Industry Questions.docx
DOCX document 14 KB Posted
- Attached to
- Multi-Integration Audiovisual System Bldg 16 PRANG Federal contract opportunity
- Solicitation number
- W50S93-20-B-5009
- Issued by
- Department of the Army National Guard
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Scope of Work - Bldg 16 FSS Multi-Integration Audiovisual Systems (Final Update 19 June2020).docx | DOCX document | |
| W50S93-20-B-5009 Amendent 0001 Combo - Solicitation Multi-Integrator Audiovisual System Bldg 16.docx | DOCX document | |
| Bldg 16 Drawings for Multi-Integration System W50S9320B5009.pdf | ||
| Scope of Work - Bldg 16 FSS Multi-Integration Audiovisual Systems v2 (Updated 03June2020).docx | DOCX document | |
| DD 369_POPLICE_RECORD_CHECK.pdf | ||
| W50S93-20-B-5009 Combo - Solicitation Multi-Integrator Audiovisual System Bldg 16.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Multi-Integration System Building 16 Questions and Answers
1. Size of the three projection screens?
7’ height x 12’ wide
1. Conceptual integration drawing of the equipment as requested. In order to understand the audiovisual operation logistics expected.
Not available. Per discussion conducted during site visit, vendors can provide own recommendation based on customers requirement.
1. Location of main equipment rack Multipurpose Dinning (room 157) or Telecomm (room 173)- Location will be Room 157, Multipurpose Dining room.
1. Define part 9 of item 3. “The contractor will:” on the Scope of Work (SOW) Stand alone audiovisual control console (smart hub) to be store in a secure cabinet.- See updated Scope of Work (SOW) for clarification.
1. On part 8 of item 3 states a specific quantity of speakers does it need to be that or is it open for recommendation?
It is just a recommendation. We are open to suggestions and proposals. See updated Scope of Work.
1. The wireless microphones will require antennas that are not listed and will be included in the proposal- We will accept proposals with suggestions to improve the operation of the system. Any required configuration for system operation should be provide by the vendor.
1. On part 4 of item 3 what do you mean by required software for the Smart TV?
In case that any software is needed to operate the Smart TVs; then, vendor should include them. However, please see the updated Scope of Work (SOW).