W50S9B-20-Q-0009, Classroom Conversion Questions and Answers

30 June 2020

Q.1: The government is calling for electrical and communication outlets alongside the walls.

The walls are to be sound dampening. Can the government provide clarity of the wall construction? Does the government require the use of surface mounted raceway and junction boxes to the walls?

A.1: Contractor to fur out the walls with dry wall; currently there is CMU block for the walls.

Raceway, junction boxes, and conduit to be between the dry wall and CMU block.

Q.2: What type of cable is required for Ethernet ports?

A.2: CAT 6 green wire.

Q.3: How many Ethernet ports does the government require per outlet?

A.3: Minimum two port per outlets; however, four per outlet is ideal.

Q.4: How many feet is there between the proposed classroom space to the Telecommunications Room?

A.4: 45 ft.

Q.5: At what height will the new drop ceiling be installed?

A.5: 10 ft.

Q.6: How many feet are between the floor and existing ceiling?

A.6: The current ceiling is at a slope with the lowest point at 14 ft. and highest 17 ft.