AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of

2. Amendment/Modification No.

3. Effective Date

4. Requisition/Purchase Req No.

5. Project No. (If applicable)

6. Issued By Code 7. Administered By (If other than Item 6) Code

8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)

9A. Amendment Of Solicitation No.

9B. Dated (See Item 11)

10A. Modification Of Contract/Order No.

10B. Dated (See Item 13) Code Facility Code

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting And Appropriation Data (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS

It Modifies The Contract/Order No. As Described In Item 14.

A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In

The Contract/Order No. In Item 10A.

B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set

Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).

C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:

D. Other (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.

14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. Name And Title Of Signer (Type or print)

16A. Name And Title Of Contracting Officer (Type or print)

15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed

By (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITIONS UNUSABLE

30-105-02 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

SEE SCHEDULE

X

Firm Fixed Price

0001 2017AUG23

W58RGZ

ARMY CONTRACTING COMMAND-REDSTONE

REDSTONE ARSENAL AL 35898-5280

DAWN PATTERSON

EMAIL: DAWN.P.PATTERSON2.CIV@MAIL.MIL

W58RGZ-17-R-0220

2017AUG03

X

X 2017SEP15 03:00pm

/SIGNED/

2 signed

SEE SECOND PAGE FOR DESCRIPTION

1 4

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION A - SUPPLEMENTAL INFORMATION

Buyer Name: DAWN PATTERSON

Buyer Office Symbol/Telephone Number: CCAM-AL-M/(256)842-5181

Type of Contract 1: Firm Fixed Price

Kind of Contract: Maintenance Contracts

*** End of Narrative A0000 ***

1. Reserved.

2. This is a five (5) year Firm-Fixed-Price (FFP) Indefinite Delivery Indefinite Quantity (IDIQ) contract pursuant to FAR 52.216-22

3. There is an adequate Depot Maintenance Work Requirement (DMWR) and applicable Maintenance Engineering Order(s) (MEOs) for the Overhaul/Repair of the UH-60 Actuator. This is a 100% Small Business Set-

Aside.

4. When Applicable, the contractor is reminded to complete the Foreign Military Sales (FMS) Customer DA FORM 2410 (Component Removal and Repair Overhaul Record), submitted with the item for repair, in accordance with DA Pamphlet 738-751 and TB-1500-341-01. Upon completion of repair, if authorized, the contractor is reminded to fill out U.S. Army DA Form 2410 and return it to the FMS customer with the repaired asset(s), along with the FMS customer version of the DA Form 2410.

5. The FMS Customer and geographical location(s) for deliveries, inspection and acceptance points are unknown at this time.

6. Subject to the availability of funds, any quantities ordered will be priced at the unit price established for the ordering period in which they are ordered. Funds shall be obligated by issuance of Delivery Orders and not by the contract itself.

7. The minimum quantity set forth herein shall be obligated on Delivery Order (DO) 0001, to be issued simultaneously with the award of the contract. Any additional quantities ordered will be priced at the firm fixed price in effect during the ordering period in which they are ordered.

8. The Government will not be required to obtain the contractor's signature prior to the issuance of an order.

9. Reserved.

10. The Government has segregated the estimated quantities into five ordering periods. However, this does not preclude exercising the

Government's right under FAR 52.216-19 by ordering the maximum quantity specified in FAR 52.216-19(b)(1) at any time during the five year ordering period.

Ordering Period 1 will be from date of contract award through 365 days after contract award (DACA).

Ordering Period 2 will be from 366 DACA through 730 DACA.

Ordering Period 3 will be from 731 DACA through 1,095 DACA.

Ordering Period 4 will be from 1,096 DACA through 1,460 DACA.

Ordering Period 5 will be from 1,461 DACA through 1,825 DACA.

11. Please insert your firm fixed unit prices for the 1st, 2nd, 3rd, 4th, and 5th ordering periods in the spaces provided under each

CLIN/SubCLIN.

12. For purposes of Block 12 on page 1, the offer acceptance period is 120 days from the date for receipt of offers specified in Block

9, unless a different period is inserted by the offeror in the blank in Block 12.

13. No Government Furnished Materials (GFM), other than the reparable assets and reusable containers, will be provided.

14. Offers shall be submitted in accordance with FAR Clause 52.212-1. Facsimile and electronic submissions are not authorized.

Proposals shall be mailed to:

Army Contracting Command - Redstone

ATTN: Dawn P. Patterson, CCAM-ALM

Bldg. 5303, 2nd Floor

Redstone Arsenal, AL 35898-5280

15. If any offeror chooses to hand carry their proposal, the offeror must reach the appointed location (identified as building 5300, 5300 Martin Road, Redstone Arsenal, AL 35898, Foyer) by the date and time as stated in block 9 on page 1 of the solicitation. Please be

2 4

W58RGZ-17-R-0220 0001

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

advised that Redstone Arsenal is a restricted facility and should an offeror choose to hand carry a proposal, a minimum of 72 hours notice to the Contracting Officer is required in order to ensure access by the closing date/time of the solicitation. Any unauthorized entity must be identified as having a need, as validated by the Contracting Officer, in order to gain access to the post. The contracting office must notify the Gate personnel, who monitor post access, a minimum of 48 hours prior to an entity gaining entrance to the restricted post. Please note that any proposals delivered late as a result of failure to comply with the procedure will not be accepted, IAW FAR 52.212-1 entitled "Instructions to Offerors-Commercial Items".

