This document contains Questions and Answers (Q&A) related to Solicitation W50S9J-24-B-0007 for a roof replacement project at the West Virginia Air National Guard facility at Yeager Airport.
The key details include:
- Bid bond requirement is 20% of the bid price
- Contractors are allowed to take core samples during the site visit, but must share the results with other bidders
- The government will only accept bids for an ethylene-propylene-diene-monomer (EPDM) roofing system, per the solicitation requirements
- There are 12 skylights on the roof, 8 of which need to be replaced
- The EPDM membrane must be terminated via counterflashing where the existing roof is terminated, rather than run up and over the parapet walls
- The solicitation includes NIST SP 800-171 DoD assessment requirements that must be met prior to contract award
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Absract of Offers B7 B109 Roof Replacement2.pdf | ||
| Absract of Offers B7 B109 Roof Replacement.pdf | ||
| QandA 7172024.docx | DOCX document | |
| QandA 7102024.docx | DOCX document | |
| Amendment 0001.pdf | ||
| Attendance Sheet - Site Visit.pdf | ||
| Q and A B7.docx | DOCX document | |
| Solicitation.pdf | ||
| B109 Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
7/8/2024
SOLICITATION W50S9J-24-B-0007
Roof Replacement West Virginia, Air National Guard
Requests for Information - Questions and Answers
| RFI # |
| Date |
| Question |
| Answer |
| 1. |
| 6/18/2024 |
| Are the bid bonds required at 20% or $3M whichever is less? |
| Yes 20% of bid price |
| 2. |
| 6/27/2024 |
| Are vendors able to take core samples at the visit? |
| Yes but only on contractor and the results must be shared with other possible bidders. |
| 3. |
| 7/1/2024 |
| Would the government be willing to accept bids for alternate roofing systems (ie EPDM)? |
| Contractor shall install ethylene-propylene-diene-monomer (EDPM) roof membrane system per the project drawings and the roofing system Manufacturer’s specifications. |
| 4. |
| 7/1/2024 |
| Are there any skylights on the roof? |
| Yes, there are eight skylights. |
| 5. |
| 7/1/2024 |
| Is there a staging area close to the project (Building 109)? |
| Yes |
| 6. |
| 7/8/2024 |
| Does aluminum coping have to have a .080 thickness? What are the acceptable thicknesses? |
| Install new pre-finished at least 0.050” thick aluminum coping systems around entire parapet wall top. |
| 7. |
| 7/8/2024 |
| There are 12 skylights on the roof system, but only 8 are listed in the solicitation. Can you please identify the 8 that need to be replaced? |
| Remove and replace (12) Skylights, and install safety railing around the (12) skylights. |
| 8. |
| 7/8/2024 |
| Is it the intent of the solicitation that EPDM membrane be ran up and over the parapet walls or that they be terminated via a counterflashing where existing roof is terminated? |
Be terminated via a counterflashing where existing roof is terminated.
9.
10.
11.
12.
13.
14.
15.