Text version

W50S9B-20-Q-0009, Classroom Conversion Post Site Visit Questions, Unanswered

2 July 2020

The following are the questions received in connection with the 1 July 2020 site visit. The numbering system used is a continuation from the Questions and Answers document dated 30 June 2020. Official answers to these questions are anticipated by 10 July 2020.

Concerning Statement of Work (SOW) 2.3, Demolition and Remaining Structure

Q7. Does the government want to save any of the items demolished/removed for future use?

Q8. After removal of the damper over the double doors how will the vent opening be addressed?

Q9. After demolition of the gas unit heater, will caping the existing roof pipe outside be acceptable?

Concerning SOW 2.4, Structural

Q10. Does the government want to have insulation between the block wall and the drywall for sound deadening?

Q11. If no insulation is required, how much air gap is required between wall and finished drywall?

Q12. Will current epoxy floor remain with no repair?

Q13. The bolts to be removed and filled, will the epoxy floor be repaired?

Q14. Please advise if the cabinet will be wall mount or floor mounted?

Q15. What will be the required cut out size for the double doors (window size)?

Q16. Will the blinds for the cut-out windows need to be built in to glass or will mounted to the door be acceptable?

Concerning SOW 2.5, Plumbing

Q17. What is the size of the new sink?

Q18. The plumbing for the proposed sink area is outside the new cabinet configuration. Will the plumbing be installed and connected on the outside of the new cabinet?

Concerning SOW 2.6, HVAC

Q19. Please advise how the mini split will tie into the existing HVAC System?

Q20. Where are the desired locations of the mini split interior and exterior equipment?

Q21. Will a concrete housekeeping pad need to be poured, or will lightweight pad be acceptable for the condensing unit?

Q22. Is a wall mount bracket for the exterior condensing unit acceptable?

Concerning SOW 2.7, Electrical

Q23. How many lighting zones are required to be dimmed?

Q24. Will there be a GFCI requirement for the sink area?

Concerning SOW 6.1, Drawings

Q25. The Conceptual Drawing shows an item next to the sink. Please advise as to what the item is?

Concerning Project Over All

Q26. Will a lay down area be provided for dumpster/material storage?

---------------------------------- End ----------------------------------