UNCLASSIFIED
SOURCE SELECTION SENSITIVE
Contract W5J9CQ-16-R-0008
Statement of Objectives For
Geospatial, Research, Integration, Development and Support (GRIDS III) Sample Task Order
Integrated 3D Wide Area Mapping Sensor System
1. Purpose.
The purpose of this sample cost plus fixed fee task order is to develop and deploy a new sensor with the ability to collect Nadir and off-Nadir images to allow for 3D image capability. The 3D capability is not for use in single target source images, but rather for large area capture to allow for a more robust 3D view of areas of interest. Particular attention should be focused on off-Nadir LIDAR and EO collections to support High Resolution 3D imagery in support of Mission Planning Rehearsal and situational awareness in conjunction with Non-Combatant Evacuation Operations (NEO). Overall Period of Performance for this task order will be twenty-four (24) months.
2. Scope.
The Contractor shall provide highly specialized expertise and technical services to execute the objectives of this SOO that directly correlates to the overarching objectives and goals of the AGC’s overall mission. The Contractor shall provide all personnel and supervision necessary to perform the services defined in the SOO. All tasks must be performed to the standards set forth in this document.
3. Period and Place of Performance
3.1 The basic contract period of performance is twenty-four (24) months with one base year of twelve (12) months and a twelve (12) month option.
3.2 The contractor shall provide on and off-site services in support of AGC’s tasks. Design, development, engineering and testing are expected to take place at CONUS locations.
4. Background. With past NEO missions showing a lack of planning information and with past analyses showing a need for better situational awareness, the AGC is seeking to increase situational awareness by incorporating 3D high resolution imagery into the pre-deployment phase of NEO. This effort seeks to develop an innovative 3D sensor capability to provide never before seen data imagery of a dense urban environment. This sensor(s) would allow for the collection and rapid production of 3D models of city wide areas to include ingress and egress for military forces.
The warfighter’s requirement for high-resolution terrain data has grown exponentially as has the requirement for accurate, timely high-resolution 3D elevation and imagery data to support current and future operations. High-resolution 3D geospatial information provides the foundation data necessary to produce geospatial products that provide the force multiplier necessary for successful operations. The goal of this project is to explore using high-resolution imagery capable of creating 3D models for mission critical situational awareness and battlefield intelligence in support of NEO mission planning and rehearsal.
5. Performance Objectives
AGC requires a contractor with the capability to manage a highly technical development and system integration effort.
This effort seeks to develop and test an innovative 3D LIDAR and EO sensing technology to collect and produce data capable of 3D model generation for mission rehearsals in relation to NEOs. The newly developed sensor will be able to quickly cover a large region using aerial manned and/or unmanned platforms to deliver large quantities of high resolution data which can then be delivered as 3D models to support required situational awareness and mission planning of NEO missions. This effort will focus on enhancing the government’s knowledge and understanding of LIDAR/EO combined imagery and its use in 3D high resolution model generation with the ability to collect high resolution data from an aerial platform. The contractor must also be capable of providing a team of highly qualified personnel that will be able to meet the following GRIDS III requirements:
5.1 Conduct Geospatial and Geospatial Intelligence (GEOINT) Systems research, development, engineering, analysis and operations, including identifying and addressing gaps in geospatial science & technologies.
5.1.1 The Contractor shall conduct GEOINT Systems research, development, engineering, analysis and operations, including identifying and addressing gaps. The contractor shall provide a sensor that will deliver to the government an improved NADIR and OFF NADIR, rapid, collection system to allow for dense urban environment 3D rendering and/or foliage penetration. The contractor is encouraged to utilize state of the art technology and provide new and innovative ideas to create a sensor that can provide data to satisfy the end state of providing 3D model generation of dense urban environments to a level of detail needed for mission rehearsals. Final products will include detailed 3D rendering of urban environments that may reduce in level of detail from center of city outward to the edges of the urban environment. Final products to be created from the data generated will include primary, secondary, and tertiary routes; landing zones, Line of Sight, and 3D details within the total city confines.
5.1.2 The contractor shall design a flight payload to allow for (T) manned or (O) unmanned operations.
5.1.3 High Altitude collection is desired (i.e. at the least, greater altitude than most Surface to Air threats). Resolution of final imagery must be at a minimum (O) .2 – (T) .5 meter posting LIDAR and (T) 5cm – (O) 2 cm for EO NADIR.
