EIE378
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
PROPOSAL TITLE / LOCATION: F-35A AIRCRAFT WEATHER SHELTER, SQUAD #1, EIELSON AIR FORCE BASE, ALASKA (EIE378)
a. This amendment provides changes to the solicitation as indicated on the continuation pages of this document.
b. DUE DATE FOR FINAL PROPOSAL REVISIONS IS HEREBY EXTENDED TO 08 DECEMBER 2017 AT 1400 ALASKA TIME. Proposals shall be submitted in accordance w ith Section 00 21 00, paragraph 1.9, Proposal Submittals.
c. YOU ARE REQUIRED TO ACKNOWLEDGE RECEIPT OF THIS AMENDMENT ON THE REVERSE SIDE OF THE STANDARD FORM 1442.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 06-Dec-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911KB-17-R-0003
X 9B. DATED (SEE ITEM 11)
23-May-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
06-Dec-2017
CODE
U.S. ARMY ENGINEER DISTRICT, AK
CEPOA-CT (W911KB)
PO BOX 6898
JBER AK 99506-0898
W911KB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911KB-17-R-0003
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
a. The following drawings are substituted for the superseded documents/sections:
NONE
b. The following revised documents/sections are substituted for the superseded documents/sections: The identifier “AM#11” appears before and after new and/or revised materials, except as noted below.
SECTION 02 61 13 – EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
- Revised paragraph 3.8.1 (Reissuing entire specification).
NOTE: Revisions within the following documents do not contain the above referenced identifiers:
SECTION 00 11 00 – STANDARD FORM 1442
- The required response time/date has changed from 07-Dec-2017 02:00 PM to 08-Dec-2017
02:00 PM
c. The following sections are deleted:
d. The following documents are added:
e. The following revisions are incorporated:
f. Other:
(End of Summary of Changes)
ALL OTHER TERMS AND CONDITIONS SHALL REMAIN THE SAME.
F-35A AIRCRAFT WEATHER SHELTER (SQD 1) W911KB-17-R-0003
EIE378 AM#11
SECTION TABLE OF CONTENTS
DIVISION 02 - EXISTING CONDITIONS
SECTION 02 61 13
EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
PART 1 GENERAL
1.1 MEASUREMENT AND PAYMENT
1.1.1 Measurement
1.1.2 Payment
1.1.2.1 Excavation and Transportation
1.1.2.2 Backfilling
1.1.2.3 Stockpiling
1.2 REFERENCES
1.3 DESCRIPTION OF WORK
1.3.1 Scheduling
1.3.2 Work Plan
1.3.3 Other Submittal Requirements
1.4 SUBMITTALS
1.5 REGULATORY REQUIREMENTS
1.5.1 Permits and Licenses
1.5.2 Air Emissions
1.5.3 AM#7... Chemical Testing ...AM#7
PART 2 PRODUCTS
2.1 SPILL RESPONSE MATERIALS
2.2 BACKFILL
PART 3 EXECUTION
3.1 SURVEYS
3.2 EXISTING STRUCTURES AND UTILITIES
3.3 CONTAMINATED MATERIAL REMOVAL
3.3.1 Excavation
3.3.2 Shoring
3.3.3 Dewatering
3.4 CONFIRMATION SAMPLING AND ANALYSIS
3.5 CONTAMINATED AND POTENTIALLY CONTAMINATED MATERIAL STORAGE
3.5.1 Long Term and Short Term Stockpiles
3.5.2 Liquid Storage
3.6 SAMPLING
3.6.1 Sampling of Stored Material
3.6.2 Sampling Liquid
3.6.3 Sampling Beneath Storage Units
3.7 SPILLS
3.8 BACKFILLING
3.8.1 Confirmation Test Results
3.9 CLOSURE REPORT
-- End of Section Table of Contents --
Section 02 61 13 Page 1
Section 02 61 13 Page 2
SECTION 02 61 13
EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
PART 1 GENERAL
1.1 MEASUREMENT AND PAYMENT
1.1.1 Measurement
Measurement for excavation and onsite transportation shall be based on the actual number of cubic yards of contaminated material in-place prior to excavation. Determination of the volume of contaminated material excavated shall be based on cross-sectional volume determination reflecting the differential between the original elevations of the top of the contaminated material and the final elevations after removal of the contaminated material. Measurement for backfilling of excavated areas shall be based on in-place cubic yards of compacted fill. Measurement for construction of stockpile areas shall be based on the number of square yards of stockpile liner constructed.
