Exhibit B_Projected Implementation Plan_ Clinical Chemistry.pdf

PDF 117 KB Posted

Attached to
Chemistry Testing - Cost Per Reportable Result
Solicitation number
W9114F-25-Q-A035
Issued by

About this file

The document is a Projected Implementation Plan for a clinical chemistry testing contract. The timeline outlines key milestones from contract award on 30 June 2025 through go-live with patient testing on 30 August 2025. Specific implementation steps include ordering instruments within 10 business days of contract award, conducting on-site or virtual meetings with each site, completing instrument delivery by 31 July 2025, and verifying instruments between 1-15 August 2025. The plan notes that milestones can be completed earlier than the specified dates, which are considered "no later than" deadlines.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Projected Implementation Plan

Date / Timeline Action

30 JUNE 2025 Contract award within first 10 business days from contract award

Order instruments and conduct on-site walk through or virtual meeting with each site

31 JULY 2025* Instrument Delivery

1 - 15 AUGUST 2025* Instrument Verification Completed

30 AUGUST 2025 Go-Live with Patient Testing

*These are no later than dates. Milestones can be completed earlier then the dates specified.