Pre Proposal Conference Slides.pdf
PDF 5 MB Posted
- Attached to
- CANO MARTIN PENA ECOSYSTEM RESTORATION PROJECT (CMP-ERP) CONTRACT 3 PHASE 1, EXCAVATION AND STABILIZATION
- Solicitation number
- W51DQV25RA004
- Issued by
-
Department of the Army
About this file
These pre-proposal conference slides detail the Caño Martín Peña Ecosystem Restoration Project (CMP) Contract 3 Phase 1, a U.S. Army Corps of Engineers project in San Juan, Puerto Rico. The project aims to restore the tidal connection between San José Lagoon and San Juan Bay by excavating and stabilizing a 900-meter channel, with an estimated construction cost between $25-100 million. Key contract details include a firm-fixed-price solicitation (W51DQV25RA004), full and open competition, an estimated 1,363-day performance period, and a bid submission deadline of June 17, 2025 at 2:00 pm AST via the Procurement Integrated Enterprise Environment (PIEE).
The project involves multiple complex engineering tasks, including developing a Material Management Area, preparing disposal pits, dredging access and transition channels, installing steel sheet pile walls, protecting bridges from scour, and managing environmental considerations. Construction challenges include working in densely populated areas with narrow access routes, managing high volumes of solid waste, and maintaining strict water quality standards. The contractor will be required to perform at least 30% of the work, submit a bid guarantee of 20% of the bid price (or $3 million), and pay liquidated damages of $6,505 per calendar day of delay. Subcontracting plans will be required for non-small business firms.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site Visit Attendance List_5-15-2025.pdf | ||
| W51DQV25RA004 0003.pdf | ||
| W51DQV25RA004 0002.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CAÑO MARTIN PEÑA ECOSYSTEM RESTORATION PROJECT
CNT 3 PHASE 1 – PRE-PROPOSALS CONFERENCE
CARIBBEAN DISTRICT
15 MAY 2025
PROJECT OVERVIEW
San Juan Metropolitan Area
SAN
JOSE
LAGOON
SAN JUAN
BAY
BOCA DE
CANGREJOS
LA TORRECILLA
LAGOON
LOS COROZOS
LAGOON
CAÑO MARTIN
PEÑA CHANNEL
ECOSYSTEM RESTORATION PROJECT
PURPOSE
The Caño Martín Peña Ecosystem Restoration Project (CMP) aims to re-establish the tidal connection between the San José Lagoon and the San Juan Bay (SJB), which would improve dissolved oxygen levels and salinity stratification, increase biodiversity by restoring fish habitat and benthic conditions, and improve the functional value of mangrove habitat within the San Juan Bay Estuary.
SPONSORS
DNER - Puerto Rico Department of Natural and Environmental Resources
Corporación del Proyecto ENLACE del Caño Martín Peña.
