This solicitation seeks proposals for security and access control services at Kwajalein Atoll/Reagan Test Site in support of the United States Army Garrison-Kwajalein Atoll. The services include security guard services, access control, law enforcement, anti-terrorism/force protection, and security administration. Offerors must be registered in SAM and proposals are due by November 30, 2020. The government anticipates awarding a hybrid contract utilizing both firm-fixed-price and cost-plus-fixed-fee contract line items to one contractor. The period of performance includes one base year and four one-year option periods, with an additional six-month evaluated extension allowed. This is an 8(a) set-aside with a NAICS code of 561612. The incumbent contractor is Alutiiq Pacific, LLC.
View the file
Other files
Show all 50
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W52P1J-20-R-0093 18 November 2020
Industry Questions and USG Responses
Q1: Please provide current incumbent contractor information.
A1: The current services are being performed by Alutiiq Pacific, LLC under Contract W9113M-
15-C-0015 awarded on 27 February 2015 as a competitive 8(a) in the amount of $4,052,913.43.
Q2: Will the Government consider extending the due date to December 4, 2020?
A2: The USG does not anticipate extending at this time.
Q3: M.3.1 Facilities Clearance: The PCO will verify that the Commercial and Government Entity
(CAGE) code(s) for the Offeror and the teammates/subcontractors/managing partner, provided in Volume I, Proof of Facilities Clearance, Validation of Compliance with ANSI/ASIS PSC.1-2012, Supplemental Documents, and Executive Summary, possess a Secret Facility Clearance via the
Defense Security System (DSS) Industrial Security Facilities Database (ISFD) by the Solicitation closing date. If the CAGE code for the Offeror and the teammates/subcontractors/managing partner provided does not possess a Secret Facility Clearance, the USG will find the Offeror unacceptable. The USG will not further evaluate unacceptable proposals and the USG will not consider the Offeror’s proposal for award.
Is this truly what was intended, or are there provisions for allowing cleared individuals working for an uncleared subcontractor to be carried in the Prime Contractor’s JPAS while the subcontractor is being sponsored for their own Facility Clearance?
A3: Section M, M.3.1. has been revised to require only the Offeror to hold the appropriate
Facility Clearance Level. Subcontractors/teammates/managing partners do not have to carry a company facility clearance but shall hold the appropriate individual clearances.
Q4: Please confirm that Offerors must provide an ANSI/ASIS PSC.1-2012 and/or ISO 18788 certification document or certificate to provide validation of compliance with ANSI/ASIS PSC.1-
2012, American National Standard, Management System for Quality of Private Security
Company Operations- Requirements with Guidance.
A4: The USG will accept either the ANSI/ASIS PSC.1-2012 or the ISO 18788 certification. Section
L, L.3.2. and Section M, M.3.2. have been updated to reflect this.
Q5: “L.5.1.10 Past Performance Questionnaire (PPQ): The information to be provided with each contract reference is on the PPQ, The Offeror must complete PPQ Sections IA and IB for each contract reference and send copies of the PPQ to the respondent Point of Contact (POC) as identified in IB in a timely manner. The Offeror shall include these documents in Volume III, Section 1 of its proposal. The PPQ respondents will send the completed questionnaire directly to the U.S. Government POC as identified in Part III of the PPQ.” Please confirm that only Part I of the PPQ is required for inclusion in the RFP response.
A5: The USG confirms that only Part I of the PPQ is required to be included in an Offeror’s proposal. Section L, L.5.1.10 has been updated to reflect this.
Q6: Will the Government please confirm that any copies of rate agreements or copies of other whole page/multiple page documents will not count against the 5 Page Limit for the Executive
Summary?
A6: Paragraph L.3.5.1 has been revised to remove the submission of rate agreements.
Q7: Will the Government please confirm that header and footer text can be smaller than 12
Point Font?
A7: Header and footer text can be smaller than 12 Point font but no smaller than 10 Point font.
Section L.2.5. has been updated to reflect this.
Q8: Will the Government please confirm that a “Cover Page”, “Front Cover”, and “Cover Sheet” are all referring to the same Cover Page that should be on the front of every volume?