Final geo-registered, orthorectified color imagery should be at a minimum (O) 2-10 (T) cm resolution with (T) 1 meter
- .5 (O) resolution elevation data. Off NADIR resolution should be at a minimum (T) 20-10 (O) cm after final processing (orthorectified/geo-registered).
5.2 Integrate, execute and transition Command, Control, Communications, Computers, Cyber, Intelligence, Surveillance and Reconnaissance (C5ISR) concepts, processes and architectures. The Contractor shall integrate, execute and transition C5ISR concepts, processes and architectures. Developed sensor shall be integrated into standard technologies while allowing for state-of-the-art execution and transition into programs of record. The contractor will ensure capability performs to the standards or higher than current standards and can transition into common sensor programs.
5.3 Conduct experiments, demonstrations, and test and evaluation of software intensive systems that display data on a geospatial foundation.
5.4 The contractor shall assess accuracy, reliability, and operational utility of remote sensing and C4ISR geospatial intelligence collection systems. Final sensor may be a combination of newly developed and/or existing sensor technology adapted for this new mission. The contractor shall provide assessments of various collection systems and offer the government technical solutions with regard to the best solution
5.5 Perform vigorous Verification, Validation and Accreditation (VV&A) on emergent geospatial tools and methods to the standards and specifications documented in US Army regulation.
5.6 The contractor shall develop and apply new technologies and processes related to Geospatial/GEOINT Exploitation tools, FMV, ABI, SOM, AGI, WAMI and other trade crafts to this task. Other sensors that may improve capabilities are encouraged (i.e. IR, SAR/INSAR). Innovative collection parameters and ways to improve imagery detail in the final product are sought. Tools to combine processing techniques to take advantage of FMV with standard mapping collections will be considered.
5.7 Develop, integrate and operate ground segments/stations for the Intelligence, Surveillance and Reconnaissance (ISR) payload types (e.g., Electro-optical Infrared (EO/IR), Hyperspectral Infrared Sounder (HIS), Light Detection and Ranging (LIDAR), Radio Detection and Ranging (RADAR), Signals Intelligence (SIGINT), communications, etc.).
5.8 The contractor shall examine and evaluate technologies and tools from Government, Academia, and Industry including, but not limited to, C5ISR tools in relation to this task order. Any relevant technologies that may improve quality, promote increased sensor reliability/sustainability and/or ensure lower risk in final product are encouraged.
5.9 The contractor shall prepare all necessary documentation to support large scale enterprise geospatial services.
5.10 Develop and operate test suites of hardware and software that are capable of testing the exchange of geospatial data between Army mission command systems.
6. Operating Constraints
6.1 Management, Reporting, and Data Requirements
6.1.1 Propose the most comprehensive and cost effective Contract Data Requirement List (CDRL) tailored to the proposed design solution.
6.1.2 Employ appropriate life cycle management processes to ensure government investment is adequately administered
6.1.3 Use Standard project management tools and reporting procedures
6.1.4 Provide Scientific and Technical Reports
6.1.5 Report Status Monthly
6.1.6 Obtain sufficient rights in technical data, both software and hardware, such that the Government can maintain and modify any deliverables and/or end products using Government personnel and third party contractors.
6.2 Security Requirements
6.2.1 The contractor will be required to have access to Unclassified, For Official Use Only (FOUO), Secret, Top Secret (TS), and Sensitive Compartmented Information (SCI), during their performance of this contract. Contractor personnel requiring access to government data shall hold at least a Secret clearance and shall be eligible for access to Top Secret, and SCI data. A DD Form 254, Contract Security Classification specification, will be prepared by the ordering agency and issued with the task order, providing specific classification guidance.
6.2.2 All Key contractor personnel shall possess TOP SECRET clearance and be eligible for SCI adjudication on the start date of the period of performance. All remaining contractor personnel shall possess at a minimum SECRET clearances.
6.2.3 The contractor shall perform in accordance with the Department of Defense (DoD) Industrial Security Manual (DoD 5220.22M) and ensure that classified material is handled in accordance with the latest appropriate security classification specifications.
6.2.4 Loss or suspension of required security clearance as set forth on the DD Form 254, “Contract Security Classification Specifications”, would result in the contractor’s inability to perform in accordance with the terms and conditions of this contract. As a result of this failure to perform, the contractor is subject to termination under the appropriate termination clause herein.
