This document contains two Contract Data Requirements Lists (CDRLs) for contract W56KGY-24-R-0002. CDRL C001 requires the delivery of scientific and technical reports in the form of a field support technical manual. The contractor must follow DI-MISC-80711A and include all information required by the Statement of Work. Deliverables are due 140 days after award and with each major release. CDRL C002 requires the submission of software/firmware change requests according to the frequency and recipients outlined in the Statement of Work. Both CDRLs require deliverables to be submitted electronically using Microsoft Office formats or other searchable digital formats. The Army Contracting Command at Aberdeen Proving Ground is the requiring office for these CDRLs in support of the Intelligence Application Information Collection Management effort.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
C001 C TDP TM OTHER MISC
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Information Collection Management Application
W56KGY-24-R-0002 TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
C001 Scientific and Technical Reports Field Support Technical Manual
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-MISC-80711A SOW Para 3.9, 3.18.1, 3.18.2, 3.18.3 SFAE-IEW-DC
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
LT ASREQ 140 DAYS XDADO b. COPIES
8. APP CODE D 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE
Draft Final
A N/A SEE BLOCK 16
Reg
Repr o
16. REMARKS:
BLOCK 4: In addition to the requirement of DI-MISC 80711A, the contractor shall include all the information required by the SOW. Contractor format acceptable.
BLOCK 12: Deliverables shall be complete, stand-alone, and address all the concerns in PWS paragraphs shown in Block 5. Deliverables shall be submitted and exchanged electronically, in Microsoft ® Office product suite or in searchable digital formats.
BLOCK 13: The contractor shall deliver documents with each major release.
SFAE-IEW-DC
ACC-APG (CCAP-CCC)
*ELECTRONIC SUBMITTAL
15. TOTAL 3
G. PREPARED BY
Erin Gardner PM IS&A – Procurement Coordinator
H. DATE
06 Nov 2023
I. APPROVED BY
J. DATE
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item) Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
C002 C TDP TM OTHERMISC
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Information Collection Management Application
W56KGY-24-R-0002 TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
C002 Software/Firmware Change Request
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-MISC-81807 SOW Para 3.12.2, 3.14.2 SFAE-IEW-DC
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
LT ASREQ ASREQ b. COPIES
8. APP CODE D 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE
Draft Final
A N/A ASREQ
Reg
Repr o
16. REMARKS:
SFAE-IEW-DC
ACC-APG (CCAP-CCC)
*ELECTRONIC SUBMITTAL
SEE BLOCK 16
15. TOTAL 3
G. PREPARED BY
Erin Gardner PM IS&A – Procurement Coordinator
H. DATE
06 Nov 2023
I. APPROVED BY
J. DATE