QnA2.pdf
PDF 67 KB Posted
- Attached to
- Dining Hall & Gym Cleaning Services
- Solicitation number
- W50S9624QA011
- Issued by
-
Department of the Army National Guard
About this file
This document contains a federal contract opportunity solicitation for janitorial services at a South Dakota Air National Guard dining hall and gym. The solicitation seeks a contractor to provide non-personal cleaning services for the 114th Fighter Wing dining hall and base gym in Sioux Falls, South Dakota. Services include cleaning facilities, equipment, and utensils as well as handling supplies. The dining hall services are required up to 12 weekends per year, normally on drill weekends from Saturday through Sunday. Gym cleaning services are required twice per week on mutually agreed upon days and times. The contract period of performance is one base year with four optional one-year periods. Quotes are due by January 30, 2024 and the award will be made based on past performance and price. The solicitation is set aside exclusively for small businesses with a $22 million size standard.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Quote Sheet v2.xlsx | XLSX spreadsheet | |
| QnA1.pdf | ||
| Site Visit Notes and Attendance.pdf | ||
| Revised PWS.pdf | ||
| B.08 W50S9624QA011 Attachment 1 - PWS-Dining Hall & Gym Cleaning.pdf | ||
| B.08 W50S9624QA011 Attachment 2 - Quote Sheet-Dining Hall & Gym Cleaning.xlsx | XLSX spreadsheet | |
| B.08 W50S9624QA011 Attachment 3 - Wage Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W50S9624QA011 – Dining Hall & Gym Cleaning Services Question and Answer
Amendment 2 – 26 January 2024
Question 0022: Since QnA1 clarified the gym cleaning requirement is only one day per week, will the gym be closed during cleaning? If so, for how long?
Response 0022: There will be a notice on the door to alert patrons that the gym is closed for cleaning. If patrons try to use the gym during these times and it becomes a problem we will address it further. If the problem persists we will consider locking the door during the cleaning time.
Question 0023: Will there be air fryers that need cleaning?
Response 0023: There are no air fryers to clean. Also, contractor employees will not be expected to clean the deep fryers.
Question 0024: Regarding 5.1.4 Equipment Cleaning - interior walls, floors and ceiling will be cleaned daily.
Can you explain the ceiling cleaning? Will there be equipment provided for the contractor to reach the ceiling?
How high is the ceiling?
Response 0024: The ceiling does not normally require cleaning. If it should require cleaning for some reason i.e., something splatters on it, then a tall folding ladder will be provided. The ceiling height is 10’.
Question 0025: Did the last contract end because services were no longer needed?
Response 0025: The previous contractor struggled to provide satisfactory service due to apparent staffing issues. This resulted in the contract being terminated for convenience by the Government.
Question 0026: Is there any other information not listed in the PWS from the site visit that is pertinent for others subs who missed the visit to know?
Response 0026: Please see Site Visit Notes posted with Amendment 0001.
End of Amendment 2 Q&A.