6.2.5 Facility Requirements. Based on task order requirements, the contractor will be required to have a TOP SECRET facility clearance with SECRET safeguarding capabilities. The Contractor shall require access to Communications Security (COMSEC) information, SCI, Non-SCI intelligence information, and FOUO information. The Contractor shall also require access to the JWICS/SIPRNET/NIPRNET Systems. These are necessary to perform the C5ISR mission requirements and enable open access to sensor information required to develop and operate in a classified environment.
6.2.6 The Contractor shall comply with all applicable DoD security regulations and procedures during the performance of this contract. The Contractor shall not disclose and must safeguard procurement sensitive information, computer systems and data, Privacy Act data, and Government personnel work products that are obtained or generated in the performance of this contract. This includes dissemination of protocols and papers not generally available through the public literature.
6.2.7 Anti-Terrorism (AT) Awareness Training for Contractor Personnel Traveling Overseas. All US based contractor employees and associated sub-contractor employees traveling overseas will receive the government provided Area of Responsibility (AOR) specific AT awareness training prior to departure.
6.2.8 Contractor Employees Who Require Access to Government Information Systems. All contractor employees with access to a government info system must be registered in the Army Training Certification Tracking System (ATCTS) at commencement of services, and must successfully complete the DOD Information Assurance Awareness prior to access to the information systems and then annually thereafter IAW AR 380-67 (Personnel Security Program) and Homeland Security Presidential Directive 12 (Policy for a Common Identification Standard for Federal Employees and Contractors).
6.2.9 Handling Requirements: In performing this contract, the Contractor may receive and generate classified material, modify, or store classified hardware, have access to classified information outside the U.S, Puerto Rico, U.S.
possessions and trust territories, require a COMSEC account, have Operations Security (OPSEC) requirements, and be authorized to use the Defense Courier Service.
6.2.10 OPSEC Standing Operating Procedure/Plan. The Contractor shall develop an OPSEC SOP/Plan in accordance with AR 530-1, Operations Security, within 90 days of contract award. The OPSEC SOP/Plan must be reviewed and approved by the RA OPSEC Officer. The SOP/Plan will include the government's critical information, why it needs to be protected, where it is located, who is responsible for it, and how to protect it.
6.2.11 Key Control: The need for key control may be required based on this task order. Contractor personnel shall establish and implement methods of making sure all keys/key cards issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. NOTE: All references to keys include key cards. No keys issued to the Contractor by the Government shall be duplicated. The Contractor shall develop procedures covering key control that shall be included in the Quality Control Plan. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The Contractor shall immediately report any occurrences of lost or duplicate keys/key cards to the Contracting Officer.
6.2.11.1. In the event keys, other than master keys, are lost or duplicated, the Contractor shall, upon direction of the Contracting Officer, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks shall be deducted from the monthly payment due the Contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the monthly payment due the Contractor.
6.2.11.2. The Contractor shall prohibit the use of Government issued keys/key cards by any persons other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer.
6.2.12 Personal Identity Verification (PIV)
6.2.12.1 The Contractor shall comply with PIV procedures implemented by Homeland Security Presidential Directive- 12 (HSPD-12), Federal Information Processing Standards Publication (FIPS PUB) Number 201-1, Office of Management and Budget (OMB) Guidance M-05-24.
6.2.12.2 The Contractor shall insert this clause, FAR 52.204-9 as required by FAR 4.1303, in all subcontracts when the Subcontractor is required to have physical access to a Federally-controlled facility or access to a Federally-controlled information system.
6.2.12.3 In accordance with HSPD-12, OMB M-05-24 and FIPS 201-1, unless a previous favorable background investigation has been completed in the last ten (10) years, all Contractor employees shall be the subject of a background investigation conducted by the Government.
6.2.12.4 No Contractor employee shall commence work until the Personnel Security Questionnaire (PSQ) paperwork has been completed, reviewed and submitted to the Office of Personnel Management (OPM).
6.2.12.5 Contractor employees not meeting the minimum PIV requirements shall be the subject of a National Crime Information Center (NCIC) check prior to beginning work in addition to the submission of the PSQ to OPM.
6.2.12.6 Non-US citizens shall not be used in the performance of this contract unless the provisions of Army Regulation 25-2, Information Assurance have been fully completed and approval has been granted by the Government for the non-US citizen to perform the required mission.
