Exhibit B_ Projected Implementation Plan Chemistry VCZ.pdf

PDF 116 KB Posted

Attached to
Chemistry Testing - Cost Per Reportable Result
Solicitation number
W9114F-25-Q-A035
Issued by

About this file

The document is a Projected Implementation Plan for a Chemistry Testing contract for the U.S. Army Health Clinic in Vicenza, Italy. The implementation timeline spans from 01 July 2025 to 30 August 2025, with key milestones including contract award, instrument ordering and site walk-through within the first 10 business days, instrument delivery by 31 July 2025, instrument verification between 1-15 August 2025, and go-live with patient testing by 30 August 2025. The plan specifies that milestones can be completed earlier than the specified dates, providing flexibility in the implementation process.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Projected Implementation Plan

Date / Timeline Action

01 July 2025 Contract award within first 10 business days from contract award

Order instruments and conduct on-site walk through or virtual meeting with each site

31 JULY 2025* Instrument Delivery

1 - 15 AUGUST 2025* Instrument Verification Completed

30 AUGUST 2025 Go-Live with Patient Testing

*These are no later than dates. Milestones can be completed earlier then the dates specified.