A8: “Cover Page”, “Front Cover”, and “Cover Sheet” are all referring to the document that should be included on the front of every volume as referenced in L.2.1., L.2.6.1, and L.2.7.
Q9: Will the government please confirm that a cover letter would be excluded from page count?
A9: As stated in the response to Q8, “Cover Page”, “Front Cover”, and “Cover Sheet” are all referring to the document that should be included on the front of every volume as referenced in L.2.1., L.2.6.1, and L.2.7. “Cover Page”, “Front Cover”, and “Cover Sheet” are excluded from the page limit as stated in the Exclusions in L.2.1.
Q10: “If the incoming contractor is new and hires an employee of the incumbent contractor
(currently providing security guard services), the employee must be retrained/recertified (to include medical, Individual Reliability Program [IRP] screening, and training certification).
However, the Government will afford the awardee the opportunity to show/document proficiency for current/incumbent employees. These employees will not be required to re-complete the 120hrs of initial training.”
Please clarify method for documenting proficiency of incumbent employees.
A10: If a Contractor hires an employee of the incumbent contractor, that employee’s IRP package will be used to verify proof of training.
Q11: Will the government be providing shipping of the contractor provided vehicles from the
Concord, CA shipping location? If so, is there a cost associated with the transportation of the vehicles from California to Kwajalein? How long does the shipment of vehicles take from
California to Kwajalein?
A11: The USG will provide shipping of Contractor provided vehicles from Concord, CA. Shipping is based on full containers and takes an estimated 6-8 weeks by boat.
Q12: Will the government be providing fuel for the contractor provided vehicles? If so, is there a cost to the contractor for the fuel? Do vehicles need to be capable of any particular fuel type?
A12: The USG will provide fuel for the Contractor provided vehicles. Fuels used by the USG are
MOGAS and JP-5 diesel. Paragraph 5.22.5 of the Performance Work Statement has been updated to reflect this.
Q13: Due to the required 14-day quarantine in Hawaii and subsequent 21-day quarantine at
Kwajalein due to the COVID-19 pandemic, will the government consider extending the 60-day phase-in to 90 days to offset the 35 days of quarantine time that will delay transition team activities?
A13: The USG will extend the 60 day mobilization period to 90 days.
Q14: Section L.6 of the proposal indicates that the only required for Volume IV is the completion of the Price Matrix (Attachment 0004). Please confirm no supporting narrative is required in addition to the Price Matrix (Attachment 0004).
A14: A supporting narrative is not required to be submitted in addition to the Price Matrix for
Volume IV.
Q15: PWS Section 1.4.8.1 states weapons must be stored in an authorized storage facility.
Is the storage facility, along with weapons safes, provided by the Government?
A15: The USG will provide an authorized storage facility for weapons and ammunition.
Paragraph 1.4.8.1 of the Performance Work Statement has been updated to reflect this.
Q16: PWS Section 2.29.3 states, the contractor is financially responsible for flying the handler and dog to the U.S. Mainland to be re-certified or the contractor will pay the TDY expenses for certification authority to travel to Kwajalein and certify the team.
Please confirm a Government certification authority will be available to travel to Kwajalein to provide K9 certification.
A16: The USG cannot confirm the certification authority will be available to travel to Kwajalein to provide K9 certification. Per PWS 2.29.3 it is the responsibility of the Contractor to provide certification and recertification of the contract working dog team. Certification is provided at the following locations: Redstone Arsenal (Huntsville), Alabama; Aberdeen Proving Ground, Maryland; Fort Irwin, California; and Joint Base Lewis-McChord, Washington
Q17: PWS Section 5.7 discusses Contractor Acquired Purchases (CAP) and that’s that All
Purchase Requests (PR), or Purchase Orders (PO) that utilize the CAP Contract Line
Identification Number (CLIN) will clearly identify the classification of GFP, (Equipment, Special
Test Equipment, Special Tooling, or Material) on the PR/PO. After review of the CLIN structure, there does not appear to be a specific CLIN for CAP purchases. Please confirm any CAP purchases would be invoiced under the Mission Operations Support CLIN.
A17: Per Paragraph 5.7 of the Performance Work Statement, CAP is limited to Mission
Operations (CPFF) requirements. Therefore, any Contractor Acquired Purchases for mission support would be invoiced under the Mission Operations Support CLIN.