6.2.13 Visit Notifications
6.2.13.1 If the Contractor has previously been granted a facility clearance (FCL) through the Defense Industrial Security Clearance Office (DISCO), the Contractor Facility Security Officer (FSO) shall submit visit notifications via Joint Personnel Adjudication System (JPAS) in the format prescribed and provided by AGC Security through the Government COR.
6.2.13.2 If the Contractor is not cleared through DISCO, the Contractor shall submit a signed visit request on company letterhead stationary through the Government COR. The request shall include the full name (last, first, middle), date of birth (MM/DD/YYYY), place of birth (city, state, country), citizenship, type of last investigation and date last investigation was completed, if any, and shall be the subject of a NCIC check prior to beginning work.
6.2.14 Regulations
All Contractor employees shall read all applicable security regulations, to be provided by the Government. Contractor personnel shall familiarize themselves with the Government’s regulations and policies and site-specific regulations regarding access to sensitive materials, computer facility/IT network access, issue of access credentials which shall be provided as required by the Government.
6.2.15 Physical Security
Some work shall be performed off the Government site however, when the Contractor is required to work on the Government site, the Contractor shall be responsible for safeguarding all Government information and property provided for contractor use based on direction from the COR as applicable. At the close of each work period, Government facilities, equipment, and materials shall be secured.
6.2.16 Access Credentials
The Contractor shall establish and implement methods of making sure all access credentials (CAC; DD Form 1466, DoD Building Pass) issued to the Contractor employees by the Government are not lost or misplaced and are not used by unauthorized persons. No access credentials issued to the Contractor by the Government shall be duplicated. The Contractor shall develop procedures covering access credentials that shall be included in the Quality Control Plan.
Such procedures shall include turn-in of any issued access credentials by Contractor personnel who no longer require access to Government information systems or Government facilities. The Contractor shall immediately report any occurrences of lost access credentials to the COR.
6.2.16.1 In the event access credentials are lost or damaged, the Contractor employee shall immediately notify the COR who will notify AGC Security of the loss or damage and request re-issue of the credential.
6.2.16.2. Multiple occurrences of loss or damaged access credentials shall be reported to the Contracting Officer.
When the replacement of access credentials is performed by the Government, the total cost of re-issuing the credential(s) shall be deducted from the monthly payment due the Contractor.
6.2.16.3 The Contractor shall prohibit the use of Government issued access credentials by any persons other than the Contractor employee to whom the credential is issued. The Contractor shall prohibit the opening of secure or locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the AGC Security Office.
6.2.17 Anti-Terrorism and Operations Security Requirements
6.2.17.1 AT Level I Training. All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: https://atlevel1.dtic.mil/at.
6.2.17.2 Access and General Protection/Security Policy and Procedures. Contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by the Government representative). The Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, Headquarters, Department of the Army (HQDA) and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
6.2.17.3 iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 15 calendar days of new employees commencing performance with the results reported to the COR NLT 45 calendar days after contract award.
6.2.17.4 Contractor Employees Who Require Access to Government Information Systems. All contractor employees with access to a Government info system must be registered in the ATCTS at commencement of services, and must successfully complete the DOD Information Assurance Awareness prior to access to the Information System (IS) and then annually thereafter.
6.2.17.5 For Contracts that Require OPSEC Training. Per AR 530-1, Operations Security, new contractor employees must complete Level I OPSEC training within 30 calendar days of their reporting for duty. All contractor employees must complete annual OPSEC awareness training and adhere to the organization’s security program.
6.2.17.6 For Information assurance (IA)/information technology (IT) training. All contractor employees and associated sub-contractor employees must complete the DoD IA awareness training before issuance of network access and annually thereafter. All contractor employees working IA/IT functions must comply with DoD and Army training requirements in DoDD 8570.01, DoD 8570.01-M and AR 25-2 within six months of employment.
6.2.17.7 For IA/IT certification. Per DoD 8570.01-M , DFARS 252.239.7001 and AR 25-2, the contractor employees responsible for IA/IT functions shall be appropriately certified upon contract award. The baseline certification as stipulated in DoD 8570.01-M must be completed upon contract award.
6.3 Key Personnel
6.3.1 Certain skilled experienced professional and/or technical personnel are essential for successful contractor accomplishment of the work to be performed under this task order. These are defined as "Key Personnel" and are those persons whose resumes are submitted for evaluation with this proposal. Key Personnel for this task order will be at the contractor’s discretion, but will include at a minimum a Task Order Lead, Systems Engineer, Software Engineer, and Hardware Engineer. The contractor shall notify the contracting officer in writing as to whom will fill these key personnel roles. Key personnel shall be available between 8:00 a.m. to 4:30p.m., Monday thru Friday except Federal holidays or when the government facility is closed for administrative reasons. A POC must be available for the key personnel in the event they are not available at these times (i.e. leave/ sick time).