1.1.2 Payment
1.1.2.1 Excavation and Transportation
Compensation for excavation, onsite transportation of contaminated material, and transportation for disposal will be paid as a unit cost. This unit cost shall include any other items incidental to excavation and handling not defined as having a specific unit cost.
1.1.2.2 Backfilling
Compensation for backfill soil, transportation of backfill, backfill soil conditioning, backfilling, compaction, and geotechnical testing will be paid as a single unit cost.
1.1.2.3 Stockpiling
AM#9... All soils excavated within the areas designated for 100% stockpiling will require stockpiling on liners. Areas designated for 100% stockpiling are shown on drawing C-102. Additionally, location where long term stockpiles will be constructed is identified on drawing C-102.
A minimum of three long-term stockpiles shall be constructed as directed by the Contracting Officer. The intent is to segregate soils potentially contaminated with perfluorooctanesulfonic acid/perfluoroctanoic acid (PFOS/PFOA) from soils potentially contaminated with petroleum, oil, and lubricants (POL). Previous sample results indicate the contaminants are not co-mingled. Of the minimum three stockpiles, two of the stockpiles will be for potentially contaminated POL soils. POL contaminated soil shall be separated into one stockpile with photoionization detector (PID) reading less than 20 parts per million (ppm) and one with PID readings equal to or greater than 20 ppm.
The Contractor will not dispose of soils potentially contaminated with
Section 02 61 13 Page 3
PFOS/PFOA but will maintain these long term stockpiles until the project's Beneficial Occupancy Date (BOD). For other long term stockpiles, soils with contaminant levels that exceed action levels shall be disposed off site. Clean soils shall be disposed of at a location identified by the Contracting Officer within 7 miles of the project site. See Proposal Schedule for separate CLIN for disposal of POL Contaminated soils and disposal of clean soils.
In addition, soils excavated outside the areas designated for 100% stockpiling with PID readings equal to or greater than 20 ppm shall be placed in a short term stockpile. Short term stockile locations are shown on G-102. Compensation for construction of short term stockpiles will be paid for as a unit cost. This unit cost shall include all aspects of grading, preparation, handling, placement, maintenance, removal, treatment, and disposal of stockpile cover materials and liner materials and all other items incidental to construction of stockpiles. ...AM#9
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D5434 (2012) Field Logging of Subsurface Explorations of Soil and Rock
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
STATE OF ALASKA ADMINISTRATIVE CODE (AAC)
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1926 Safety and Health Regulations for Construction
40 CFR 302 Designation, Reportable Quantities, and Notification
1.3 DESCRIPTION OF WORK
The work consists of excavation, temporary storage, and disposal of of petroleum, oils, and lubricants (POL) contaminated material and potentially perfluorooctanesulfonic acid (PFOS) contaminated material. Reference Appendix A/sheet C-102 for further detail on areas requiring 100% stockpiling and sampling, and areas requiring active screening and subsequent stockpiling if POL contamination is identified.
Test boring locations can be found in the Chemical Data and Geotechnical Reports. Sample results exceeded Alaska Department of Environmental Conservation (ADEC)soil cleanup levels as follows; perfluorooctanesulfonic acid (PFOS) marginally exceeded the cleanup level in boring AP-6026 (10-14 feet below ground surface (bgs); gasoline range organics (GRO) exceedance in AP-6023 (10-11 feet bgs); and polynuclear aromatic hydrocarbons (PAHs) exceeded in borings AP-6034 (5-6 feet bgs) and AP-6039 (0-2 feet bgs).
Section 02 61 13 Page 4
Although associated laboratory results did not exceeced cleanup levels, elevated photoionization detector (PID) readings were identified in borings AP-6042 and AP-6023; these borings are located in the northwest corner of the proposed site near a historic buried pipeline break. The building footprint is within ST020, otherwise known as OU1, which potentially has BTEX and vinyl chloride in the soil and BTEX in the ground water. . Submit a Work Plan as specified below. Notify the Contracting Officer if contaminated material is discovered that has not been previously identified or if other discrepancies between data provided and actual field conditions are discovered.