Q18: PWS section 5.22.5 indicates that fuel for Government furnished vehicles will be provided by the Government. There is no mention of fuel for contractor furnished vehicles.
In order to accurately price fuel for contractor vehicles, please provide estimated mileage per day, per each vehicle.
A18: See answer to Question 12. The USG will provide fuel for the Contractor provided vehicles.
Q19: PWS Section 2.12.3 states the contractor shall be able to provide an interpreter fluent in speaking and writing both English and Marshallese to assist the DES 24 hours a day; however, Part 7 of the PWS indicates an Interpreter/RMI Liaison is only required for 1 8-hr shift per day.
Please clarify which of the following is the correct staffing for the Interpreter/RMI Liaison position: 24 hours per day, 7 days per week, 8 hours per day, 7 days per week, 8 hours per day, 5 days per week excluding federal holidays
A19: The Interpreter/RMI Liaison shall be staffed 8 hours per day, 5 days per week: Tuesday-
Saturday, excluding federal holidays. Paragraph 2.12.3 of the Performance Work Statement has been updated to reflect this.
Q20: PWS Part 7 indicates that the following positions are required for one 8-hour shift per day;
however, it does not specify the number of days per week.
• Chief of Security
• Captain of Guards
• Property Control Manager
• Human Relations Manager
• Lieutenant (E&E)
• Lieutenant (DSC)
• Lieutenant (ROI)
• Boat Operator (ROI)
• Access Control Officer – Deckhand (ROI)
• Lieutenant (Kwaj Marine)
• Access Control Officer – Deckhand (Kwaj Marine)
Please confirm the positions identified above are required for one 8-hour shift, 5 days per week excluding federal holidays.
Q20: The positions identified shall be staffed 8 hours per day, 5 days per week: Tuesday –
Saturday, excluding federal holidays. Part 7 of the Performance Work Statement has been
Q21: PWS Section 2.29.1 states the contractor shall provide 2 trained and certified explosives detection dog teams and 2 trained and certified drug detection dog teams. PWS Section
2.29.7.1.1 indicates that each dog team will work approximately 32 hours per week (6 hours training + 24 hours work schedule + 2 hours emergency response); however, Part 7 of the PWS indicates that 4 teams are needed 8 hours per day.
Please clarify the number of dog teams that are needed each day, the length of the shift required each day, and the number of days per week the teams are required (i.e. 2 teams are required 8 hours per day, Tuesday – Saturday).
A21: Per paragraph 2.29.1 of the Performance Work Statement “ One CEDD and one CNDD will be available at all times. Two CDTs shall operate Tuesday-Saturday 0800-1600.” Two teams are needed per day, one CEDD and one CNDD. The requirement is for 4 teams total (2 CEDD and two
CNDD) for days off.
Q22: Part 7 of the PWS indicates that 1 Sergeant and 2 Security Officers are required 12 hours per day at CPS; however, the total staffing for CPS is 6.
Please clarify if the 3 CPS positions are required 24 hours per day and the number of days per week each position is required (i.e. 7 days per week).
A22: 3 CPS positions are required 24 hours per day, 7 days per week. The Position Table in Part
7 of the Performance Work Statement has been updated for CPS to include a CAC/EBS System
Operator, this position shall be staffed 8-hours per day, 5 days per week, excluding Federal holidays. Per the Position Table the following is required for CPS: 1 Sergeant and 2 Security
Officers per 12-hour shift and 1 CAC/EBS System Operator who will work one- eight hour shift.
Therefore, a total of 7 personnel (2 Sergeants, 4 Security Officers, and 1 CAC/EBS System
Operator) are needed per day.
Q23: Part 7 of the PWS indicates that 1 Sergeant, 2 Security Officers, and 4 Access Control
Officers are required 9.5 hours per day at E&E; however, it does not specify the number of days per week.
Please clarify the days per week the E&E Sergeant, Security Officers, and Access Control Officers are required.
A23: Per Paragraph 2.14.1 of the Performance Work Statement, E&E shall operate Monday--
Saturday and shall be staffed during all inbound flights.