6.3.2 The contractor shall notify the AGC Contracting Officer if they intend to substitute any individual serving as key personnel. In the event of such substitution/replacement, key personnel must have at least equivalent qualifications to the original individual intended to fill the specified role. Key personnel on this task order including subs, are subject to COR approval based on qualifications reviewed before they can be placed on this task order.
6.3.3. The Contractor shall submit their proposed key personnel to meet the Government’s needs based upon the key tasks within the SOO. The Contractor shall include the title of the key personnel, the qualifications to meet the Government need as well as the educational experience necessary to successfully perform as the key personnel on the task.
6.4 Access to and Disclosure of Information
6.4.1 The contractor may require access to data and information proprietary to a Government agency, another Government contractor, or of such nature that its dissemination or use, other than as specified in this contract, would be adverse to the interests of the Government or others. Neither the contractor, nor contractor employees shall divulge or release data or information developed or obtained under performance of this contract, except to authorized Government personnel or upon written approval of the COR or designated representative. The contractor shall not use, disclose, or reproduce proprietary information bearing a restrictive legend, other than as specified in the contract.
6.4.2 Disclosure of information regarding operations and services of the activity to persons not entitled to receive it, or failure to safeguard any classified, proprietary or other similar items or information that may come to the contractor (or any persons under the contractor’s control) in connection with work under this contract, may subject the contractor, contractor’s agent, or employees to criminal liability under Title 18, Sections 793 and 798 and/or other sections of the United States Code. Neither the contractor nor the contractor’s employees shall disclose or cause to be disseminated, any information concerning the operations of the activity that could result in, or increase the likelihood of, the possibility of a breach of the activities’ security or interrupt the continuity of operations.
6.4.3 The contractor shall direct to the COR, all inquiries, comments, or complaints arising from matters observed, experienced, or learned as a result of, or in connection with the performance of this contract, the resolution of which may require the dissemination of official information.
6.4.4 Inquiries received by the contractor for work performed under this contract shall be referred to the Government for evaluation under the Freedom of Information Act (FOIA) of 1975, Public Law 93-502, 5 U.S.C., Section 552. The AGC legal counsel shall be responsible for determining whether such requests will be honored. The contractor will not release any information concerning the project to the public without written authorization from the Government.
6.4.5 The contractor shall not release any information (including photographs, files, public announcements, statements, denials, or confirmations) on any part of the subject matter of this contract, or any phase of any program hereunder, without the prior written approval of the COR. The contractor shall not release information regarding individuals without prior authority of the COR. Any documentation showing individuals’ names or other personal information will be controlled and protected. The provisions of the Privacy Act of 1974, Public Law 93-579, 5 U.S.C., Section 552a, shall apply.
6.5 Travel
6.5.1 Area of Travel. The Contractor may be required to travel to several locations within the CONUS to support the development of demonstration, exercises and/or experiments. Specifically, travel may include testing the prototype at several locations to include but not limited to: Fredericksburg, VA; Manassas, VA; Hanscom AFB, MA; Yuma, AZ;
Camp Pendleton, CA; and White Sands Missile Range, NM.
6.5.2 Travel Policy. The Government will reimburse the Contractor for allowable travel costs incurred by the Contractor in performance of the contract and determined to be in accordance with FAR subpart 31.2, subject to the following provisions: Travel required for tasks assigned under this contract shall be governed in accordance with rules set forth for temporary duty travel in the Department of Defense Joint Travel Regulations (JTR). All travel and expenses must be approved by the COR in writing, prior to travel.
6.5.3 Travel, subsistence, and associated labor charges for travel time are authorized for travel beyond a 50-mile radius of the local office, whenever a task assignment requires work to be accomplished at an alternate work site. No travel, subsistence or associated labor charges for travel time shall be charged for work performed within a 50-mile radius of the Contractor’s local office, normal work site, or temporary work site unless approved in advance by the Contracting Officer Representative (COR). Under no circumstances will costs be reimbursed for travel performed for personal convenience and daily travel to and from the normal work site, to include parking expenses.