PSXE172003
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
REASON FOR AMENDMENT: Incorporate questions and answ ers
1. Questions and answ ers 1-27 are hereby incorporated in to this solicitation.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 24-Aug-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W50S9822B0002
X 9B. DATED (SEE ITEM 11)
15-Aug-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
24-Aug-2022
CODE
USPFO TN 134 MISSION SUPPORT CONTRACTING
123 BRISCOE DRIVE
MCGHEE TYSON ANG BASE TN 37777-6227
W50S98 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W50S9822B0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
QUESTIONS AND ANSWERS
PV Array Q&A
1. Please provide a slope stability analysis report if available.
A: A slope stability analysis is not currently available
2. If a slope stability analysis report is not available, please confirm subcontractor is not responsible for the completion of the analysis.
A: The current documents do not require the contractor to complete a slope stability analysis.
3. Add-Alternate PV system exceeds inverter manufacturer DC/AC ratio and max DC input. Please provide design information for the Add-Alternate PV system or confirm that an additional inverter would be required to not exceed manufacturer limits.
A: As noted in th alternate descriptions, provide the required items for a complete and fully working system
4. Please confirm that Aluminum conductors are allowed to be used in low voltage and medium voltage circuits.
A: See specification sections 26 0513 -MEDIUM-VOLTAGE CABLES and SECTION 26 0519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES, for types and use of cable materials
5. Please confirm copper conductors may be utilized instead of aluminum in electrical circuits.
A: See specification sections 26 0513 -MEDIUM-VOLTAGE CABLES and SECTION 26 0519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES, for types and use of cable materials
6. Please confirm the number of modules for the solar array system. E2.0 indicates 1824 modules while E2.1 indicates 792 modules.
A: Follow the module layout as indicated on sheet A2.1 for what is in base Bid (Subarray 1-4). In addition, alternate subarrays are identified in the Alternates descriptions.
7. Please confirm a revenue grade meter is optional.
A: The Optional Revenue Grade Meter, identified on Sheet E5.1, shall be provided as part of the project.
8. Please provide clarification if the 2000 A PV switchboard will still be required if the Add-Alternate PV system is not pursued.
A: Yes, the larger infrastructure is to remain to allow for expansion of the system in the future.
9. Please provide clarification on circuit ID A.1. DC circuit is not illustrated on E5.1 as indicated in the circuit schedule.
A: For clarification of circuit A1, refer to Detail I, Sheet E4.5
10. Please provide stamped issued for construction drawing set for the Add- Alternate PV system design to include stringing, inverter mounting, grounding, interconnection, etc.
A: As noted in each Alternate description, contractor to is responsible for and to provide all items for a fully operational system with the expanded subarrays as noted in each alternate. The Engineer will work with the contractor to verify specific details once final array size is determined based on awarded alternates.
11. What year version of the National Electrical Code must be followed for this project; the 2014, 2017 or the 2020 version?
A: The design shall conform to the 2020 version
12. Who is the Authority Having Jurisdiction (AHJ) over this property for code and permitting purposes?
A: This is a federal project. It is required per the contract documents,to follow all applicable and noted codes/criteria, there is no permitting or approval required.
13. Please provide the most current topographical survey of the potential solar array site.
A: See sheet C1.0
14. Please provide the most current underground utilities maps of the potential solar array site.
A: See sheet C1.0 for existing survey information and all utilities identified at the time of survey
15. Please provide the most current electrical systems maps of the potential solar array site.
A: See sheet C1.0 for existing survey information and all utilities identified at the time of survey
16. Please include a description and photographs of the physical equipment (if any) where the interconnection is to be connected at each of the potential solar array site.
A: ANG to determine if they want to allow contractors to open/inspect gear as part of prebid visits.
17. Is there any requirement for ground cover in the ground solar array such as geotextile fabric & crushed rock or planting grass? If so, what are the specific requirements?
A: Yes. 94,500 sf of Creeping Thyme is the base bid. Thymus praecox as shown on sheet C2.0
18. Are there any restrictions to changing grade or elevation in the ground solar array area?
A: Grade changes are not currently shown or anticipated to be required. However, if the contractor desires to change grade and can show benefit to the construction process, betterment of the final installation of the Array, and so as not to impact usefulness or cause harm to surrounding grade or facilities, the contractor could make those changes. Any change would be based on final approval by and coordination with the government.
19. Please confirm the modules, DAS and inverter makes/models that expected to be provided by the contractor as of this time.
A: See specification section 26-3100
20. What area can be used for a material and equipment laydown to include the storage of containers and vehicles?
A: Contractor staging area is shown on sheet C2.0. Proposed laydown and storage areas are available adjacent to the work site area in both the Grass and asphalt areas as designated by the COR.
21. Is a job trailer allowed? If so, where could it be located? What are the procedures to connect power to a job trailer?
A: Job trailers are allowed and can be located within the work site area. Power is available at the shelter by the project site entrance.
22. Will water be provided on site? If so, where can we get water?
A: Water is available for filling tanks but not for service to office trailers.
23. Will spoils be allowed to be disposed of on-site?
A: Spoils may NOT be disposed of on-site. Clean, debris free soil can be regraded into existing site. Contractor must plan for cleaning/sweeping streets if used for transport, erosion control and seeding must be accomplished per the drawings.
24. Please provide the snow, wind, and seismic load requirements.
A: Arrays and their supports shall be designed to resist the loading requirements of ASCE 7-16.
- The PV Array shall be considered to be in Risk Category II.
- Design wind speed shall be 105 mph. Exposure C shall be assumed.
- Ground snow load shall be 10 psf. Snow importance factor shall be 1.0.
- Seismic accelerations shall be Ss=0.902 and S1=0.161. Seismic site class D shall be assumed. Seismic Importance factor shall be 1.0.
25. What location will be able to be used for?
a. Dumpster location
b. Lay down area
A: See sheet C2.0. Proposed laydown and storage areas are available adjacent to the work site area in both the Grass and asphalt areas as designated by the COR. It is up to the contractor to locate their proposed dumpster and laydown areas within the work site area and coordinate with the COR.
26. Please provide electrical details and interconnection details for any and all sources of backup and emergency power generation that will be connected to the same electrical grid as the proposed system, to include any site-wide systems. If there are no sources of backup or emergency power generation, please confirm that there are none.
A: Connection details to the existing emergency power generation system are provided on the Electrical drawings as part of the bid documents. Any available system wide drawings will be proved to the successful bidder.
27. The solicitation states electronic bids are not accepted. Please confirm what address the hardcopy bids are to be mailed to.
A: 123 Briscoe Drive Louisville, TN 37777
(End of Summary of Changes)