1.3.1 Scheduling
Notify the Contracting Officer 30 calendar days prior to the start of excavation of contaminated material. The Contracting Officer will be responsible for contacting regulatory agencies in accordance with the applicable reporting requirements.
1.3.2 Work Plan
AM#9... A programmatic Uniform Federal Policy for Quality Assurance Project Plan (UFP-QAPP) has been developed for the F-35 Beddown program and will be provided to the contractor. The contractor shall amend the programmatic UFP-QAPP as necessary for this project. ...AM#9
Submit a Work Plan and compliant UFP-QAPP for approval within 60 days prior to starting work at the site. No work at the site, with the exception of site inspections and surveys, shall be performed until the Work Plan is approved. Allow 60 calendar days in the schedule for the Government's, ADEC's, and the U.S. Environmental Protection Agency's (EPA's)review. No adjustment for time or money will be made if resubmittals of the Work Plan are required due to deficiencies in the plan. At a minimum, the Work Plan shall include:
a. Schedule of activities.
b. Method of excavation and equipment to be used.
c. Shoring or side-wall slopes proposed.
d. Storage methods and locations for liquid and solid contaminated material.
e. Borrow sources and haul routes.
f. Decontamination procedures.
g. Spill contingency plan.
h. Disposal plan
1.3.3 Other Submittal Requirements
Submit separate cross-sections of each area before and after excavation and after backfilling, test results, and copies of the Closure Report within 14 calendar days of work completion at the site.
Section 02 61 13 Page 5
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Note that ADEC and EPA approval will also be required for the Work Plan and the Closure Report. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Work Plan; G
SD-02 Shop Drawings
Surveys
SD-06 Test Reports
Closure Report; G
1.5 REGULATORY REQUIREMENTS
1.5.1 Permits and Licenses
AM#9... Obtain required federal, state, and local permits for excavation, storage, and transportation of contaminated material. Permits shall be obtained at no additional cost to the Government. Excavations deeper than 6 inches require an approved Base Civil Engineering Work Clearance Request (AF Form 103).
Where soils are transported off base, Contractors shall submit an Alaska Dept. of Environmental (ADEC) "Transport, Treatment, & Disposal Approval Form for Contaminated Media" to the Tanks & Spills Program Manager (907-377-5209) for submission to ADEC. The form is available online at https://dec.alaska.gov/spar/csp/guidance_forms/csguidance.htm. ADEC approval shall be secured prior to transport off-base. The project will not include the diposal or treatment of soil potentially contaminated with PFOS/PFOA or PFOS/PFOA comingled with POL. ...AM#9
1.5.2 Air Emissions
Air emissions shall be monitored and controlled in accordance with Section
01 57 20.01 29 ENVIRONMENTAL PROTECTION.
1.5.3 AM#7... Chemical Testing ...AM#7
AM#7... Required sampling and chemical analysis shall be conducted in accordance with the DOD QSM and 18 AAC 75. Note that PFOS/PFOA analysis must be performed by a laboratory that is Environmental Laboratory Accreditation Program (ELAP) accredited under QSM version 5.1 (PFAS by LCMSMS Compliant with QSM 5.1 Table B-15). ...AM#7
Section 02 61 13 Page 6
PART 2 PRODUCTS
2.1 SPILL RESPONSE MATERIALS
Provide appropriate spill response materials including, but not limited to the following: containers, adsorbents, shovels, and personal protective equipment. Spill response materials shall be available at all times when contaminated materials/wastes are being handled or transported. Spill response materials shall be compatible with the type of materials and contaminants being handled.
2.2 BACKFILL
Backfill shall be placed in accordance with other sections of these specifications, as appropriate. Excavated materials conforming to specification requirements for materials to be used for fills, backfilling, grading or topsoiling, may be utilized provided there are no indications of contamination as defined herein.
Backfill material shall be tested for the parameters listed below at a frequency of once per 3000 cubic yards. A minimum of one set of classification tests shall be performed per borrow source. One backfill sample per borrow source shall also be collected and tested for the chemical parameters listed below.
Chemical Parameter Test Frequency Criteria
GRO, DRO, RRO, PAHs, VOCs, and PFOS/PFOA
One per 3000 cubic yards Most stringent applicable ADEC Table B1/B2 criteria (Under 40 Inch)
Do not use material for backfill until borrow source chemical and physical test results have been submitted and approved.