16. Reserved.

17. Reserved.

18. The contractor shall provide with their proposal a response that addresses the contractor's plan to meet all government special tooling and test equipment requirements with either:

1. Physical possession of the required tools, 2. Confirmed requisitions for the required tools, 3. Confirmed arrangements for subcontracting the processes requiring the special tools, or 4. Specific plans describing their technical approach to develop equivalent tools.

19. Reserved.

20. The contractor is instructed to put the following words in the remarks column of the DD 250/WAWF: "Repair and Return Process D6".

21. Access to DLA EMALL is NOT authorized. ___

22. The National Defense Authorization Act for Fiscal Year 1993, Public Law 102-484, Section 326, prohibits use of Other Direct Cost

(ODC) in Department of Defense contracts awarded on or after 1 June 1993, unless appropriate authority is granted.

23. The following websites are provided for the purpose of obtaining/reviewing various Army publications and technical manuals/bulletins:

A. https://liw.logsa.army.mil/etmapp/#/etm/home - Technical Manuals and Bulletins

B. http://www.apd.army.mil/ - DA Pamphlets and Army Regulations

24. COMPLETE THE FOLLOWING CONTRACTOR POINT OF CONTACT INFORMATION:

NAME: _________________________________________

TELEPHONE NUMBER: _____________________________

FAX NUMBER: ___________________________________

E-MAIL ADDRESS: _______________________________

*** END OF NARRATIVE A0001 ***

The purpose of this Amendment 0001 is to publish Government responses to Industry questions received through Tuesday, August 22, 2017.

1. Industry Question: Will DLA stock any of the mandatory replacement parts required by DMWR 1-1680-332 for overhaul of pn 70400-06641-

117?

Government Response: The supply chain necessary to supply Mandatory Replacement Parts is the responsibility of the Contractor. The

Government does not dictate nor manage the supply chain.

2. Industry Question: We would like to verify that you will only accept proposals by US Mail, up to the date and time specified in the closure?

Government Response: As detailed in Section A, Block 8 and Paragraphs 14 and 15:

Block 8. Offer Due Date/Local Time: 2017SEP07 03:00pm (please note in the response to question 5 below, the proposal due date will be extended)

3 4

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

14. Offers shall be submitted in accordance with FAR Clause 52.212-1. Facsimile and electronic submissions are not authorized.

Proposals shall be mailed to:

Army Contracting Command - Redstone

ATTN: Dawn P. Patterson, CCAM-ALM

Bldg. 5303, 2nd Floor

Redstone Arsenal, AL 35898-5280

The Government does not dictate the method the solicitation is "mailed", only that a hard copy must be delivered by the noted due date/local time. Or should the offeror choose to hand deliver, then paragraph 15 is states:

15. If any offeror chooses to hand carry their proposal, the offeror must reach the appointed location (identified as building

5300, 5300 Martin Road, Redstone Arsenal, AL 35898, Foyer) by the date and time as stated in block 8 on page 1 of the solicitation. Please be advised that Redstone Arsenal is a restricted facility and should an offeror choose to hand carry a proposal, a minimum of 72 hours notice to the Contracting Officer is required in order to ensure access by the closing date/time of the solicitation. Any unauthorized entity must be identified as having a need, as validated by the Contracting

Officer, in order to gain access to the post. The contracting office must notify the Gate personnel, who monitor post access, a minimum of 48 hours prior to an entity gaining entrance to the restricted post. Please note that any proposals delivered late as a result of failure to comply with the procedure will not be accepted, IAW FAR 52.212-1 entitled "Instructions to Offerors-

Commercial Items".

3. In reviewing section L and M of the proposal it appears only the cost section of the DO is to be completed in the template provided.

Is Redstone ACC also requiring a written response to the SOW section C and is there a page limit associated with any technical response?

Government Response: As detailed in Section A, Paragraphs 11 and 18:

11. Please insert your firm fixed unit prices for the 1st, 2nd, 3rd, 4th, and 5th ordering periods in the spaces provided under each CLIN/SubCLIN.

18. The contractor shall provide with their proposal a response that addresses the contractor's plan to meet all government special tooling and test equipment requirements with either:

1. Physical possession of the required tools, 2. Confirmed requisitions for the required tools, 3. Confirmed arrangements for subcontracting the processes requiring the special tools, or 4. Specific plans describing their technical approach to develop equivalent tools.

4. Industry Question: Is it possible to authorize purchasing from DLA in order to proceed?

Government Response: As detailed in question 1 above and Section A, Paragraph 21:

21. Access to DLA EMALL is NOT authorized.

5. Industry Question: Request an extension on the due date?

Government Response: Proposal Due Date will be extended from 7 September 2017 to 15 September 2017, 3:00 pm Central.

Except as provided herein, all other terms and conditions remain unchanged and in full force and effect.

*** END OF NARRATIVE A0002 ***

4 4