install two modular shielded switchgear enclosures with associated auxiliary equipment installed to replace existing non-shielded transformers and incidental related work. AM#04... The combined area of the two enclosures plus one half of the area of the bolt-on snow vestibules shall not exceed 1400 square feet. ...AM#04

As for contract options, the following items shall be included:

a. IDT Coordination Improvements.

b. Shielded Manhole Cover Replacement and Upgrades.

c. R&C Shielded Conduit Replacement.

1.2.2 Location

The work is located at the Ft. Greely, Alaska facilities, approximately as indicated. The exact location will be shown by the Contracting Officer.

1.3 WORK RESCHEDULING

Normal duty hours for work are from 7:00 a.m. to 5:00 p.m., Monday through Friday. Requests for additional work requires written approval from the Contracting Officer 7 days in advance of the proposed work period.

SECTION 01 11 00 Page 1

1.7.2 Construction Activities

All construction activities shall be planned and performed in a manner to avoid or minimize any affect on operating equipment. All construction activities will be coordinated with the facility user through the Contracting Officer. The Contractor's schedule as provided in Section 01 32 01.00 10 PROJECT SCHEDULE will need to provide sufficient detail of the work tasks in order for the facility users, through the Contracting Officer, to evaluate potential impacts to facility operations and coordinate activities; Such as the Construction and Demolition/Work Plan, shall include information which details the project phasing, construction sequencing, demolition, temporary systems and required notifications to enhance the coordination needed to accomplish the project while providing minimal impact and risk to building operations. This plan shall be submitted for Government approval prior to commencing work.

AM#04...

1.7.2.1 Construction Free Zone (CFZ)

a. The Construction Free Zone (CFZ) needs to be in place first unless there is earthwork to be done that will interfere with the new CFZ fence. The purpose of the CFZ fence is to help minimize the number of security escorts needed to satisfy MDC escorting requirements. It does not need to be a security fence. The CFZ fence can tie in to the existing taut wire fence and can be any standard temporary fencing, such as chain link or plastic per approval of the Contracting Officer.

b. The FE6 fence for the new perimeter needs to be installed before the existing taut wire fence that is between the project area and IDT compound can be demolished. This is true even when trenching between the new switchgear pad area and the IDTs and the manholes.

c. There is a fence proximity restriction of 10 feet only on the taut wire fence that is currently around the site. The fence proximity restriction in this case is the area in which no materials may be stored or vehicles parked. Additionally care should be taken to avoid walking within the area. There is no proximity restriction on the temporary CFZ fence. Any time work is being done inside the taut wire perimeter, security escorting is required.

...AM#04

1.8 DISPOSITION OF MATERIALS

1.8.1 Construction Debris

The Contractor shall comply with the requirements of the U.S. Army Space and Missile Defense Command Materials and Waste Management Procedures for Fort Greely, Alaska. The point of contact for waste disposal at Fort Greely is Ms Sandi Delong at (907)873-4381.

The Fort Greely disposal area located near the borrow pit can be used for disposal of inert construction debris. All material to be disposed of in the disposal area must be authorized by the Contracting Officer. The Contractor shall submit a request indicating the type and amount of material to be disposed. Authorized material shall be disposed of in the location and as dictated by the Contracting Officer. All contractor's unauthorized material shall be removed from Fort Greely and disposed of by the Contractor.

SECTION 01 19 30.00 29 Page 10

1.8.8 Salvageable Material

Salvageable material, if not otherwise indicated, shall become the property of the Contractor. The value of such salvage shall be reflected in the contract price.

1.8.9 Disposal of Soils

No existing soil stockpile shall be moved from its present location without written permission from the Contracting Officer. No soils shall be removed from the installation for off-site disposition. Soils may be temporarily removed from the installation when approved for off-site remediation. Such soils shall be properly tracked and fully accounted for until returned to the installation and shall not be mixed with other soils at any time. AM#04... The Contractor may utilize the Ft. Greely borrow pit for both fill and disposal of materials from and to the MDA. The Contractor shall coordinate with the Contracting Officer as there may be limited quantities of prescreened classified material available for the project. ...AM#04 Refer to Fort Greely policies at the end of this section.

1.9 HEMP SHIELD

The work required by this contract does include penetration of or attachment to the HEMP shield. The Contractor shall not penetrate the HEMP shield except as specifically approved by the Contracting Officer.

No welding to the HEMP shield will be permitted unless it is approved by and coordinated through the Contracting Officer. Any anchorage to floor that requires drilling and anchor bolts shall not penetrate the floor shield. If the HEMP shield is damaged by the Contractor, it shall be repaired and tested as directed by the Contracting Officer.

1.10 EXCAVATION CLEARANCE

Not used.

1.11 PARKING AND TRANSPORTATION

1.11.1 Parking Plan and Restrictions

Contractor's Personnel may not bring privately owned vehicle "POV's" into the MDC. The Contractor shall submit to the Resident Engineer a "Parking Plan" for Government approval. In the plan the contractor shall request to park their POV's and/or commercial vehicles and equipment along Fire Break Road west of the sprung structure in the existing gravel parking area. The Plan shall clearly show a marked area and posted signs designating this parking lot, showing the boundaries and dimensions, to avoid any pedestrian or vehicle traffic impacts to the surrounding sensitive security systems. The plan shall show the route to the work area including areas that the contractor is free to access without escorts. The plan must state that "No wondering outside the parking boundaries or travel routes is allowed without an escort".