PROJECT TYPE
Ecosystem Restoration
CAÑO MARTÍN PEÑA OVERALL IMPLEMENTATION
LUIS
MUÑOZ
RIVERA
BRIDGE
TREN
URBANO
BRIDGE
Martin Pena
BRIDGE
CONTRACT 1|VEGETATION REMOVAL
CONTRACTS
STATUS: Awarded Sep 2024, Construction start Dec 2024. Expect completion in Oct 2026
SCOPE
Construction of a 115-foot-wide by
6.5-foot-deep channel Installation of riprap at the channel bottom and the side slopes to prevent scour Steel sheet pile walls will be installed at the eastern end
CONTRACT 3 PHASE 1 | CHANNEL EXCAVATION / STABILIZATION
PROJECT IMPLEMENTATION, FEATURES, AND MAP
SOLID WASTE REMOVAL CONTRACT
STATUS: Completed Oct 2023, 15K Tons removed + Modification for additional 3.8K Tons
STATUS: Completed June 2023, 36 acres vegetation removed
CONTRACT 2 | WESTERN BRIDGES SCOUR
PROTECTION. Martín Peña, Tren Urbano, and Luis Muñoz Rivera
STATUS: Contracts award anticipated in Sep 2025
SCOPE
1.2 miles channel dredging Access channel dredging from staging area to eastern end of CMP Bank stabilization to include sheet pile Barbosa Bridge scour protection
Contract 2
Contract 3: Phase 1
Contract 3: Phase 2
BARBOSA
BRIDGE
Barbosa
BRIDGE
CONTRACT 3 PHASE 2| CHANNEL EXCAVATION / STABILIZATION
STATUS: Contract award anticipated in Sep 2028
SCOPE
1 mile channel dredging from Barbosa Bridge to western end of CMP Bank stabilization to include sheet pile ~ 35 acres mangrove/wetland restoration for entire channel Recreation features
CONTRACT 3 PHASE 1 OVERVIEW
• Material Management Area (MMA) / Staging Site Development (CDRC)
• San Jose Lagoon Disposal Pits Preparation
• Access Channel Preparation
Moscoso Bridge Protection
• Transition Channel Improvements from main channel to access channel
• Main Channel Improvements from Barbosa Bridge to transition channel
Sheet Pile Installation
Barbosa Bridge Scour Protection
Barbosa
BRIDGE
SJ1
SJ2
SJ4/5
SJ3
Access Channel
Transition Channel
MMA
Disposal Pits
Main Channel
CONTRACT 3 PHASE 1 FEATURES
MATERIAL MANAGEMENT AREA / STAGING AREA
Features:
• Access Road
• Concrete Dock (29.3 x 17.2 m)
• Concrete Ramp
Dock
Boat ramp
MMA
(6-8 acres)
Access road extension ~400 m
Ciudad Deportiva Roberto Clemente (CDRC)
18 m
Precast Concrete Pile
Concrete Slab
Fender System
CONTRACT 3 PHASE 1
SAN JOSE LAGOON DISPOSAL PITS
• Disposal of dredged material (sediment)
• SJ1 Pit will be dredged to a bottom elevation of -9.14 m (total capacity ~ 391K cubic meters)
• Dredged material from SJ1 will be disposed directly (no screening needed) into
SJ2/3/4/5
• SJ1 will be capped by 61 cm of clean sand during Phase 2
SJ1
SJ2
SJ4/5
SJ3
SJ1
SJ2
SJ3
SJ4/5
Disposal Pits
7CONTRACT 3 PHASE 1
ACCESS CHANNEL
• Dimensions (trapezoidal) 3000 meters long
15.2 meters wide (bottom)
1.8 meters deep 3:1 side slopes Moscoso Bridge will be protected
• Anticipated minimum dredging ~ 7K cubic meters
• Dredged material will be disposed directly into pits
(no screening needed)
SJ1
Access Channel
Typical Cross Section
7.6 m 7.6 m
EL -1.8 m
Bathymetry mean sea level
8CONTRACT 3 PHASE 1
MOSCOSO BRIDGE PROTECTION
• 8.7 meters clearance at the access channel cross point
• 30.1 meters span length
• Piers will be protected by means of fenders
15 m precast concrete pile composite lumber
9CONTRACT 3 PHASE 1
TRANSITION CHANNEL
• Dimensions (trapezoidal) 450 meters long channel
3.1 meters deep
30.5 meters wide (bottom) 3:1 slope
• Estimated dredged volume ~ 33K cubic meters
• Dredged material will be disposed directly into SJ1 pit (no screening needed)
Typical Cross Section
15.25 m 15.25 m
EL -3.1 m
Mean sea level
10CONTRACT 3 PHASE 1
MAIN CHANNEL
• Dredging of 900 meters long channel
• Rectangular cross section (30.5 x 3.1 m)
• Steel sheet pile channel walls with concrete cap (12 m)
• Estimated dredged volume ~ 103K cubic meters
• Expected higher trash and debris. Separation of solid waste (debris) from sediments will be performed by a metal sieve.