Q24: Part 7 of the PWS indicates that in addition to the Lieutenant, 1 Sergeant, 2 Security
Officers, and 3 Access Control Officers are required 12 hours per day at DSC; however, the total staffing for DSC is 13.
Please clarify if the DSC Sergeant, Security Officer, and Access Control Officer positions are required 24 hours per day and the number of days per week each position is required (i.e. 7 days per week).
A24: Positions are 24 hours, 7 days per week. Per the Position Table in Part 7 of the
Performance Work Statement the following is required for DSC: 1 Sergeant, 2 Security Officers, and 3 Access Control Officers per 12-hour shift and 1 Lieutenant who will work one eight-hour shift. Therefore, a total of 13 personnel (1 Lieutenant, 2 Sergeants, 4 Security Officers, and 6
Access Control Officers) are needed per day.
Q25: Part 7 of the PWS indicates that in addition to the Lieutenant, Boat Operator, and Access
Control Officer - Deckhand, 1 Sergeant, 1 Security Officers, and 2 Access Control Officers are required 12 hours per day at ROI; however, the total staffing for ROI is 11.
Please clarify if the ROI Sergeant, Security Officer, and Access Control Officer positions are required 24 hours per day and the number of days per week each position is required (i.e. 7 days per week).
A25: ROI Sergeant, Security Officer, and Access Control Officer positions are required 24 hours per day, 7 days a week. Per the Position Table in Part 7 of the Performance Work Statement the following is required for ROI: 1 Sergeant, 1 Security Officer, and 2 Access Control Officers per
12-hour shift and 1 Lieutenant, 1 Boat Operator, and 1 ACO-Deckhand who will work one eight-hour shift. Therefore, a total of 11 personnel (1 Lieutenant, 2 Sergeants, 1 Boat Operator, 2
Security Officers, 1 ACO- Deckhand, and 4 Access Control Officers) are needed per day.
Q26: The Price Matrix requires offerors to provide a cost per person per day for 365 days per year (305 days in the base period). This may lead to an inaccurate calculation of cost. For example, if the Chief of Security is only required to work 5 days per week (see question 9), the total days per year would be closer to 250 rather than 365.
Would the Government consider revising the spreadsheet to change the number of days column to a contractor provided (yellow cell) number of hours per position and changing the position daily rate per person to an hourly rate per person? The total price per SubCLIN would then be the number of hours per position * position hourly rate * total number of personnel required. This would provide for a more accurate representation of the proposed cost. This method would also provide the Government with pre-established labor rates to be used when preparing Mission Operation Support estimates.
A26: The Price Matrix is being revised to update the ‘number of days’ for those positions that are required to be manned 5 and 6 days per week. This is a Firm Fixed Price effort and therefore the USG will only obtain daily rates per person. The Price Matrix will be released via amendment to the solicitation by 20 November 2020. *Updated Price Matrix- Released with
Amd 0005 on 18 November 2020.
Q27: There is no mention of Covid-19 related precautions in the solicitation.
Are there any Covid-19 related quarantine (i.e. 2 weeks in Hawaii or 3 weeks on Kwajalein) or
Covid-19 testing requirements that must be followed when deploying individuals from the U.S.
to Kwajalein?
A27: Currently, the Garrison must seek approval to bring personnel into RMI. Once approved, Contractors traveling into Kwajalein shall receive COVID-19 testing before traveling to Hawaii.
Contractors shall quarantine for 14 days in Hawaii and shall be retested prior to flying to
Kwajalein. Upon arrival into Kwajalein contractors shall be tested and then quarantine for 21 days. Contractors shall be retested on day 15 of quarantine and day 20 of quarantine. After confirmation of a negative test they will be released from quarantine. These restrictions are subject to change and may be different at time of award.
Q28: PWS Section 2.29.3 states contract handlers must attend and graduate from a formal training program course that results in the handler/dog team certification by Army Certifying
Authority. When contracted by Department of the Army the canines must be certified according to AR 190-12 standards, and re-certified annually thereafter or as needed.
The contractor is financially responsible for flying the handler and dog to the U.S. Mainland to be re-certified or the contractor will pay the TDY expenses for certification authority to travel to
Kwajalein and certify the team.
a. Is the Army Certifying Authority a Government employee?
