Attachment 6 Questions and Answers.pdf
PDF 113 KB Posted
- Attached to
- Communications Infrastructure Upgrade Ft. Cavazos, TX Federal contract opportunity
- Solicitation number
- W9115123Q0078
About this file
This document contains questions and answers regarding communications infrastructure upgrade work at Fort Cavazos, Texas under solicitation W91151-23-Q-0078 from the Department of the Army Materiel Command Mission and Installation Contracting Command Fort Hood. The questions and answers specify connector types, fiber assignments, locations for terminating fibers and grounding equipment, procedures for pumping manholes if necessary, and references for mule tape strength. No other salient details are provided regarding required products or services.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 7 Questions and Answers Version 2.pdf | ||
| Attachment 3 Wage Determination 2015-5237 Revision No 22.pdf | ||
| Amendment W9115123Q00780003.pdf | ||
| Site Visit Sign in.pdf | ||
| Attachement 5 Confined Space Entry SOP 5AUG21.pdf | ||
| Amendment W9115123Q00780002.pdf | ||
| Attachment 1 Fort Cavazos Telecommunications Guide v2.pdf | ||
| W9115123Q00780001 Amendment.pdf | ||
| Attachment 4 SANEC VAL.pdf | ||
| RFQ W9115123Q0078.pdf | ||
| Attachment 2 FiberInstall_Map.pdf | ||
| Attachment 1 Ft. Cavazos Telecommunications Guide.pdf | ||
| Attachment 3 Wage Determination.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers W91151-23-Q-0078
1. What type of connectors will be on the bulkheads of the panels? i.e. SC/UPC, SC/APC, LC/UPC
“ST” type connectors shall be installed in B91078. B90132 does not require connectors as the FOC shall be coiled in the MH.
2. How many fibers will need to be terminated in each panel or existing splice enclosure?
The install depicts a 12 FOC shall be installed & all 12 fibers shall be terminated with “ST” type connectors.
3. What are the fiber assignments for the existing fiber enclosure?
The FOC name is: 91078 FOC 27, 1-12.
4. We were instructed at the onsite visit to leave 200' on the last manhole outside bldg. 90132.
Can you please provide the manhole number?
MH4112
5. In Building 91078 can you please specify the rack number, RU number, and panel number where the fiber will land?
Rack 3, Shelf 4, F 1-12
6. In Building 91078 can you please confirm the location of the grounding/bonding bus bar we are to use for a double-hole lug?
The ground bus bar is located at the top of Rack 4.
7. Do all Manholes have a built-in ladder?
No, all Manholes do not have ladders.
8. If we need to pump the manhole, what is the direction/process to pump, and are there any environmental issues we need to monitor?
All pumped water shall be diverted to either grass or dirt areas. Water shall not be directed to hard surface roads which will allow water to enter storm drains. The NEC POC shall be available for more conformation if manholes need to be pumped.
10. What strength mule tape needs to be left in the duct bank?
Reference the T-IDG, Section 6.11.1, f.