• After screening and removal of solid waste, the remaining dredged material will be transported by shallow-draft barges and bottom dumped in a controlled manner at SJ1 disposal pit.
• The solid waste will be transported to the MMA, and then, trucks will haul material to an approve landfill.
Main Channel
CONTRACT 3 PHASE 1
CHANNEL WALLS
• Approximately 900 meters long channel
• Rectangular cross section (30.5 x 3.1 m)
12CONTRACT 3 PHASE 1
BARBOSA BRIDGE SCOUR PROTECTION
• Dimensions (trapezoidal) 61 meters long
3.1 meters deep
30.5 meters wide (bottom) 3:1 slope riprap gradation size: D50 (0.23 meters) riprap layer size: 0.51 meters
CONSTRUCTION CONSIDERATIONS
Limited access: Most of the access routes are local roads (narrow streets) with adjacent residential structures vulnerable to damages
Construction on the wet: Diversion of the channel won't be allowed
Activities below Barbosa and Moscoso Bridges: Low vertical clearance
Higher solid waste (garbage, debris): Percentage of solid waste could be higher than the percentage assumed during design
Dredged material management: Material management must comply with the Water Quality Certificate, state and federal laws.
Water quality in the SJL: turbidity control, controlled placement of the sediments into the pits to limit the release of grey waters.
Water releases from the MMA : Water returning into water of the US must be tested and comply with the Water Quality Certificate before release
Community Outreach: Working in Caño Martín Peña area requires coordination with ENLACE (NFS) and the G-8 due to the proximity of residential structures and dense population
CONTRACTING OVERVIEW
Samuela Adams Contract Specialist
Katrina Chapman Contracting Officer
File Name
ACQUISITION APPROACH
• Solicitation No. W51DQV25RA004
• Type of contract: Firm-fixed-price
• Acquisition Method: FAR Part 15 Negotiations – Request for Proposal (RFP), Full and Open Competition (Unrestricted)
• Transmission Method: Electronically via Procurement Integrated Enterprise Environment (PIEE). Bids must be received by the Government no later than June 17, 2025 at 2:00 pm (AST).
• Estimated Magnitude of Construction: Between $25,000,000 and $100,000,000
• North American Industry Classification System (NAICS): 237990, Other Heavy and Civil Engineering Construction
• Estimated Period of Performance: 1363 calendar days after receipt of the Notice to Proceed (NTP)
• Liquidated Damages: $6,505.00 for each calendar day of delay until the work is completed or accepted
• Performance of Work by the Contractor: 30%
PROJECT GENERAL INFO
• Technical Inquiries and Questions: shall be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org). ProjNet closes seven (7) calendar days prior to bid closing. Bidders inquiries must be entered into ProjNet for an official answer.
• Bid Guarantee: an electronic copy of the bid guarantee shall be submitted with the bid. The bid guarantee shall be 20% of bid price or $3,000,000, whichever is less.
• Payment and Performance Bonds: awardee must submit payment and performance bonds equal to the total bid price within 10 days of contract award.
• Note: Subcontracting Plan is required from Other than Small Business Firms (FAR Part 19)
PROJECT GENERAL INFORMATION
• All amendments must be acknowledged in block 19 of the Standard Form (SF 1442) Solicitation
1. Make sure to monitor SAM.gov and PIEE for any amendments to be published.
AMENDMENTS
RESOURCES 19
• Systems for Award Management (SAM): www.sam.gov
• ProjNet: www.projnet.org
• Procurement Integrated Enterprise Environment (PIEE): https://piee.eb.mil
1. The only authorized transmission method of proposals in response to the subject solicitation is electronically via the Procurement Integrated Enterprise Environment (PIEE) website. No other transmission methods, such as email, facsimile, hand-carried, proprietary or DOD SAFE submissions, proposals submitted by mail, etc. will be accepted. Offers submitted via any other transmission method other than the PIEE website will not be evaluated.
2. The Offeror’s proposal/bid must be received by the Government no later than the date/time specified in the solicitation and cited above.