QUESTIONS ANSWERS - 8.12.2026.pdf
PDF 128 KB Posted
- Solicitation number
- W50S9H26QA037
- Issued by
-
Department of the Army National Guard
About this file
This is a Questions and Answers document for federal contract W50S9H26QA037.
The document addresses a single inquiry regarding responsibility for electrical and compressed air installations associated with a lift project at Camp Douglas. According to the response, the installing vendor bears responsibility for relocating existing electrical and compressed air runs to accommodate the new lift. Both utilities are already present on-site and require only repositioning to fit the new lift specifications. The document was current as of 12 August 2026.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W50S9H26QA037 – QUESTIONS AND ANSWERS
Q1. Will Camp Douglas be responsible for electrical and compressed air runs to the lift?
A1. Installing vendor will be responsible for electrical and compressed air runs to the lift. Electrical and compressed air are already in place, they would just need moved to �it the new lift.
Current as of 12 August 2026