A28a: Yes the Certifying Authority is a Government employee..
b. If the Army Certifying Authority is a Government employee, please provide the expected TDY expenses the contractor would be responsible for.
A28b: The USG does not have an estimated cost for this.
c. If the Army Certifying Authority is a Government employee, please provide the locations within the U.S. where the certification can be completed.
A28c: With prior coordination, certification can take place at the following locations:
Redstone Arsenal (Huntsville), Alabama; Aberdeen Proving Ground, Maryland; Fort Irwin, California; Joint Base Lewis-McChord, Washington.
d. Will the Government accept canine certification from a 3rd party vendor?
A28d: The USG will not accept canine certification from a 3rd party vendor. Certifications must be completed through a DOD recognized MWD/CWD certification authority.
e. Can we assume the certifying authority will travel to Kwajalein at minimum one time per year to provide certification?
A28e: The USG cannot confirm that the certification official will travel to Kwajalein to provide certification.
f. Will the certifying authority be available during the mobilization period on Kwajalein?
A28f: See response to Question 28c.
Q29: PWS Section 2.29 discusses the contract working dogs. While we understand that constant training is required to maintain the dog team certifications; there is no mention of training aids being Government or Contractor provided. With Kwajalein being an OCONUS location, it is nearly impossible for a civilian company to obtain licensing to import/transport substances such as narcotics for these training purposes.
Please confirm canine training aids (explosives and drugs) will be Government provided.
A29: Paragraph 2.29.1 of the Performance Work Statement states “Explosive and drug training aids will be supplied by the USG IAW AR 190-12.”
Q30: In evaluation of the minimal staffing levels of 49 compared to the post requirements, it would appear that 49 personnel adequately provides coverage; however, it is not possible to determine the number of additional personnel needed to support Mission requirements without historic workload data for Mission support.
Would the Government please provide either an estimated number of personnel needed to support Mission requirements or historic workload data so that offerors can develop a level of effort estimate for personnel needed for the Mission requirements?
A30: Per Part 7 of the PWS, the support package for Mission Operations is on average no more than 8 armed personnel (IAW with Paragraph 1.4) for 24/7 coverage, and typically includes a boat operator and three additional personnel. On average there are 12 missions a year and the estimated duration for each mission is 24 hours a day, 7 days a week for two weeks. This fiscal year the missions have only required 4 personnel 24 hours, 7 days a week.
Q31: PWS Section 1.4.6 discusses the CAC and EBS systems. This section indicates that all CAC equipment and supplies are provided by the Government but coordinated through the contract; however, it does not address the EBS system supplies.
Please confirm all supplies and equipment for both the CAC and EBS systems are provided by the Government. If not, please provide historical data to estimate cost.
A31: The USG will provide CAC/EBS equipment and supplies. Paragraph 1.4.6 of the Performance Work Statement has been updated to reflect this.
Q32: PWS 1.4.12-5 : Therefore, the contractor will provide for veterinary services for all contracted dogs.
Does the contractor have access to onsite veterinary services at the contractor expense?
A32: Per PWS 1.4.12-5 veterinary services are the responsibility of the Contractor. It is recommended veterinary services be worked from a CONUS or Hawaii veterinary to have assurance of routine care. There is a Vet Tech located on island but they are not tasked with the care of the working dogs. They will afford emergency care and inoculations as available.
Q33: Minor repair is defined as Level 1 maintenance, such as changing oil, replacing filters, replacing batteries with a cost NTE $500.
Is the NTE value per incident, year, month, life of contract? Can the government provide historical information in regard to preventative maintenance in order to better calculate expenditures?
A33: The LOGCAP Contractor is responsible for preventative maintenance to include oil changes, filters, batteries required to maintain the vessels. Paragraph 2.28.2 of the Performance Work Statement has been updated to reflect this.
Q34: Exclusions from page count: Sample Resumes. Are sample resumes required? If so, for what positions and in what Volume should they be included?
A34: Sample resumes are not required.
Q35: If CPARs are available for a contract, can they be used in lieu of PPQs?
A35: CPARs cannot be used in lieu of the PPQ. However, as stated in L.5.1.10, the U.S.
Government reserves the right to use data provided in the Offeror’s proposal and data obtained from other sources.
