A.03 Performance Requirements Summary_ICIDS-V.pdf
PDF 92 KB Posted
- Attached to
- Electronic Security Systems
- Solicitation number
- W519TC26QICID
About this file
This is a Performance Requirements Summary document for the ICIDS-V (Intrusion Detection and Identification System - Version 5) contract, detailing staffing, inspection, maintenance, and quality assurance requirements with 100% acceptable quality level (AQL) conformance across all performance objectives.
The contractor must maintain minimum staffing of one Site Manager/Engineering Technician (DAQ SMS Certified with Security+), one Electronics Technician III (DAQ SMS Certified if accessing SCIF/SAPF, with Network+ and Security+), and two Electronics Technicians II (DAQ SMS Certified if accessing SCIF/SAPF, with Network+). All personnel must meet DoD 8570.01-M certification standards, maintain current DAQ certifications, and pass Tier-1 background checks. Operational requirements include conducting monthly soft inspections and semi-annual full inspections of IDS-equipped buildings using DA Form 4930, with deficiencies addressed within one month. Emergency response standards mandate certified technician response within one hour during core duty hours and within two hours for non-duty hour calls. System restoration must occur within six hours of arrival, with IDS failures resolved within 24 hours. The contractor must maintain a detailed maintenance database, submit Monthly Status Reports by the 10th workday of each month, perform monthly backups and database updates coordinated with the CAAA Physical Security Officer, maintain on-site inventory of OEM-approved spare parts with one-year warranties, and conduct semi-annual physical inventory reporting within ten days. Additional requirements include providing "as-built" CAD drawings for installations and implementing a Quality Control Plan (QCP) with participation in Government-led Quality Assurance Surveillance Plan (QASP) reviews. All performance standards are verified through random sampling and customer feedback.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A.02 ICIDS Services PWS Revised 07.08.2026.docx | DOCX document | |
| ICIDS-V Shelf Stock.xlsx | XLSX spreadsheet | |
| Martin Cty Wage Determination.pdf | ||
| Attachment 0001 - ICIDS Services PWS Revised 06.03.26.docx | DOCX document | |
| Attachment 0003 - Site Visit Requirement Form.pdf | ||
| Attachment 0002 - Pricing Matrix.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Requirements Summary ICIDS-V
Performance Objectives and PWS Paragraph
Performance Standard Acceptable Quality Level
(AQL)
Method of Inspection
1.5.2 Minimum staffing:
1 Site Manager/Engineering Technician (DAQ SMS Certified, Security+)
All personnel must meet Dod 8570.01-M certification standards and maintain current DAQ certifications.
100 % conformance Random Sampling/ Customer Feedback
1.5.3 Minimum staffing:
1 Electronics Technician III (DAQ SMS Certified if accessing SCIF/SAPF, Network+ and Security+)
All personnel must meet Dod 8570.01-M certification standards
1.5.4 Minimum staffing:
2 Electronics Technicians II (DAQ SMS Certified if accessing SCIF/SAPF, Network+)
All personnel must meet Dod 8570.01-M certification standards
3.2 Document inspections
using DA Form 4930 and submit digital reports monthly.
Address deficiencies within one month of identification.
Conduct:
• Monthly “Soft Inspections” for all IDS-equipped buildings/magazines.
Conduct:
• Semi-annual “Full Inspections” including tamper circuits and sensor testing.
3.3.3 Certified technicians must
respond to:
• Emergency calls within 1 hour during core duty hours.
Certified technicians must respond to:
• Non-duty hour calls within 2 hours.
3.3.4 Maintain a detailed
maintenance database tracking all work orders, parts used, and technician actions.
3.3.5 Submit Monthly Status
Reports (MSRs) by the 10th workday of each month.
100 % conformance Random Sampling/ Customer Feedback
3.3.6 Certified technicians must
respond to:
• System restoration within 6 hours of arrival;
IDS failures must be resolved within 24 hours.
3.5 Maintain on-site
inventory of approved spare parts.
3.5.2 All parts must be OEM-
approved or equivalent and carry a 1-year warranty.
3.5.3 Perform semi-annual
physical inventory and report within 10 days.
3.7.3.7 Provide “as-built” CAD
drawings for all installations.
100 % conformance Random Sampling/ Customer Feedback
3.8 Perform monthly
backups, updates, and configuration corrections.
Coordinate all database changes with the CAAA Physical Security Officer/ESS Liaison.
100 % conformance Random Sampling/ Customer Feedback
3.11.1 All personnel must pass
Tier-1 background check.
100 % conformance Random Sampling/ Customer Feedback
4.2 Implement a Quality
Control Plan (QCP) and participate in Government-led Quality Assurance Surveillance Plan (QASP) reviews.