PART 3 EXECUTION
3.1 SURVEYS
Perform surveys immediately prior to and after excavation of contaminated material to determine the volume of contaminated material removed. Also, perform surveys immediately after backfill of each excavation. Provide cross-sections on 25 foot intervals and at break points for all excavated areas. Locations of confirmation samples shall also be surveyed and shown on the drawings.
3.2 EXISTING STRUCTURES AND UTILITIES
No excavation shall be performed until site utilities have been field located. Take the necessary precautions to ensure no damage occurs to existing structures and utilities. Damage to existing structures and utilities resulting from the Contractor's operations shall be repaired at no additional cost to the Government. Utilities encountered that were not previously shown or otherwise located shall not be disturbed without approval from the Contracting Officer.
Section 02 61 13 Page 7
3.3 CONTAMINATED MATERIAL REMOVAL
3.3.1 Excavation
Excavation shall be performed in a manner that will limit spills and the potential for contaminated material to be mixed with uncontaminated material. An excavation log describing visible signs of contamination encountered shall be maintained for each area of excavation. Excavation logs shall be prepared in accordance with ASTM D5434.
AM#9...Reference Appendix A/sheet C-102 for further detail on areas requiring 100% stockpiling, and areas requiring active screening and subsequent stockpiling if POL contamination is identified. Per ADEC guidance, soils from areas of known or discovered contamination (even with photo-ionization detector (PID) screening levels below 20 ppm) must be stockpiled separately and analytical samples must be collected to determine disposition of soils. Note that PFOS/PFOA contamination cannot be screened using a PID, and that potentially PFOS/PFOA contaminated soil should not be mixed with soil below cleanup levels. Soil shall be segregated into at least three stockpiles (soils presumed to be below cleanup levels, soils with PFOS contamination, and soils with POL contamination exhibiting PID readings >20 parts per million).
Soils excavated outside of the areas designated for 100% stockpiling shall be screened with a PID. Soils with screening values <20 ppm from these areas do not have to be placed on a liner and can be used for backfill or transported to clean fill areas without additional sampling. Excavated soils with PID readings equal to or greater than 20 ppm will have to be stockpiled on a liner and sampled prior to disposal. ...AM#9
3.3.2 Shoring
If workers must enter the excavation, it shall be evaluated, shored, sloped or braced as required by EM 385-1-1 and 29 CFR 1926 section 650.
3.3.3 Dewatering
Surface water shall be diverted to prevent entry into the excavation. No dewatering shall be performed without prior approval of the Contracting Officer. AM#9... Dewatering operations at sites with known contamination shall comply with Section 01 57 20.01 29 and requires approval from EPA Region 10 and ADEC. ...AM#9
3.4 CONFIRMATION SAMPLING AND ANALYSIS
AM#9... After the excavation reaches the limits necessary for consrtuction, confirmation samples shall be collected and analyzed for the following contaminants:
Chemical Parameter Action Level
GRO, DRO, RRO, PAH, VOCs (plus 10% low level VOCs), PAHs, and PFOS/PFOA
Most stringent applicable ADEC Table B1/B2 criteria (Under 40 Inch)
Screening and laboratory samples from the limits of excavation shall be collected at locations and at frequencies identified in the programmatic UFP-QAPP. Locations of samples shall be marked in the field and documented
Section 02 61 13 Page 8 on the as-built drawings. ...AM#9
3.5 CONTAMINATED AND POTENTIALLY CONTAMINATED MATERIAL STORAGE
Material shall be placed in temporary storage immediately after excavation.
The following paragraphs describe acceptable methods of material storage.
Storage units shall be in good condition and constructed of materials that are compatible with the material or liquid to be stored. If multiple storage units are required, each unit shall be clearly labeled with an identification number and a written log shall be kept to track the source of contaminated material in each temporary storage unit.