Q36: Section L.2.1 indicates financial capability documents are excluded from the proposal page count. Section L.3.5.1 requires offerors to provide a copy of any rate agreements.
Please confirm the copies of rate agreements referenced in section L.3.5.1 are considered financial capability documents and are excluded from the proposal page count.
A36: See response to Question 6.
Q37: Reference PWS 2.29.3 –“ Contract handlers must attend and graduate from a formal training program course that results in the handler/dog team certification by Army Certifying Authority. Canines shall be certified and shall maintain this certification in accordance with Army Regulation 190-12. When contracted by Department of the Army the canines must be certified according to AR 190-12 standards, and re-certified annually thereafter or as needed.”
AR190-12: 2–2. Military working dog personnel qualifications and responsibilities a. Initial training. All MOS 31K personnel will successfully complete the MWD (31K) Handler Course Phase 1 conducted by USAMPS, Fort Leonard Wood, MO and the MWD Handler Course Phase 2 conducted by the 341st TRS, JBSALackland AFB, TX. Department of the Army Civilian Police (DACP) handlers will successfully complete the DACP Academy conducted by USAMPS, Fort Leonard Wood, MO and the MWD Handler Course Phase 2 conducted by the 341st TRS, JBSA- Lackland AFB, TX. Combat Engineer’s must successfully complete the MDD Handler Course conducted by USAES, Fort Leonard Wood, MO. On-the-job training for the purpose of qualifying military or civilian personnel as MWD handlers are prohibited
A. Would the PCO elaborate on the availability of a Department of the Army certifying authority on the Kwaj Atolle?
A37A: See response to Question 28.
B. What are the locations where this certification is conducted both for initial and annual concurrency?
A37B: See response to Question 16 and Question 28.
C. How are Veterinary Services provided (GF or CF) for health visits and inoculations?
A37C: Veterinary services are Contractor furnished. See response to Question 32.
Q38: Weapons: Sections L, M and the PWS reference the 9mm pistol as the weapon for armed personnel.
a. Please confirm that 9MM pistols be contractor provided as CFE and not GFE serially managed items for weapons supplied?
A38a: Per paragraph 4.20.7.2 of the Performance Work Statement, 9MM pistols shall be Contractor furnished.
b. Are there any other weapon types required or allowed for use in this scope; ie. Shotgun for maritime patrols?
A38b: No other weapon types required or allowed for use under this contract.
c. Will ammo type (ball vs hollow-point) be specified and provided as GFE for either range practice or base operations?
A38c: Ammunition for range qualifications or base operations shall be Contractor provided.
The ammo type is 9mm ball. Paragraphs 3.21 and 4.20.7.13 of the Performance Work Statement have been updated to reflect this.
d. Will a gunsmith be provided as DAC?
A38d: The USG will not provide a gunsmith.
e. Will a range safety officer be provided as DAC?
A38e: The Provost Marshall will be in attendance during range qualifications to ensure range procedures are followed.
Q39: PWS 1.4.7 - The contractor shall be responsible for the storage and safeguarding of weapons and ammunitions, and these items will be protected IAW AR 190-11. These weapons and ammunition shall be accounted for at all times. Will an Arms Room facility be provided in accordance with PWS 1.4.8.1- Weapons: Weapons must be stored in an authorized storage facility IAW AR190-11, Chapter 4. GFE listing does not reflect arms room, facilities, or securable racks.
A39: See response to Question 15.
Q40: Demobilization-(Section H and PWS) The Government Solicitation assigns a “Demobilization CLIN” as FFP for each Option year.
a. Does the USG anticipate executing demobilization activities each year?
A40a: The Government does not anticipate executing demobilization activities each year. It is included to afford the Contractor an opportunity to escalate demobilization pricing if necessary. The requirement and demobilization may need to occur at the end of any year of performance (i.e. if an option is not exercised, Demobilization will occur at the end of that time period).
b. would those activities include pricing the return of entire workforce (EXPATs) to CONUS on Commercial airlines?
A40b: Yes, it would include the return of all personnel to their Home of Record.
Q41: Communication: Reference PWS Part 10, CDRL Deliverables:
a. How does the current team communicate off-island if needed. For example. Contractor needs to provide CDRL updates to the COR, is that done via Gov’t provide internet/email?
