This document is a Questions and Answers (Q&A) file for Request for Proposal W51AA1-26-Q-A045 for a Sanding Booth project at Tobyhanna Army Depot. The Contract Specialist is Kristen Zigmont (kristen.zigmont.civ@army.mil). The Q&A addresses clarifications regarding attachment numbering discrepancies, electrical and environmental design requirements, system layout drawings, booth structure specifications, fire protection systems, site preparation, climate control infrastructure, fall protection certification, material safety data sheets, evaluation criteria, and contract type and timeline.
Key technical requirements include: booth interior height of approximately 14 feet with a roll-up door sized to maximum height; personnel working from both floor level and elevated platforms with fall protection; fiberglass sanding of CARC-painted materials with repair and curing performed inside the booth; Class I Division 2 classification inside the booth with Class I Division 1 at the spray zone (with Class I Division 1 across the board as an alternative); three-stage filtration with VOC removal on exhaust air; carbon filtration on exhaust air; and fall protection requiring field certification. The Depot will provide compressed air systems for sanding and breathing air, with natural gas available in an adjacent room and facility drainage in the adjacent room. The contract is a Firm Fixed/Price Purchase Order with a 420 calendar day (14-month) completion timeframe from Notice to Proceed, with a target completion date of May 31, 2028. Award is anticipated for mid-June following solicitation closing. Technical evaluation will assess compliance with the Performance Work Statement specifications, with past performance evaluated through CPARS and FAPIIS systems and rated as Acceptable/Unacceptable. No bid bond is required.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Proposal W51AA1-26-Q-A045 Project Title: Sanding Booth
Questions and Answers
Contract Specialist: Kristen Zigmont, Email: kristen.zigmont.civ@army.mil
Question #1: Performance Work Statement Page 1 of 74 Paragraph 1.2 states that Attachment 3 contains a diagram of the proposed booth configuration – it does not. Attachment 3 is the Contract Data Requirements List.
Attachment 4 contains the “Proposed Sanding Booth Area” diagram
Answer #1: Please excuse the discrepancy between the attachment numbers listed on SAM.gov and those referenced within the body of the Performance Work Statement (PWS).
The numbering correctly aligns with the attachment order provided at the end of the PWS.
Question #2: Performance Work Statement Page 1 of 74 Paragraph 1.2 states that Attachment 4 contains the Dust Explosivity Report – it does not. Attachment 4 contains the “Proposed Sanding Booth Area” diagram.
Attachment 5 contains the Dust Explosivity Report.
Answer #2: Please excuse the discrepancy between the attachment numbers listed on SAM.gov and those referenced within the body of the Performance Work Statement (PWS).
The numbering correctly aligns with the attachment order provided at the end of the PWS.
Question #3: Attachment 5 - Is it the Government’s intent that the “Laboratory Report – Explosivity of Dust Clouds” be the basis of design for the proposed sanding booth, cross-draft and vacuum systems?
Answer #3: No. Follow electrical and environmental requirements specified in 5.2.2.a and 5.2.2.5.
Question #4: Are as-built drawings for the existing building available? We understand they would be shared only after award.
Answer #4: Yes, they are available.
Question #5: S6.0 Electrical Safety Page 20 of 74 - Please provide a copy of the “TYAD Electrical Standard.”
Answer #5: Copy attached. Please refer to section 3-10 in the attach Design Guide for TYAD electrical requirements.
Attachment 04 – Questions and Answers Request for Proposal W25G1V-22-R-0043
Question #6: 5.2.1.2 System Layout Drawings – Page 45 of 74. Due to lead times for booth shop drawings, we request the 45-day timeframe be extended to 75 days from award.
Answer #6: This will be taken into consideration at time of award.
Question #7: 5.2.2.1. a Booth Structure and Design Page 45 of 74 – Please clarify desired height within the booth and size of roll-up doors.
Answer #7: Available room height is 27’. Desired booth interior height is approximately 14’ high. Roll-up door should be sized to maximum possible height after allowing for door control mechanism.
Question #8: .2.2.1. c Booth Structure and Design Page 46 of 74 – Please provide as-built information/drawings for the mezzanine floor system or acknowledge the possibility that additional structural design and construction may be needed to support units placed on the mezzanine, therefore associated costs would require a modification to the contract.
Answer #8: As-built drawings will be shared only after award. Mezzanine can be viewed during the pre-solicitation meeting.
Question #9: 5.2.2.1. e Booth Structure and Design Page 46 of 74 – Please clarify that the work includes a compressed air system for sanding and breathing air. Please clarify where compressor can be placed on grade.
Answer #9: Tobyhanna Army Depot will provide compressed air system for sanding and breathing air. No additional compressor is required.
Question #10: 5.2.2.3 Fire Protection Page 47 of 74 – Please acknowledge that design and installation of increased sprinkler pipe sizes can only be determined after award, therefore associated costs would require a modification to the contract.
Answer #10: Acknowledged.
Question #11: 5.2.2.4.a Accessories Page 48 of 74 – Please clarify fall protection system. Will personnel work from elevation platforms within the booth?
Answer #11: Personnel will work from floor level and from elevation platforms within the booth.
Questions #12: 5.2.3.1 Site Preparation Page 50 of 74 – Elsewhere this RFP requires the booth floor to be flush with the room floor. Please clarify if the booth requires a steel plate floor?
Answer #12: A steel floor is NOT required.
Questions #13: Please clarify location and capacity of electrical panel(s) available to power all booth equipment.
Answer #13: Available for observation during site visit. The system may be designed for either 480V or 208V, and controls may be 120V.
Questions #14: Does the fall protection require field certification?
Answer #14: Yes.