3.5.1 Long Term and Short Term Stockpiles
Stockpiles shall be constructed to isolate stored contaminated material from the environment. AM#9... A stockpile cross-section detail is attached to specification 01 57 20.01 29. ...AM#9 Stockpiles shall be constructed to include:
a. A chemically resistant geomembrane liner free of holes and other damage. Non-reinforced geomembrane liners shall have a minimum thickness of 20 mils. Scrim reinforced geomembrane liners shall have a minimum weight of 40 lbs/1000 square feet. The ground surface on which the geomembrane is to be placed shall be free of rocks greater than 0.5 inches in diameter and any other object which could damage the membrane.
b. Geomembrane cover free of holes or other damage to prevent precipitation from entering the stockpile. Non-reinforced geomembrane covers shall have a minimum thickness of 10 mils. Scrim reinforced geomembrane covers shall have a minimum weight of 26 lbs/1000 square feet. The cover material shall be extended over the berms and anchored or ballasted to prevent it from being removed or damaged by wind.
c. AM#9...Berms or wattles surrounding short term stockpiles shall be a minimum of 6 inches in height. Berms surrounding long term stockpiles shall be a minimum of 12 inches in height. Vehicle access points shall also be bermed ...AM#9.
d. The liner system shall be sloped to allow collection of leachate.
Storage and removal of liquid which collects in the stockpile, in accordance with paragraph Liquid Storage.
3.5.2 Liquid Storage
Liquid collected from excavations, stockpiles, and decontamination procedures shall be temporarily stored in 55 gallon drums or 250 gallon tanks. Liquid storage containers shall be water-tight and shall be located on site as indicated by the COR. The containers shall be properly labeled with the following: installation name and tracking number; waste category (RCRA or Non-RCRA); contents (IDW Water, etc); location; profile number (if appropriate); generator's point of contact (POC) including office phone number, installations POC and office phone number; and status (eg., "pending lab analysis"), as appropriate. A drum marking example is included as an attachment to specification 01 57 20.01 29.
Section 02 61 13 Page 9
3.6 SAMPLING
3.6.1 Sampling of Stored Material
AM#9... The contractor shall not collect samples from soil stockpiles potentially contaminated with PFOS/PFOA or comingled PFOS/PFOA and POL contamination. However, other short term and long term stockpiles shall be sampled to determine disposition of soils.
Representative samples of stored material shall be collected using incremental sampling methodology (ISM), and collection of incremental samples shall be collected in accordance with the 2012 Interstate Technology & Regulatory Council (ITRC) Incremental Sampling Methodology Guidance. ISM sample design must be clearly identified in the Work Plan.
Samples shall be tested for the following:
Chemical Parameter Action Level
GRO, DRO, RRO, PAHs, VOCs (plus 10% low level VOCs), and PFOS/PFOA
Most stringent applicable ADEC Table B1/B2 criteria (Under 40 Inch)
Where contaminant levels exceed the action levels soils shall be treated offsite with one exception. If laboratory results indicate that the soil is contaminated with PFOS/PFOA (or PFOS/PFOA comingled with POL), the contaminated soil shall be added to a long term stockpile constructed for PFOS/PFOA contaminated soil. Analyses for contaminated material to be taken to an offsite treatment facility shall conform to local, state, and federal criteria as well as to the requirements of the treatment facility.
Documentation of all analyses performed shall be furnished to the Contracting Officer. Additional sampling and analyses to the extent required by the approved offsite treatment, storage or disposal (TSD) facility shall be the responsibility of the Contractor and shall be performed at no additional cost to the Government. ...AM#9
3.6.2 Sampling Liquid
Liquid collected from excavations, storage areas, and decontamination facilities shall be sampled at a frequency of once for every 500 gal of liquid collected. Samples shall be tested for the following:
Chemical Parameter Action Level
GRO, DRO, RRO, PAHs, VOCs, and
PFOS/PFOA
ADEC ground water cleanup level
Liquid with contaminant levels that exceed action levels shall be treated offsite. Analyses for contaminated liquid to be taken to an offsite treatment facility shall conform to local, state, and federal criteria as well as to the requirements of the treatment facility. Documentation of all analyses performed shall be furnished to the Contracting Officer.
Additional sampling and analysis to the extent required by the approved offsite treatment, storage or disposal (TSD) facility receiving the material shall be the responsibility of the Contractor and shall be performed at no additional cost to the Government.