A41a: Communication in performance of the PWS and related to duties of their job will be done via Government provided internet and email.
b. How does the current security team communicate with corporate leadership on contract issues such as financial/HR/Logistics?
A41b: Communication with corporate leadership required per the PWS can be completed via the USG provided commercial internet.
c. Is Internet or phone service available to contractors as a non-cost service?
A41c: The USG will provide internet and phone services for performance of the PWS and related to duties of their job. Internet and phone service for personal use is not provided by the USG.
Q42: CDRL A006 Contractor Work Breakdown Structure (CWBS) CDRL states, “Draft submitted with the proposal.”
Please clarify which volume CDRL A006 is to be included. There are no instructions in Section L relative to CDRLs.
Is CDRL A006 excluded from the page count?
A42: The draft Contractor Work Breakdown Structure (CDRL A006) shall be included in Volume I. This will be excluded from the page count. L.3.6. has been updated to reflect this.
Q43: CDRL A008 Quality Control Plan CDRL states, “The contractor shall submit a draft copy of the quality control plan with the proposal.”
Please clarify which volume CDRL A008 is to be included. There are no instructions in Section L relative to CDRLs.
Is CDRL A008 excluded from the page count?
A43: The draft Quality Control Plan (CDRL A008) shall be included in Volume I. This will be excluded from the page count. L.3.6. has been updated to reflect this.
Q44: L.1.8 Our Representations/Certifications data are current in SAM Database. L.1.8 states, “The purpose of electronic Representations and Certifications is to provide all Offerors with a portal in which to submit Reps/Certs in a publicly accessible format, nullifying the requirement to submit identical information in response to each and every Federal contract solicitation.”
Are offerors still required to include a copy of Sections A-K with the proposal submission in Volume I?
A44: Yes, per Section L.3.3. Offerors must provide a completed and signed copy of the Solicitation including Sections A-K and any amendments.
Q45: L.2 Standard Proposal Instructions The page limit exclusions list refers to “Any financial capability documents”. Will the Government clarify if financial capability documents are required, and if so, what type?
A45: There are not any specific financial capability documents that are required.
Q46: L.6.6. & M.6.4 Does the Government require a separate, detailed Excel Cost proposal to perform the Total Price Evaluation and validate the reasonableness of our offer in accordance with IAW FAR 15.404-1?
A46: The USG provided a Government surrogate number for the CPFF portion of the contract.
Therefore, a detailed Excel Cost proposal is not required to be submitted.
Q47: Solicitation P 16 – H.5.1.1 (4) – what are the medical and dental service rates?
A47: The USG does not have these rates. The Contractor can contact International SOS (the provider) at 805-355-2223 or 805-355-2224 for the current rates.
Q48: Solicitation P 17 – H.5.1.2 (1) – Is the contractor responsible for flights to and from US mainland to Meck Island?
A48: Meck island can only be accessed via ferry or helicopter from Kwajalein. The ferry or helicopter transportation is provided by the USG.
Q49: Attachment 0002 P8 – L.4.3 – does the contractor need to provide a learning management system, or is this government furnished?
A49: The Contractor shall provide certifications for their employees with the exception of the required JKO certifications. The USG does not provide a learning management system.
Q50: PWS 1.4.5.6 – P6 – who devises the quarterly exercises?
A50: The Garrison and DES will devise these exercises.
Q51: PWS 1.4.6 – P6 – can we assume that all incumbent staff have up-to-date training on all systems?
A51: Yes.
Q52: PWS 1.4.12.5 – P 9 – Is there an onsite vet for K9 care?
A52: There is not onsite veterinary services for K9 care for contract working dogs. There is a Vet Tech located on island but they are not tasked with the care of the working dogs. They will afford emergency care and inoculations as available.
Q53: PWS 2.15.1 – P17 – Do the Roving Security Patrols travel on non-metaled roads or routes that would require an off road vehicle?
A53: No. Roving Security Patrols do not require an off-road vehicle.
Q54: PWS 2.29.3 – P21 – in the event that recertification of a dog is not granted, would the replacement cost be reimbursable?
A54: No, the cost would not be reimbursable if recertification of a dog is not granted.