Questions #15: Does the facility have chilled water for the climate control system, if so, what is the water temperature and % percent of glycol?
Answer #15: Chilled water is not available.
Questions #16: Does the facility have natural gas for the climate control system, if so, how far to the closest connection point?
Answer #16: Natural gas is available in the adjacent room of the same building, available for observation during site visit.
Questions #17: The climate control systems are large and heavy, is there a location outside the building the climate control system could be pad mounted?
Answer #17: Anticipated location is on the mezzanine adjacent to the sanding room.
Questions #18: Where is the closest facility drain for condensate from the climate control system?
Answer #18: Facility drain is available in the adjacent room of the same building, available for observation during site visit.
Questions #19: The equipment manufacturers are suggesting a 3-4 week lead time for design concept and costing, could the solicitation due date be extended to June 30, 2026
Answer #19: N/A
Questions #20: Do they want the carbon filtration on the recirculation air or the exhaust air ?
Answer #20: Carbon filtration should be on the exhaust air.
Questions #21: Please provide technical data sheets and material safety data sheets for all fiberglass mesh and resin and any other coatings that may be applied within the booth.
Answer #21: Working on MSDS for fiberglass mesh and resins. MSDS for sanded materials are shown below. Other info: West System Epoxy Resin 105, NSN/LSN 8040013805856 and 205 Hardener NSN/LSN 8040014163071.
Questions #22: Is a bid bond required? If so, please advise the required amount.
Answer #22: No, this is not a construction order.
Questions #23: RFP page 2 states “This award will be based on best value to the Government, considering price, technical, and past performance”, however there are no instructions regarding the submission of technical and past performance. Please provide evaluation criteria for these items if they are required.
Answer #23: Technical - The Government will evaluate the proposal as providing or complying with all the requirements set forth in the Government's specification in Attachment 1 - Performance Work Statement (PWS). Any exceptions to the PWS must be called out in the technical submission.
Past Performance- The Government will use all available Contractor performance rating databases and systems in evaluating the Offeror's past performance. If lack of relevant data exists, the Government reserves the right to request examples of past performance from offerors.
-Past Performance will be evaluated by reviewing Contractor Performance Assessment Reporting System (CPARS) and the Federal Awardee Performance and Integrity Information System (FAPIIS). Past Performance will be rated as Acceptable/Unacceptable.
Provide examples of like or similar work.
Questions #24: Is there a timeframe established for contract award?
Answer #24: Once the solicitation closes, then aiming for Mid-June.
Questions #25: The requirement currently states that the booth have 3-Stage Filtration with VOC removal. If we’re only sanding within the booth, VOC’s will not be present because the paint is dry. Will they also be painting within this booth as well?
Answer #25: See PWS paragraph 1.2: A new Sanding Booth will provide Tobyhanna Army Depot (TYAD) capability to repair dents, holes, cracks, etc. in composite materials by applying epoxies and glazing compounds, and by performing wet lay-ups using carbon fiber, fiberglass and Kevlar. The Sanding Booth will handle composite material repairs for the depot workload. Epoxies and glazing compounds will be applied while wearing proper personal protective equipment, including coveralls, safety goggles and respirators with organic vapor cartridges.
Questions #26: Class I Div 1 vs Div 2 — they spec’d C1D1 throughout. We can absolutely build to C1D1, we do it every day. But if they’re open to it, C1D2 inside the booth (with C1D1 only at the spray zone) is a real cost saver on lighting and controls. Want to ask if they have a preference, or if they want us to default to C1D1 across the board for AHJ defensibility. Either is fine on our side, just want to know which way they’re leaning.
Answer #26: C1D2 inside the booth (with C1D1 only at the spray zone) will be considered. If possible, please provide cost of C1D1 across the board as well.
Questions #27: What’s actually happening in this booth? They call it a sanding booth but they spec’d a paint booth — carbon VOC stage, breathable air drops, sprinklers, the whole package. Is this sand + spray + cure all in one enclosure? Or sanding only with the carbon stage there as belt-and-suspenders? Changes how we engineer the recirc / regain air piece.
Answer #27: Booth is used for sanding of fiberglass that has been painted with CARC paint, then fiberglass repairs are performed and cured inside the booth as well. Some assets require the worker to be more than 4 feet above ground level, necessitating fall protection. The fiberglass sanding dust tested weak positive for explosivity.
Personnel also work from floor level and from elevated platforms within the booth.
Questions #28: Biggest part going in —rough L x W x H and weight. Confirms door opening and whether they need rails / dollies / overhead
Answer #28: Available room height is 27’. Desired booth interior height is approximately 14’ high. Roll-up door should be sized to maximum possible height after allowing for door control mechanism. Fall protection rails overhead in ceiling – alternative solutions will be considered.
Questions #29: Utilities at the Bldg 10 location — available amps at 480V, gas service psi and BTU, compressed air capacity, and where the breathable air supply comes from.
Answer #29: Available for observation during site visit. Tobyhanna Army Depot will provide compressed air system for sanding and breathing air. No additional compressor is required. Work with the assumption that we have more than enough capacity; the vendor should identify what they will need/consume and TYAD D/Installation Services (DIS) will accommodate. In event gas is at higher pressure (2 psig or 5 psig), DIS should be able to regulate down to normal pressures…7” to 11”.
Questions #30: Type of Contract?
Answer #30: This is a Firm Fixed/Price Purchase Order.
Questions #31: Requested Target Completing Date?
Answer #31: The contractor shall complete all contractual work within 420 calendar days (14 months) of Notice to Proceed. Target completion date is 31 May 2028. This includes 6-month allowance for Environmental permits to be obtained by TYAD personnel after award, if needed depending on booth system design.