Exhibit B_Projected Implementation Plan_ Clinical Chemistry.pdf
PDF 117 KB Posted
- Attached to
- Chemistry Testing - Cost Per Reportable Result
- Solicitation number
- W9114F-25-Q-A035
- Issued by
-
Department of the Army Medical Command
About this file
The document is a Projected Implementation Plan for a clinical chemistry testing contract. The timeline outlines key milestones from contract award on 30 June 2025 through go-live with patient testing on 30 August 2025. Specific implementation steps include ordering instruments within 10 business days of contract award, conducting on-site or virtual meetings with each site, completing instrument delivery by 31 July 2025, and verifying instruments between 1-15 August 2025. The plan notes that milestones can be completed earlier than the specified dates, which are considered "no later than" deadlines.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Projected Implementation Plan
Date / Timeline Action
30 JUNE 2025 Contract award within first 10 business days from contract award
Order instruments and conduct on-site walk through or virtual meeting with each site
31 JULY 2025* Instrument Delivery
1 - 15 AUGUST 2025* Instrument Verification Completed
30 AUGUST 2025 Go-Live with Patient Testing
*These are no later than dates. Milestones can be completed earlier then the dates specified.