The Contractor is responsible for coordinating, organizing, and implementing this Parking Plan.

1.11.2 Personnel Transportation

The Contractor shall submit to the Resident Engineer the procedure of

SECTION 01 19 30.00 29 Page 12

e. Facility Systems Operation and Maintenance Manuals (Reference Section 01 78 00 CLOSEOUT SUBMITTALS and Section 01 78 00 OPERATION AND

MAINTENANCE DATA).

All requests for commissioning submittals, lists, schedules, etc. shall be submitted directly to the Contracting Officer.

1.4 COMMISSIONING TEAM

The Commissioning Team Members are defined in this section as:

a. Commissioning Authority - USACE-Alaska District.

b. Government's Facility Representative - MDA/DPF

c. Construction Contractor Commissioning Team Representative - Contractor.

1.5 FACILITY SYSTEMS TO BE COMMISSIONED

As a minimum, the commissioning of the following equipment in this project shall be completed after the Designer of Record has completed his final design. This is a partial list; additional items will be required based on Contractor final design.

The systems to be commissioned are listed below:

a. Electrical power supply system energization.

(1) SUS (Switch, Transformer, Switchgear).

(2) MCC.

(3) Panelboards.

(4) Low Voltage Transformers.

(5) UPS.

(6) FPP PCMS remote control operation.

(7) Medium Voltage Conductors and Terminations.

(8) All new electrical equipment and systems AM#04...(Options #0010 and #0011 #0009)...AM#04.

b. HEMP System AM#04...(including Options #0006, #0007, and #0008, and

#0009)...AM#04.

c. New HEMP Filters.

d. PLC to Site Control Monitoring System (SCMS) Interface Test.

e. PLC to Power Control Monitoring System (PCMS) Interface Test.

f. Power Quality Monitoring System (PQMS).

g. HVAC Systems.

SECTION 01 91 00 Page 3 emergency power to the control and redundant compressed air system.

Power assist system shall include the following:

a. Pressure regulator and air control valve to control the speed and direction of the door.

b. Provide pneumatic mechanism to power assist.

c. Air control valve operable from inside or outside.

d. Allowance for manual operation within 15 seconds should loss of air pressure occur.

AM#04...

2.6.2 Threshold Protectors

Provide threshold protectors for each of the HEMP shielded doors with a raised threshold. Protectors shall consist of portable ramps that protect the threshold when equipment carts or other wheeled vehicles are used to move articles across threshold. Ramps may be asymmetrical to account for different floor elevations on each side, but slope of ramp shall not exceed 8:1 on either side. Ramps for a single-wide door shall be designed to support a 500 pound force applied to a 3 inch by 1/2 inch footprint for cargo loading. Footprint contact area shall be anywhere on the threshold seal area covered by threshold protector. Provide mounting brackets, convenient to the entry, to store ramp when not in use.

...AM#04

2.6.2 HEMP Shielded Door and Hatch Locks, Interlocks, Indicating Lights, and Alarms

2.6.2.1 Interlocks

Positive shielded door interlocks for multiple HEMP shielded doors configured as a PEV shall be provided such that, under normal conditions, the RF seal of only the inner or only the outer door or doors of a PEV door set can be broken at a time (i.e., the integrity of the host facility shielded volume is maintained during passing through a PEV door set).

Local override of the interlock in the event of emergency, circuit malfunction, or if one of the doors is inadvertently left open shall be provided. Remote override of the interlock from fire alarm or other emergency alarm systems shall be provided. Doors shall be provided with a mechanical emergency open pushbutton that releases air pressure on the seals.

2.6.3 Indicating Lights

Door status indicating lights shall be provided on the outside of the outer door(s) and on the inside of the inner door(s) of each vestibule shielded door set. The lights shall turn on steady to indicate the OPEN or CLOSED status of the opposite doors of the set. The lights shall flash when both doors are open or when the door interlock override is activated.

The indicating light panel shall provide a warning that an alarm will sound if both doors are simultaneously open.

SECTION 08 34 49.00 20 Page 10

2.6.4 Alarms

An audible alarm shall be provided to indicate that AM#04... either a single door or hatch is open, or that one or more of the inner and outer both doors of a PEV are open, compromising the integrity of the host facility shielded volume. The alarm shall continue to sound until either the single door or hatch, or all inner or all outer (or both) PEV doors are closed or override switch is actuated ...AM#04. Low-voltage piezoelectric-type alarms in tamper-proof enclosures shall be installed in locations shown on the host facility HEMP design drawings. The sound intensity shall be 45 dBA minimum at 10 feet.

2.6.5 Door or Hatch Operation Counting Device

On the interior side of HEMP doors and hatches, provide electric or electronic device for counting open, close cycles of HEMP shielded doors or hatches if the manufacturer's recommended maintenance procedures schedule maintenance…