ATTACHMENT_0009_-_List_of_Deliverables.xlsx

XLSX spreadsheet 12 KB Posted

Attached to
Supply and Installation of New Commercial Laundry Equipment at Pine Bluff Arsenal
Solicitation number
W52P1J-17-R-LAUN
Issued by

About this file

Summary of documents to be submitted by interested vendors with proposal, and post-award documents to be submitted by the awardee if a contract is issued.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W52P1J-17-R-LAUN

ATTACHMENT 0009 - LIST OF DELIVERABLES

W52P1J-17-R-LAUN: Supply and Installation of Commercial Laundry Equipment

List of DeliverablesDue Date*
With Proposal
1Written technical proposal to include the following:NLT June 2, 2017 unless directed otherwise by Contracting Officer
- Name of Offeror's designated Contract Manager in accordance with SOW 37.11.
- Source of all proposed equipment and materials in accordance with SOW 9.2.2.
- Disclosure of attendance at site survey in accordance with SOW 5.2.
- Warranty information in accordance with SOW 7.0.
2Manufacturer's literature in accordance with SOW 2.1.1.
3Shop drawings in accordance with SOW 2.1.1.9. and 2.1.2.
4Milestone chart in accordance with SOW 6.2.
5Certificates of compliance with standards included in table 9.3 of SOW.
6Quality Control Plan in accordance with SOW 37.1.
7Completed price matrix (Attachment 0002)
8Completed FAR 52.212-3 provision (Attachment 0003)
9Completed FAR 52.225-18 provision (Attachment 0004)
10Completed FAR 52.209-11 Provision (Attachment 0005)
Post-Award
1The number and names of people expected to be on-site executing the contract requirement, per SOW 37.7.1.Post-award kick-off meeting (or prior)
2Instruction manual in triplicate and electronic copy in accordance with SOW 3.1.Post-award kick-off meeting
3All required licenses and certifications required by Federal, State, and Local environmental laws and/or regulations, per SOW 37.14.3.Post-award kick-off meeting
4Certificates of completion of Anti-Terrorism Level I training submitted to COR, per SOW 37.8.1.NLT 40 days after contract award
5Certificates of completion of iWATCH training submitted to COR, per SOW 37.8.3.NLT 40 days after contract award
6Certificates of completion of Hazard Communication Standard training to COR, per SOW 37.15.4.Coordinate with COR
7Certificates of completion of Pine Bluff Arsenal General Safety Briefing to COR, per SOW 37.15.2.Coordinate with COR
8Summary of data gathered during start up, calibration, adjustments, and testing, to include date, personnel, results, instrumentation used, and other applicable details, per SOW 8.2.3.Coordinate with COR
9Furnish templates, together with instructions, showing how to anchor bolts should be set, if anchor bolts are required by the manufacturer, per SOW 25.2.Coordinate with COR
10Submit in writing, the quantity of waste removed and recycled, etc. to the DGR and/or the COR, per SOW 37.14.10.3.Monthly after start of field work
11Final Inspection/Acceptance of Installation Project (furnish all necessary inspection reports, approvals, certificates, warranties, labels, stamps or nameplates required by the SOW; as-built drawings; submit information needed for DD Form 1354, per SOW 33.Final acceptance
12Submit all identification badges to COR per SOW 37.7.2.Final acceptance
*Due dates are subject to change per guidance from either the Contracting Officer, or Contracting Officer Representative (COR)