Section 02 61 13 Page 10
3.6.3 Sampling Beneath Storage Units
Samples from beneath each storage unit (stockpile or drum location) shall be collected prior to construction of and after removal of the storage unit. AM#9... Note that since the Contractor will not sample or dispose of PFOS/PFOA contaminated soil (or comingled PFOS/PFOA with POL contaminated soil), the Contractor shall only collect samples from beneath each storage unit prior to the constuction of these stockpiles. ...AM#9
Samples shall be collected AM#8... from the footprint of each stockpile using ISM techniques (each stockpile footprint will constitute one or more decision units with each decision unit having a maximum area of 10,000 square feet) ...AM#8 from a depth interval of 0 to 0.5 feet and shall be tested for the following:
Chemical Parameter Action Level
GRO, DRO, RRO, PAHs, VOCs , PFOS and
PFOA (PFOS)
Most stringent applicable ADEC Table B1/B2 criteria (Under 40 Inch)
Based on test results, soil which has become contaminated above action levels shall be disposed of in accordance with all Federal, State, and local regulations. Contaminated material which is removed from beneath the storage unit stockpiles shall be handled in accordance with paragraph Sampling of Stored Material. As directed by the Contracting Officer and at no additional cost to the Government, additional sampling and testing shall be performed to verify areas of contamination found beneath stockpiles have been cleaned up to below action levels.
3.7 SPILLS
In the event of a spill or release of a hazardous substance (as designated in 40 CFR 302), pollutant, contaminant, or oil (as governed by the Oil Pollution Act (OPA), 33 U.S.C. 2701 et seq.), notify the Contracting Officer immediately. If a spill occurs, follow the pre-established procedures as described in the Base Wide Contingency Plan for immediate reporting and containment. Immediate containment actions shall be taken to minimize the effect of any spill or leak. Cleanup shall be in accordance with applicable federal, state, and local regulations. As directed by the Contracting Officer, additional sampling and testing shall be performed to verify spills have been cleaned up. Spill cleanup and testing shall be done at no additional cost to the Government.
3.8 BACKFILLING
3.8.1 Confirmation Test Results
AM#11... Excavations shall be backfilled immediately after confirmation samples have been collected from the limits of excavation and the sample locations have been surveyed. ...AM#11 Backfill shall be placed and compacted to the lines and grades shown on the drawings.
3.9 CLOSURE REPORT
Submit 7 copies of a Closure Report within 14 calendar days of completing work at the site. The report shall be labeled with the contract number, project name, location, date, name of general Contractor, and the Corps of
Section 02 61 13 Page 11
Engineers District contracting for the work. This report can be combined with the Field Report needed in section 3.6 of specification 31 09 20.00
29. The Closure Report shall include the following information as a minimum:
a. A cover letter signed by a responsible company official certifying that all services involved have been performed in accordance with the terms and conditions of the contract documents and regulatory requirements.
b. A narrative report including, but not limited to, the following:
(1) site conditions, ground water elevation, and cleanup criteria;
(2) excavation logs;
(3) field screening readings;
(4) quantity of materials removed from each area of contamination;
(5) quantity of water/product removed during dewatering;
(6) sampling locations and sampling methods;
(7) sample collection data such as time of collection and method of preservation;
(8) sample chain-of-custody forms; and
(9) source of backfill.
c. Copies of all chemical and physical test results.
d. Copies of all manifests and land disposal restriction notifications.
e. Copies of all certifications of final disposal signed by the responsible disposal facility official.
f. Waste profile sheets.
g. Scale drawings showing limits of each excavation, limits of contamination, known underground utilities within 50 feet of excavation, sample locations, and sample identification numbers.
On-site stockpile, storage, treatment, loading, and disposal areas shall also be shown on the drawings.
h. Progress Photographs. Color photographs shall be used to document progress of the work. A minimum of four views of the site showing the location of the area of contamination, entrance/exit road, and any other notable site conditions shall be taken before work begins. After work has been started, activities at each work location shall be photographically recorded weekly. Photographs shall be a minimum of 3 by 5 inches and shall include:
(1) Soil removal and sampling.
(2) Dewatering operations.
(3) Unanticipated events such as spills and the discovery of additional contaminated material.
Section 02 61 13 Page 12
(4) Contaminated material/water storage, handling, treatment, and transport.
(5) Site or task-specific employee respiratory and personal protection.
(6) Fill placement and grading.
(7) Post-construction photographs. After completion of work at each site, take a minimum of four views of each excavation site.
A digital version of all photos shown in the report shall be included with the Closure Report. Photographs shall be a minimum of 3 inches by 5 inches and the following information shall be included:
Project Name: Direction of View:
Location: Date/Time:
Photograph No.: Description of View:
-- End of Section --
Section 02 61 13 Page 13
| SF30 |
| 02 61 13 |