Q55: 3.12 – P 31 – is the access control officer training an online or attendance course?
A55: The training listed in Section 3.12 is a sample of what should be included in the company’s training for Access Control Officers. The Government does not provide this training.
Q56: Section H.9.2 addresses the grandfathering of wages and benefits for local hires (RMI citizens and nationals) under Article VIII of the Military Use and Operating Rights Agreement (MUORA). Are there current RMI employees who would received grandfathered wages/ benefits under this agreement? If yes, please provide the grandfathered wages and benefits for these employees.
A56: 1 RMI that is grandfathered. Current grandfathered wage is $15.99 USD per hour.
Currently offered a $50K death benefit.
Q57: Section 4.21 of the PWS indicates the island can support up to 65 security personnel with housing provided through a mix of bachelor quarters (BQs) and family housing. Are dependents allowed to accompany employees who are assigned to the family housing units?
A57: Currently there are seven family housing units. If a key personnel position is assigned a family housing unit then they are authorized to bring dependents. Assignment of family housing units is based on priority: Chief of Security, Captain of the Guards, Human Relations Representative, DSC/E&E/Marine Lieutenant, and Kennel Master. ROI Lieutenant will be based on ROI and will have a bachelor quarter.
Q58: Section 1.4.6 of the PWS discusses the requirement to operate, update, and maintain the CAC and EBS (badging) systems; however, there is no requirement for badging personnel on the staffing table in Part 7 of the PWS. Please clarify the staffing requirements for the personnel operating the CAC and EBS systems.
A58: The CAC and EBS systems should be manned 8-hours a day, 5 days a week (Tuesday-
Saturday). Paragraph 1.4.6 and Part 7 of the Performance Work Statement have been updated to reflect this. The Price Matrix is being revised to include this position. The Price Matrix will be released via amendment to the solicitation by 20 November 2020. *Updated Price Matrix-
Released with Amd 0005 on 18 November 2020.
Q59: In response to Question 4- since the USG specified that the Prime has to hold the
Facilities Clearance, does the same hold true for these certifications in that the Prime is required to hold these certifications to validate compliance? Or can the offeror validate compliance by showing we understand the requirements of the certifications as our partners hold the certifications and do this on a daily basis and they would be part of the management of those work areas of the PWS.
A59: Section L, L.3.2. states: ‘Offerors must provide validation of compliance with ANSI/ASIS
PSC.1-2012 American National Standard, Management System for Quality of Private Security
Company Operations- Requirements with Guidance or the International Standard ISO 18788, Management System for Private Security Operations- Requirements with Guidance.’ If proposing as a teaming arrangement, only the Prime shall provide evidence of validation of compliance. Section L, L.3.2. and Section M, M.3.2 have been updated to reflect this.
Q60: In review of the ANSI/ASIS PCS.1-2012 and ISO 18788 Quality Assurance Management
System (QAMS) standards, we have determined that there are various industry best practices and methods that could be used to meet the requirements in Sections L.3.2 and M.3.2. Please provide the Government’s expectation for validation and evidence of compliance with the
ANSI/ASIS PCS.1-2012 and ISO 18788 standards.
A60: Per Section L, L..3.2. Offerors must provide validation of compliance with ANSI/ASIS
PSC.1-2012 American National Standard, Management System for Quality of Private Security
Company Operations- Requirements with Guidance or the International Standard ISO 18788, Management System for Private Security Operations- Requirements with Guidance. Offerors shall provide evidence that they are in compliance with ANSI/ASIS PCS.1-2012 and ISO 18788.
Evidence of validation of compliance may be any of the following: a record of an audit under a previous government contract that states the Offeror is in compliance with ANSI/ASIS PSC.1 or
ISO 18788 or a certificate of certification. Section L, L.3.2. and Section M, M.3.2 have been
Q61: The Section L.3.2 and Section M.3.2 Amendment 0004 updates do not reflect language relative to certifications being required for “Validation of Compliance.” Are we correct to interpret this to mean that bidders must validate compliance with ANSI/ASIS PSC.1-2102 or ISO
18788 standards in order to meet this requirement and are not required to hold ANSI/ASIS
PSC.1-2102 or ISO 18788 certifications?
A61: See response to Question 60.